Appendix C - Stormwater Management Plan
Attached to the e-mail MCU15/0095 & REC15/0022 Development Application Stormwater Mgmt Plan (2 of 3).
Original PDF page 49, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn SPEL Automatic Alarm/Monitoring System
Control unit (electrical connections) Probe
1. Mains voltage connection; The probe is installed freely suspended in the SPEL separator within the probe
The control unit should be connected to a suitable protection tube. The 3-core cable is connected into the junction box mounted in
220/240V AC supply and fused at 3 amps. the access shaft above the probe protection tube. Extra cable is provided to enable
raising the junction box where extension shafts are incorporated.
Note: This appliance must be earthed.
Important note: In all cases good, standard electrical practice should be followed
2. Control unit/probe junction box connection and the installation must conform to the Australian Wiring Rules – AS 3000 – 2007.
Wiring from the control unit to the probe junction box In essence, the installation must be such that the intrinsic safety is
in the separator chamber requires a 3-core screened. no compromised by:
0.75mm core section cable.
• Exposure to risk of mechanical damage
Maximum cable length: 300 metres.
• Unauthorised modification of interference
3. Probe connection
• Exposure to moisture, dust and foreign bodies
A 5 metre 3-core probe cable is normally fitted to the
junction box and the probe. • Excessive heat
After all connections have been made, the cables must • Invasion of intrinsically safe circuit by other electrical equipment or circuitry
be secured by tightening each entry gland.
Certificate of conformity
The alarm device has been approved to be used in explosion-hazardous areas. The
control unit and probe are approved according to ATEX Directive 94/9/EC. These
approvals mean that the probes can be installed in Zone 0, which is continuously
explosion-hazardous.
The SPEL oilset control unit must be located in the safe area, but it can be
connected to the probe without any barrier.
Tests (10.2)
The function can be tested by lifting the probe within the probe protection tube. In
approximately 5 seconds, the alarm is given by a red light and audible signal. Both
relays release. Push the RESET button - the buzzer goes off and relay pulls in.
When the probe is placed in water again, relay pulls in and the red light goes off.
Cable break and short circuit test
Also the function can be tested in case of cable fault or short circuit. First cause
short circuit in probe cable terminals 1 and 2. Then the yellow light of short circuit
is lit. Both the relays pick up and the buzzer goes on. Remove the short circuit and
reset the buzzer.
Simulated Function Test
The function of probe, cable and electronics can be tested. Push the TEST button for
2 to 5 seconds. Both relays pick up, and the red light is lit. When the TEST button is
released, the red light goes off and relay returns to its normal position. The buzzer
and relay must be reset.
Installation
Important note: It is important that installation is carried out by a competent
technician familiar with this type of equipment or contact our Special Products
Division for installation, commissioning and maintenance service.
7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.