Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 19 of 20
15/07/2020
EMERGENCY In an emergency situation, the Site Manager or HSEQ Adviser has full responsibility and
PROCEDURES authority for ceasing the works until suitable control measures are in place.
The Project Manager and HSEQ Advisor must be immediately advised of any environmental
incident or accident.
The HSEQ Adviser will implement temporary protection and/or control measures to minimize
the potential of any environmental damage.
The Site Manager and HSEQ Adviser (or nominated other) will be available at all times while
work is in progress and are responsible for:
• Identifying emergency assembly and exit locations and detailing these on a site
map and posting maps on site notice boards.
• Erecting emergency contact numbers at prominent locations throughout the site.
• Erecting appropriate signage (i.e. emergency assembly point, pedestrian signage,
exit signs).
• Ensuring that access to assembly points and exits are kept free of obstructions.
• Ensuring adequate and appropriate spill management facilities and information are
located at accessible locations around the site.
• Ensuring adequate first aid facilities for the site.
• Ensuring that a notification system (siren, hooter, alarm) is in working order and is
located in an accessible position for emergency use.
• Ensuring that the correct fire suppression equipment is placed in strategic locations
around site for emergency use.
• Ensuring that subcontract personnel are aware of the location of such equipment
and the basis use of such equipment.
• Advising of the emergency management information during site induction.
• Developing additional procedures a required by emergent situations on the project
site.
First Aid, Recording Refer to the BBN Constructions CMP.
and Signage
Emergency The Emergency Assembly locations will be identified:
Assembly locations
• On a site map which will be located at locations around the
project site (ie. site sheds.
• By means of standard emergency signage.
Such information will be provided to subcontractors at Site Induction
Evacuation Full or partial evacuation of the site – manual signal horn (acoustic
notification method gas horn) to be activated in the affected area.
Only a member of the BBN Constructions site management team
may initiate an evacuation and activate the evacuation siren or horn.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.