Council archive · source document
RFI - Attachment 7- Site Based Stormwater Management Plan · RAL18/0023
Plans and drawings: the text below has words only, no drawings.
4.3.6 MUSIC Model Results
Figure 4.10 shows the MUSIC model treatment train layout and results from the proposed
stormwater quality improvement devices (SQIDs), which is also shown on drawings
1856/SW01-SW05 in Appendix A. The results as shown below were generated using the
stochastic option as per the guidelines.
Figure 4.10 MUSIC Model Results
All load-based pollutant reduction efficiencies are met in accordance with the Table A in
Appendix 2: Stormwater Management Design Objectives, Part G, SPP (2017) included in
Appendix B.
Site Based Stormwater Management Plan Page 16 of 20
1856-SBSMP-01_Version 2.0 (April 2019)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - Attachment 7- Site Based Stormwater Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.