ORDINARY MEETING AGENDA 17 FEBRUARY 2022
82. Fall protection must be provided to retaining walls that are over 1m high.
83. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies;
b. 1 in 4 for grassed areas;
c. 1 in 3 for planted areas;
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
84. Appropriate scour protection must be provided at the outlet of all stormwater pipes
including temporary outlets.
85. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g. by blocking or interfering with natural overland flows).
86. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Landscaping
87. The development site must be landscaped. The works must be undertaken in
accordance Noosa Plan PSP 2 – Landscaping and generally in accordance with the
approved Landscaping Plans and in particular:
a. The along the south side of the easement must include native species that
effectively screen the development and grow to a minimum mature height of 8m.
b. Plantings along the eastern side of the bio basin must grow to a minimum height
of 4m and provide screening to the car parking area.
c. The proposed 25 litre pot size feature trees within the front setback (facing
Doonella Street) must be replaced with 45 litre pot size plants
d. The existing street trees in the road reserve may be removed. If removed they must
be replaced with 4 x ex-ground Delonix regia (Poinciana’s) 400L trees as shown
on the approved landscape plans.
88. The finished level of all mulch in garden beds and landscaped medians is to be a
minimum of 50mm below the level of the adjacent top of kerb. All landscaping is to be
constructed in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
89. Suitable root barriers must be installed where proposed trees are adjacent to paths,
pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
Damage to Services and Assets
90. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Erosion & Sediment Control - Works adjacent to High Ecological Significance Water
91. Prior to the requesting the pre-start meeting the applicant must engage a Certified
Professional and Erosion Control to prepare and provide to Council scheduling plans for
the development which demonstrate that construction can be undertaken in a manner
consistent with Accepted best practice standards and all relevant conditions of this
Page 24 of 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.