               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Development Planner, Cameron Smith
                                       Development Assessment



                  APPLICATION DETAILS

                  Application No.                  MCU25/0054
                                                   OPW25/0077

                  Applicant                        20 Williams St Developments Pty Ltd
                                                   C/- Pivotal Perspective

                  Proposal                         Material Change of Use - Multiple Dwelling (3 units) and
                                                   Demolition Works;
                                                   Operational Works – Drainage Work, Stormwater & Earthworks.

                  Properly Made Date               17 June 2025

                  Further Advice Date              24 July 2025

                  Further Advice Response 6 August 2025
                  Date

                  Decision Due Date                27 August 2025

                  Report Reviewed By               Nadine Gorton 27.08.2025


                  PROPERTY DETAILS

                  Property Address                 20 William St Noosaville

                  RP Description                   Lot 3 RP 63813

                  Land Area                        551m²

                  Existing Use of Land             Dwelling House


                  STATUTORY DETAILS

                  SEQRP Designation                Urban Footprint

                  Zone                             High Density Residential

                  Precinct                         Not applicable

                  Local Plan Area                  Noosaville

                  Overlays                         Flood Hazard Overlay

                  Assessment Type                  Code




Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025
Full text of the other 20 pages

Page 2

               RECOMMENDATION
               With regard to Application No. MCU25/0054 & OPW25/0077 for a Material Change of Use - Multiple
               Dwelling (3 units) including Demolition Works & Operational Works – Drainage Work, Stormwater
               & Earthworks, situated at 20 William St Noosaville and described as Lot 3 RP 63813, it is
               recommended the application be approved in accordance with the following details for the Decision
               Notice:
               1.      APPLICATION DETAILS

                   Application No:                  MCU25/0054 & OPW25/0077

                   Street address:                  20 William St Noosaville

                   Real property description:       Lot 3 RP 63813

                   Planning Scheme:                 Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for a Material Change of Use - Multiple Dwelling (3 units) including
                       Demolition Works; and
               •       Development Permit for Operational Works – Drainage Work, Stormwater & Earthworks.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                           DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE (MCU25/0054)
                               MULTIPLE DWELLING (3 UNITS) INCLUDING DEMOLITION WORKS
                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use commencing, and then compliance maintained at all times while the use continues.
                       Currency Period
               2.      This development approval lapses if the use has not happened by 27 August 2031, unless
                       an application to extend the currency period is approved by Council.
                       Approved Plans
               3.      Development authorised by this approval must be undertaken generally in accordance with
                       the Approved Plans listed in the table below.

                          Plan No.              Rev.      Plan/Document Name                          Date

                          00461-OW1.1           .         Site Survey & Existing Services (Demolition April 25
                                                          Plan)
                                                          Prepared by SCG Consulting
                                                          Annotated by Council

                          05                    DA05 Conceptual plan – Basement                       1/8/2025
                                                          Prepared by Skale Building Design



                                                                                                         Page 2 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 3

                         06                DA05 Conceptual plan – Ground Floor                  1/8/2025
                                                   Prepared by Skale Building Design

                         07                DA05 Conceptual plan – First Floor                   1/8/2025
                                                   Prepared by Skale Building Design

                         08                DA05 Conceptual plan – Second Floor                  1/8/2025
                                                   Prepared by Skale Building Design

                         10                DA05 Western Elevation                               1/8/2025
                                                   Prepared by Skale Building Design

                         11                DA05 Southern Elevation                              1/8/2025
                                                   Prepared by Skale Building Design

                         12                DA05 Eastern Elevation                               1/8/2025
                                                   Prepared by Skale Building Design

                         13                DA05 Northern Elevation                              1/8/2025
                                                   Prepared by Skale Building Design

                         14                DA05 Northern fence elevation                        1/8/2025
                                                   Prepared by Skale Building Design

                         15                DA05 Southern fence elevation                        1/8/2025
                                                   Prepared by Skale Building Design

                         16                DA05 Eastern fence elevation                         1/8/2025
                                                   Prepared by Skale Building Design

                         17                DA05 Street fence elevation                          1/8/2025
                                                   Prepared by Skale Building Design

                         18                DA05 Section A                                       1/8/2025
                                                   Prepared by Skale Building Design

                      Building Height
               4.     The maximum height of the development must not exceed 12 metres above the ground level
                      including where excavation is undertaken the exposed portion of the external façade of the
                      building.
               5.     The ground level must be reinstated around the basement level to ensure no part of which is
                      more than 1 metre above ground level, apart from the driveway entrance.
               6.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that the building does not exceed the maximum height requirement of this Decision
                      Notice.




                                                                                                   Page 3 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 4

                      Performance Bond
               7.     Security in the form of a cash bond or trading bank guarantee to the sum of $25,000 must
                      be submitted to Council, to secure performance of all conditions of this approval, prior to pre-
                      start meeting. The cash bond or trading bank guarantee will be returned on performance of
                      the conditions of approval less any costs incurred by Council in respect of enforcing
                      performance of this permit. Council reserves the right to call upon the bond or guaranteed
                      sum to effect compliance with conditions.
                      Water & Sewer Connections
               8.     An underground connection to reticulated water and sewerage must be provided to the
                      premises in accordance with the standards and requirements of Northern SEQ Distributor–
                      Retailer Authority (Unitywater).
               9.     A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the premises.
                      Building Appearance
               10.    External design features, materials and finishes must be as shown on the Approved Plans,
                      with no inclusions or alterations made without approval in writing by Council.
               11.    External finishes of the building must be a mix of lightweight and textured external finishes,
                      with masonry areas incorporating a variety of textured finishes to break up the surface.
               12.    All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or
                      the like thus remaining as open structures, except where required to satisfy any privacy
                      condition of this Decision Notice.
               13.    All balustrades to decks and balcony areas must be open or transparent except where
                      conditioned to provide protection of privacy.
               14.    External colours and finishes must be of an understated colour scheme and low-reflective
                      roofing and cladding materials.
               15.    All air conditioning units or other mechanical equipment must be fully enclosed or screened
                      such that they are not visible from the street frontages nor adjoining properties.
               16.    Waste storage areas, clothes drying areas and external storage areas must be screened
                      from view of the street.
                      Fencing and Walls
               17.    Any street fencing must not exceed 1.8 metres in height, be set back an average of 1 metre
                      and articulated to provide visual interest by stepping the design. Any fencing on the front
                      boundary must either:
                      a.      not exceed a maximum height of 1.2 metres
                      b.      be of open construction.
               18.    The area of land between the fence and the front property boundary must be densely
                      landscaped to screen any fencing from the street as indicated on the approved plans.
                      Protection of Privacy
               19.    The external spiral staircase located on the rear third storey projection of Unit 2 must include
                      either balustrading or fixed external screens, positioned in such a way to obscure direct views
                      into the private open space areas of the adjoining property to the rear. Any screening
                      measures must be a minimum height or 1.7 metres above floor/stair level.




                                                                                                        Page 4 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 5

                      Site Access and Driveways
               20.    A sealed access driveway must be provided from William Street to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      the conditions of this approval, be generally in accordance with SCG Consulting’s
                      Operational Works Driveway & Access Plan (00461-OW4.1) and Operational Works
                      Driveway Details (00461-OW4.2) dated April 2025 and must include in particular:
                      a.      A driveway crossover in accordance with Council standard drawings RS-049 and RS-
                              050 and any associated addendum.
                      Car Parking
               21.    A minimum of 6 car parking spaces must be provided and marked on the site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      1 visitor parking spaces within the total, which are clearly marked for that purpose and
                              accessible at all times for visitor use;
                      b.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities
                      Stormwater Drainage
               22.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with the conditions of this approval
                      and be generally in accordance with SCG Consulting’s Operational Works Stormwater
                      Management Plan Basement Level (00461-SW1.1) and Operational Works Stormwater
                      Management Plan Ground Level (00461-SW1.2) dated April 2025.
                      Services
               23.    Reticulated electricity and telecommunication services must be provided to each lot/unit in
                      accordance with an approval for Operational Works and the standards and requirements of
                      the relevant service provider.
               24.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               25.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Earthworks and Retaining Walls
               26.    All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be undertaken in accordance with the conditions of this
                      approval, be generally in accordance with SCG Consulting’s Operational Works Earthworks
                      Plan (00461-OW3.1) , Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) and
                      Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) dated April 2025 and
                      contained entirely within the subject site unless written permission from the respective
                      landowner(s) is provided to Council.
               27.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Acid Sulfate Soils
               28.    All works must be carried out in accordance with updated site-specific Acid Sulfate Soil,
                      Groundwater and Dewatering Management Plans.
                      *(Refer to Advisory Note)

                                                                                                        Page 5 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 6

               29.    All waters, including stormwater runoff, groundwater seepage and leachate from acid sulfate
                      soils must achieve the following quality prior to release from the site:
                      a.      a pH range of 6.5-8.5 pH units
                      b.      50mg/L maximum total suspended solids concentration
                      c.      0.3mg/L maximum total iron concentration
                      d.      0.2mg/L maximum total aluminium concentration
                      e.      no visible plume at either the point of release from the site or within a waterway
               30.    The basement must be designed and constructed as a water excluding structure in
                      accordance with Australian Standard AS3735 “Concrete Structures for Retaining Liquids” to
                      ensure groundwater does not enter the basement after construction is completed.
               31.    All treated material must undergo verification testing at the rate of one sample per 250 m3
                      throughout the duration of the excavation phase of the development. The verification testing
                      must be undertaken by a qualified person* using the SPOCAS or Chromium Reducible
                      Sulphur testing suite, and the results must be submitted to Council for appraisal.
                      Damage to Services and Assets
               32.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      Landscaping Works
               33.    The development site must be landscaped. The works must be undertaken in accordance
                      with the PSP 2 - Landscape and the Noosa Plan 2020 for that specific area and must include
                      in particular:
                      a.      the works shown on the Approved Plans
                      b.      vegetated screening of any electrical transformers, bin storage areas and the like from
                              the road frontage
               34.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
                      Retention of Existing Trees
               35.    Existing trees in the road reserve must be retained in accordance with an Arborist Report (or
                      part thereof) prepared by a qualified person* and endorsed through an Operational Works
                      approval.
                      *(Refer to Advisory Note)
               36.    All planting areas on the eaves must be planted and maintained at all times, with replacement
                      planting undertaken promptly where plants fail or do not have a healthy and vigorous growth.
                      Waste Management
               37.    A waste storage area must be designed and maintained in accordance with Planning
                      Scheme Policy PSP9 Waste Management and the Noosa Plan’s Waste Management Code.
                      The waste storage area must be:
                      a.      imperviously paved and correctly sized for all refuse and recycling containers;

                                                                                                         Page 6 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 7

                      b.      bunded and graded so that wastewater and bin leakage drain to the sewer;
                      c.      provided with a conveniently located hosecock and backflow prevention device,
                              connected to a water supply to service the area; and
                      d.      roofed or otherwise covered.
                      Community Management Statement
               38.    Any proposed Community Management Statement required for the development pursuant to
                      the Body Corporate and Community Management Act 1997 must be submitted to Council for
                      endorsement at the same time as submission of the Building Format Plan (or similar) to
                      Council for compliance assessment.
               39.    All clauses and by-laws of the proposed Community Management Statement must accord
                      with the requirements of this Decision Notice.
               40.    Where titles are created for the units, unit 3 must be contained on a separate lot and must
                      be provided with separate services. Unit 3 must not be consolidated with any other unit
                      without the prior written consent of Council.


                      DEMOLITION WORK
                      Codes of Development
               41.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               42.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               43.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               44.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               45.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.
                      Water Quality and Drainage
               46.    Erosion and sediment control is to be undertaken in accordance with the requirements of the
                      Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
                      maintained until soils are stabilised by vegetation or sealed.
                      NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).
                      Health and Safety
               47.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.



                                                                                                      Page 7 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 8

               48.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               49.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               50.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      General
               51.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               52.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
                      Plumbing and Drainage
               53.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.




                                                                                                      Page 8 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 9

                              DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW25/0077)
                                       (DRAINAGE WORK, STORMWATER & EARTHWORKS)
                      Approved Plans
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.           Rev.   Plan/Document Name                           Date

                         00461-OW3.1        N.A    Earthworks Plan                              April 25
                                                   Prepared by SCG Consulting

                         00461-OW3.2        N.A    Earthworks Sections Sheet 1                  April 25
                                                   Prepared by SCG Consulting

                         00461-OW3.3        N.A    Earthworks Sections Sheet 2                  April 25
                                                   Prepared by SCG Consulting

                         00461-OW4.1        N.A    Driveway & Access Plan                       April 25
                                                   Prepared by SCG Consulting

                         00461-OW4.2        N.A    Driveway Details                             April 25
                                                   Prepared by SCG Consulting

                         00461-SW1.1        N.A    Stormwater Management Plan Basement April 25
                                                   Level
                                                   Prepared by SCG Consulting

                         00461-SW1.2        N.A    Stormwater Management Plan Ground April 25
                                                   Level
                                                   Prepared by SCG Consulting

                         24                 DA05 Landscape Ground                               1.08.2025
                                                   Prepared by Skale Building Design

                         25                 DA05 Landscape First                                1.08.2025
                                                   Prepared by Skale Building Design

                         26                 DA05 Landscape Second                               1.08.2025
                                                   Prepared by Skale Building Design

                         27                 DA05 Landscape species                              1.08.2025
                                                   Prepared by Skale Building Design

                         28                 DA05 Tree Planting Detail                           1.08.2025
                                                   Prepared by Skale Building Design

                      The following documents require amendment.



                                                                                                   Page 9 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 10

                           Plan o.                  Rev.        Plan/Document Name                       Date

                           PTG/02023 – 0001         1           Interim Geotechnical Investigation 28           April
                                                                Report – Proposed Residential 2025
                                                                Development
                                                                Prepared by PTG Consulting

                           ADG1808.25               0           Dewatering Management Plan               May 2025
                                                                Prepared by ADG Consulting

                           Amendments               Further acid sulphate soil investigations are required. An
                                                    updated Geotechnical Investigation Report is required including
                                                    an acid sulphate soils management plan. An updated
                                                    Dewatering Management Plan is required addressing the
                                                    management of acid sulphate soils and noise pollution.

                           23                       DA05        Landscape Trees, prepared by Skale       1.08.2025

                           Amendments               The above plans must be submitted to Council for agreement
                                                    prior to a prestart meeting and incorporate the following:
                                                           a.   Updated landscape plans that include Acronychia
                                                                imperforate planted along the entire north east and
                                                                south east boundary.
                                                           b.   Updated landscape plans that include substantial
                                                                screening shrubs along the entire southeastern
                                                                boundary where adjacent to the driveway that includes
                                                                a mixture of the following:
                                                                 i.    Syzygium ‘Straight and Narrow’
                                                                 i.    Callistemon viminalis ‘Slim’
                                                           c.    Landscape capable of screening the private open
                                                                 space of the studio from the neighbouring property.


               CURRENCY PERIOD
                      Currency Period
               2.     The Currency Period for this development approval lapses if the use has not substantially
                      started by 27 August 2031, unless an application to extend the currency period is approved
                      by Council.
                      Site Specific Conditions
               3.     A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
                      Bonds must:
                      a.        meet the requirements of Council’s relevant Planning Scheme Policy for performance
                                and uncompleted works.
                      b.        be calculated using a schedule of works and relevant bond equation.
                                                                                                        Page 10 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 11

                      c.      Include GST
                      d.      have approval of the bond calculations and amount from Council prior to lodgement
                      e.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      f.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               4.     Submit amended plans to Council as described in the List of plans requiring amendments.
                      Plans must be submitted and approved prior to the pre-start meeting.
               5.     All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               6.     Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
                      Construction at the “pre start” meeting.
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Erosion and sediment control works;
                      d.      Other relevant parties
               10.    A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      Traffic management during all phases of construction;
                      b.      Adequate parking arrangements for works and deliveries;
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      d.      provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased.
               11.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               12.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               13.    Prior to requesting a prestart meeting:
                      a.      Receipt and approval of an arborist report required as part of the higher order approval
                              MCU25/0054.
                      b.      Receipt of amended plans for approval.



                                                                                                       Page 11 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 12

                      c.      Tree protection fencing must be installed under the supervision of the qualified person*.
                              (Refer to Advisory Note)
                      *(Refer to Advisory Note)
               DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice
                      b.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines
                      c.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site
                      Works within Road Reserve/Reinstatement
               17.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               18.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               19.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Site Access and Driveways
               20.    Driveway crossovers must be constructed generally in accordance with council’s Standard
                      Drawings RS-049 and RS-050 and any associated addendum.
               21.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               22.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete.
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties.


                                                                                                       Page 12 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 13

                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      d.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path.
                      e.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               23.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
                      the Plan of Survey.
               24.    All earthworks and associated batters/retaining structures, both above and below ground
                      level, both temporary and permanent, must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
               25.    Fall protection must be provided to retaining walls that are over 1m high and located.
               26.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies
                      b.      1 in 4 for grassed areas.
                      c.      1 in 3 for planted areas.
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               27.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               28.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (eg by blocking or interfering with natural overland flows).
               29.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
               30.    Prior to the completion of the development, all site surfaces must be effectively stabilised
                      using methods which have achieved effective short-term stabilisation and which will continue
                      to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes).
                      For the purpose of this condition, an effectively stabilised surface is defined as one that does
                      not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
                      or lead to sedimentation, or lead to water contamination.
                      Erosion and Sediment Control
               31.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.




                                                                                                            Page 13 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 14

               32.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               33.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               34.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               35.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
               36.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term. For the
                      purpose of this condition, an effectively stabilised surface is defined as one that does not, or
                      is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
                      lead to sedimentation, or lead to water contamination.
                      Damage to Services and Assets
               37.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      Retention of Existing Trees and Vegetation
               38.    All trees and vegetation identified for retention must be protected in accordance with AS
                      4970, Protection of trees on development sites.
               39.    A qualified person * must be engaged for the duration of the works to:
                      a.      Ensure works are carried out in accordance with the approved Arborist Report

                                                                                                        Page 14 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 15

                      b.      Oversee installation of all tree protection fencing prior to commencement of any works
                              onsite (including any clearing).
                      c.      Supervise tree protection within the council road reserve, and neighbouring properties
                              prior to, during and following construction in accordance with AS 4970, Protection of
                              trees on development sites.
                      d.      Oversee approved tree removal in proximity to retained trees.
                      e.      Undertake a risk assessment of all trees within striking distance of the development
                              works and site and carry out hazard removal and amenity pruning in accordance with
                              AS 4373, Pruning of amenity trees.
                      *(Refer to Advisory Note)
                      Vegetation Clearing
               40.    Removal of trees and vegetation must be undertaken by a qualified person* and must
                      include:
                      a.      No damage to vegetation for retention.
                      b.      Legal disposal of all removed vegetation and debris.

                      Fauna Management
               41.    Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
                      etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
                      has left vegetation or has been relocated by a qualified fauna spotter catcher.
                      *(Refer to Advisory Note)
                      Landscaping Works
               42.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice.
                      (* Refer to Advisory Note)
               43.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.
               44.    Street trees must:
                      a.      Meet AS2303 Tree stock for landscape use.
                      b.      Be located in accordance with engineering requirements for safe vehicle and
                              pedestrian sight lines.
               FOLLOWING CONSTRUCTION
                      Certification
               45.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               46.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
                      Supervision/Certification
               47.    Prior to commencement of use the following (prepared by respective qualified persons* and
                      certifying compliance with approvals) must be submitted to Council:
                      a.      Landscaping certification confirming all works have been constructed in accordance
                              with conditions of approval.


                                                                                                        Page 15 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 16

                      (* Refer to Advisory Note)
               5.     REFERENCE DOCUMENTS

                Plan No.               Rev.   Plan/Document Name                                         Date

                -                      -      -                                                          -

               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               PLANNING
                      Equitable Access and Facilities
               1.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Development Compliance Inspection
               2.     Prior to the commencement of the use, please contact Council's Development Assessment
                      Branch to arrange a Development Compliance Inspection.
                      Nature and Extent of Approved Development
               3.     The assessment of this development was based on a proposal for a Multiple Dwelling (as
                      defined in the Noosa Plan 2020) with three units, as indicated on the Approved Plans.
                      Resubmission of Amended Plans Required
               4.     The conditions of this Decision Notice require resubmission of plans to Council with
                      amendments. Please address the amended plan/s to Council’s Development Assessment
                      Branch with the Reference No. MCU25/0054, separate to any Operational Works application.
                      To avoid delays and assessment issues with the Operational Works application, it is
                      recommended the plan/s be resubmitted prior to lodgement of any Operational Works
                      application. However, should the plans not be submitted, the applicant is advised that a
                      Preliminary Approval may be issued in lieu of a Development Permit.
                      Infrastructure Charges
               5.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue.
                      Qualified Person
               6.     For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                      for the development, a qualified person is considered to be a person who:
                      a.      is a Registered Professional Engineer of Queensland (RPEQ); and
                      b.      has a degree in civil engineering or engineering geology; and

                                                                                                             Page 16 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 17

                      c.      has a minimum of 5 years experience in the field of geotechnical engineering or
                              engineering geology.
                      Sustainability
               7.     Council encourages sustainable and energy efficient building design for all development,
                      including the use of sustainable building materials, energy efficient fittings, solar hot water,
                      photovoltaic systems (including the use of inverter/charges), solar panels, water saving
                      devices and rainwater harvesting.
                      Performance Bond
               8.     Where the works include Council assets (construction of new or modifications to existing) a
                      portion of the performance bond will be retained as a “maintenance bond” as described in
                      Council’s Planning Scheme Policy 6 Engineering Design Standards. Alternatively, the
                      developer may submit a separate “maintenance bond” at the completion of the works.
                      The bond amount will be:
                      a.      5% of the agreed value of the works or
                      b.      $1500, whichever is the greater amount
                      Fires in Urban Areas
               9.     In urban areas fires are prohibited except where in an appliance is used for domestic heating
                      or cooking purposes, which must comply with particular standards. Any area identified as a
                      fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
                      Law No. 3, Schedule 3. Refer to the following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview

               DEMOLITION WORKS
               10.    Please be advised that the building work, in accordance with section 71 of the Building Act
                      1975, must substantially start within 2 months and must be completed within 1 year after the
                      issue of the building development approval.
               11.    Where required, a temporary crossing must be provided to protect road reserve infrastructure
                      including kerb and channel.
               12.    NOTE: A Road and Footpath permit may be required prior to the commencement of work.
                      For further information, please contact Council’s Customer Service on 5329 6500.
               13.    Any damage to footpaths. Street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
               14.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2018 and the Environmental Protection
                      Regulation 2019.
               15.    NOTE: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
               16.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.




                                                                                                      Page 17 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 18

               17.    The ‘Plumbing and Drainage Regulation 2019’ states that at demolition or removal of a
                      building requires the existing sanitary drain upstream from the connection point for a service
                      provider’s sewerage system must be sealed water tight. This work is deemed as Notifiable
                      Work and must be carried out by a suitably licenced plumber who shall submit an As
                      Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               18.    The ‘Plumbing and Drainage Regulation 2019’ states work necessary for installing, replacing
                      or removing a testable backflow prevention device is included work for Notifiable Work.
                      Removal must be carried out by a suitably licenced plumber who shall submit a Form 9
                      (Registration & Report on Inspection and Testing of Backflow Prevention Devices) and Form
                      4 (Notifiable Works Form) to the QBCC (Queensland Building Construction Commission)
                      within 10 days of completing the work. Notification to Council once works and document
                      submission is complete allows removal of backflow prevention devices from Council’s
                      backflow register.
               19.    All activities associated with the removal or demolition must be contained within the property
                      boundaries at all times with site gateways opening inwards and at approved locations only.
                      If the works cannot be contained within the site, a road and footpath permit must be applied
                      for.

               OPERATIONAL WORKS
                      Building and Construction Industry (Portable Long Service Leave) Levy
               20.    The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Resubmission of Amended Documents Required
               21.    The conditions of this Decision Notice require resubmission of the referenced Geotechnical
                      Investigation Report Prepared by PTG Consulting Rev 1 dated 28 April 2025 and Dewatering
                      Management Plan Prepared by ADG Consulting Rev 0 to Council with amendments. Please
                      address the amended documents to Council’s Development Assessment Branch with the
                      Reference No. MCU25/0054 & OPW25/0077.
                      Qualified Person
               22.    For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                      for the development, a qualified person is considered to be a person who:
                      a.      is a Registered Professional Engineer of Queensland (RPEQ); and
                      b.      has a degree in civil engineering or engineering geology; and
                      c.      has a minimum of 5 years experience in the field of geotechnical engineering or
                              engineering geology.
               23.    For the purpose of preparing an Acid Sulfate Soil and Groundwater Management Plan, a
                      qualified person is considered to be either:
                      a.      a Registered Professional Engineer of Queensland (RPEQ); or
                      b.      a soil scientist with a minimum of 5 years experience in the field of acid sulfate soils.
                      General Advisory Notes
               24.    Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.



                                                                                                         Page 18 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 19

               25.    Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               26.    Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               27.    Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
               28.    If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               29.    A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Environmental Advisory Notes
               30.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               31.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               32.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               33.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability (i.e. until house construction has occurred on all lots),
                              Council Officers may take the following matters into consideration in determining
                              whether the site is capable of achieving medium to long-term stability:
                              •    evidence that the site has been effectively stabilised in the short term;
                              •    evidence that soil has been adequately ameliorated;
                              •    evidence that seed of annual and perennial grass species has been applied at an
                                   adequate rate; and
                              •    that grass seed has germinated at a density that is likely to achieve an effective
                                   grass cover.


                                                                                                        Page 19 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 20

                              For example, while hydromulch can provide an immediate and effective stabilising
                              cover to soils, the protective cover can be relatively short-lived if vegetation fails to
                              establish before the thin layer of mulch decomposes. So if hydromulch is selected as
                              the method of temporary short term stabilisation, Council Officers will seek to confirm
                              that perennial as well as annual grasses are well established at the time of plan sealing
                              to reduce the risk of instability of the site in the medium to long term. As a general rule,
                              hydromulch will only be accepted as a “patch” fix and should comprise no more than
                              20% of the exposed site area due to the high risk of failure. Due to the requirement to
                              progressively stabilise exposed areas, it is not envisioned that this will present any
                              difficulties for an appropriately managed and compliant site.
                      Retention of Existing Trees
               34.    The existing trees on adjoining properties must be retained and protected during construction
                      wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
                      operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
                      construction of the development which is the subject of this development approval.
                      Removal of Existing Trees and Vegetation
               35.    Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
                      well as optimum weed seed sterilisation.
                      Qualified Person
               36.    Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.
                      b.      Undertaking landscape construction and establishment works is considered to be a
                              person with five years current experience in commercial landscape construction
                              projects.
                      c.      Undertaking, supervising tree works and preparing arboriculture certification, is
                              considered to be a person with a minimum three years current experience in tree
                              protection, hazard identification/mitigation and Specifying Trees – a guide to
                              assessment of tree quality (NATSPEC) assessment and either:
                              i.       International Society of Arboriculture (ISA) certification; or
                              ii.      A Diploma of Arboriculture.
                      d.      Managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
                      Landscape Works
               37.    The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
                      Register where:
                      a.      An inspection revealed that any constructed rehabilitation/landscape works do not
                              comply with the conditions of the Decision Notice, Approved Plans and or Approved
                              Documents
                      b.      Certification is submitted to Council falsely stating that works comply with the approved
                              plans, documents and or conditions of the Decision Notice.


               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.

                                                                                                          Page 20 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Page 21

               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required             Subject of the required Development Permit

                Development Permit for Building Works           All building work (excluding demolition work).

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                    Page 21 of 21

Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025

Used in these records

About this file

File size
184 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Planning Report Conditions - Approval (As Publihed).pdf · 184 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.