Council archive · source document
Decision Notice - 010.2006.00002777.001 [As Published] · 132006.2777
NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 10
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
Land Use
1. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are titled and numbered Site Plan, 2 of 12; Floor Plan – Level 1, 3 of
12; Floor Plan – Level 2, 4 of 12; Floor Plan – Level 3, 5 of 12; South West Elevation, 6 of 12; South East
Elevation, 7 of 12; North West Elevation, 8 of 12; prepared by Magini and dated February 2007 and as
may be amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
3. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
4. The setback area (between frontage and the building) shall be planted with a minimum of 1 x 45 Litre
native coastal vegetation species.
5. A minimum of 20% of the site area is to be maintained as soft landscaping as defined by The Noosa Plan.
6. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to service the
detached house. The tank is to be installed to ensure water from the tank can be used both:
6.1. for external use such as watering gardens, irrigation, ornamental ponds or water features, topping
up swimming pools, outdoor cleaning; and
6.2. for use in flushing of toilets internal to the building.
7. Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be submitted, to
secure performance of all conditions of this approval, prior to the issue of a Development Permit for
building works. The cash bond or trading bank guarantee will be returned on performance of the
conditions of approval less any costs incurred by Council in respect of enforcing performance of this
permit.
8. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
constructed under overhead electricity transmission lines, or within any easements.
9. A geotechnical report, prepared by a registered professional engineer shall be obtained, and it should
either:-
9.1. certify that the site is not at risk from landslide emanating from the site or from other land; or
9.2. identify methods of stabilising all buildings, accessways and uses areas; and where the
geotechnical report identifies methods of stabilising buildings, accessways and uses areas. The
development shall implement those methods, which are recommended.
10. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
damage and made safe to the standard required by the regulatory authority;
11. All infrastructure must be disconnected, capped or sealed including:-
11.1 electricity meters removed and electrical wires disconnected; and
11.2 telephone lines are disconnected; and
11.3 high speed data cables and television provider boxes are disconnected and removed to the
standard required by the regulatory authority;
A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@dc059416\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2006.00002777.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 225 KB (small file)
- File type
No other editions are linked here.