7.2.3 Downstream Drainage Report
Refer to the attached Flood and Tide Maps, sourced from Council’s Online Mapping Portal
and attached as Appendix D.
The existing Weyba Creek Tributary discharges to Council stormwater infrastructure in
Halse Lane. A concrete lined channel conveys stormwater runoff 200m west towards the
tidal waterway Weyba Creek. Under existing conditions, this drainage network has
adequate capacity to convey minor 39% & 10% AEP) storm events. During major events
(1% AEP) this stormwater infrastructure is influenced by tailwater conditions within
Weyba Creek. Tidal Surge Levels generally exceed 1% AEP Flood Levels within the lower
reaches of the focus catchment.
7.2.4 Peak Flow Management
As indicated above, no detention measures are proposed for the site on the following
grounds;
- The increase to stormwater discharge (0.3%) is minor when considered as part
of the overall contributing catchment.
- The subject site is located at the lower end of a larger catchment. Providing
detention measures onsite would increase the likelihood of peak discharge from
the subject site coinciding with peak event runoff from upstream external
catchments.
- Stormwater runoff is directed to an existing flow path. Increases to flow depth
(1mm) are minor and will not cause an actionable nuisance to downstream
property owners.
- The eventual discharge point in Halse Lane is affected by tailwater levels within
the tidal waterway, Weyba Creek. Onsite detention measures are considered
redundant when discharging to stormwater networks affected by storm surge or
tidal prisms.
11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Info Request - Attachment 4a - Engineering Report Part 1 MCU18-0015 & RAL18-0001.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.