Planning Report
proposal report
- Audiology
- Podiatry
• The models of care and service mix proposed for the ‘Noosa Health Hub’ are based on the
University of Queensland’s primary care, clinical innovation and research organisation known
as UQ Health.
Other facilities on site will include a caretakers unit for the complex.
To provide flexibility for the use of the building, the applicant also seeks approved for offices to
enable a mix of uses that would be complementary to the medical hub.
Building Design
The medical centre is to be constructed over the two sites and comprises a three storey building
located over basement carparking to the front of the site and two floors of carparking over basement
to the rear of the site. The building is of a modern design and is well articulated to the Hofmann
Drive frontage with balconies, timber and stone details and a central three storey entrance/foyer area
that provides a defined entrance whilst emphasizing a change to the line of the building.
All levels of the building are serviced by a central lift.
The proposal plans illustrate an indicative tenancy layout and mix that includes the following:
• Basement level: carparking, service and plant rooms, bike lockers and secure bike parking
area.
• Ground floor: central entrance, foyer, ambulance drop zone, pharmacy, consulting/tenancy
rooms, rehabilitation centre, hydrotherapy pool and bin store and waste/ loading dock and
access to carparking. Internal landscaped courtyard.
• Level 1: consulting/specialist/office rooms.
• Level 2: consulting/specialist/office rooms.
The building includes an operable skylight over the central foyer area for natural light and solar
panels across the roof.
Proposal plans include:
• Appendix B – architectural plans prepared by Thomson Adsett
• Appendix C – Stormwater Management Plan prepared by MPN consulting
• Appendix D – Civil Engineering Report prepared by MPN Consulting
• Appendix E – Traffic Impact Assessment prepared by Lambert and Rehbein
Table 3: Summary of development aspects
Material change of use
Building height Roof height: 10.2m
Lift overrun: 11.3m
Gross floor area (GFA) 6388m2
martoo consulting
town planners + urban designers + development managers page 10 of 21