             10 Surfside Court – Construction Management Plan
Initial steps for the proposed work will be to erect barricade fencing to either side of the
site access opening as per attached areal photo markups. It was observed by the
builder when on site conducting preliminary site meetings etc over the course of one
week, that all pedestrian tra ic accessing the boardwalk at the end of Surfside Court,
used the pedestrian footpath on the Eastern side of the cul-de-sac without exception,
as it’s a more direct line of access. Therefore, pedestrian access will not be restricted or
impacted by the works.

The access driveway adjacent to the site is to a vacant block with no activity on the lot.
The owner of the block, Joanne Thompson, has given permission to the owner of
number 10 to use her block for access. This will provide additional o -street parking of
trade vehicles when required. The home at number 10 will be vacant during the works
and that driveway will provide o street parking, loading and unloading of trucks etc.

Once the dilapidated front boundary wall to the site is removed, all site access will be
through that point and contained within the property frontage and inside the safety
barricades. All materials, plant and equipment will be stored on site inside the property
boundaries.

The finished height of the proposed retaining wall at the sewer maintenance hole will be
no higher than the existing concrete terrace. The line of the step-back of the wall around
the maintenance hole will be approximately the same line as the existing concrete
terrace. Therefore, the accessibility of the maintenance hole has not been impacted.
The clearances around the maintenance hole were approved by Unity Water through
that part of the application process. The proposed works does not require the
excavation or unearthing of the Unity Water asset therefore it will not be impacted.
Accurate electronic pipe location will determine the exact depth and location of the
sewer line prior to commencement.

All street cleaning and care protocols will be followed throughout the construction
process.




                                    NOOSA COUNCIL
                                 REFERENCE DOCUMENT
                                 OPW25/0053 30 MAY 2025
Log in to download the original file

Compiled Reference Documents - OPW25_0053 (As Published).pdf · 4.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.