Amended Decision Notice - Approved by Delegation of Authority DBW24 0122 (As Published) · DBW24/0122

of 8

Text shows just the words. Original shows the document exactly as it was published.

                                                                               Officer:            Tiani Bird
                                                                               Direct Telephone:   07 5329 6389
                                                                               Our Reference:      DBW24/0122 & RAP24/0038
                                                                               Your Reference:     2024-72

               28 April 2025


               MBR Carey & CE Carey
               C/- Danya Cook Town Planning
               PO Box 9410
               PACIFIC PARADISE QLD 4564
               [email protected]



               Dear Sir/Madam,
                                                 Amended Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 10 April 2025, Council decided to approve the
               application, subject to conditions.
               An Amended Decision Notice was issued on 28 April 2025. The Amended Notice was as a result
               of an administrative error in the description type of the approved development. The approval date
               remains as per the date of decision.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              DBW24/0122

                   Street address:              7 Masthead Quay, Noosaville Qld 4566

                   Real property description:   Lot 593 RP 883861

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Building Work Assessable Against the Planning Scheme - Dwelling
                       House (Parapet) and demolition of existing building.
               3.      DEVELOPMENT PERMIT FOR DEMOLITION WORKS CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use of the building commencing, and then compliance maintained at all times while the
                       use continues.

               ABN 97.969.214.121                                                                 PO Box 141
               noosa.qld.gov.au                                                            Tewantin QLD 4565
               [email protected]                                                            07 5329 6500
                                                                                                            Page 1 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025
Log in to download the original file

Amended Decision Notice - Approved by Delegation of Authority DBW24 0122 (As Published).pdf · 164 KB (small file)

Full text of the other 7 pages

Page 2

                      Currency Period
               2.     This development approval lapses if the works have not substantially started by 9 April 2027,
                      unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                        Plan No.              Rev.   Plan/Document Name                            Date

                        WD.2.01               I      Site Plan, prepared by Garland Design         27/02/2025
                                                     Annotated by Council

                        WD.2.02               I      Demolition Plan, prepared by Garland 27/02/2025
                                                     Design

                        WD.2.03A              I      Ground Floor Plan, prepared by Garland 27/02/2025
                                                     Design

                        WD.2.04               I      Level 1 Floor Plan, prepared by Garland 27/02/2025
                                                     Design

                        WD.2.07               I      Roof Plan, prepared by Garland Design         27/02/2025

                        WD.3.01               I      Elevations, prepared by Garland Design        27/02/2025

                        WD.3.02               I      Elevations, prepared by Garland Design        27/02/2025

                      Noosa Waters Setback
               4.     The area within 4.5 metres of the centre line of the top of the concrete revetment wall must
                      be developed in accordance with the following:
                      (a)     A minimum of 25% of the area must be planted with shrubs and small trees with a
                              mature height of 3m or less.
                      (b)     A maximum of 25% of the area may be impervious, with the balance area soft
                              landscaping (i.e. grass, ground covers, shrubs and small trees).
                      (c)     The ground surface within 1 metre of the revetment wall must be grass or ground cover
                              and must not include shrubs or hard pavement.
                      (d)     Any side boundary fencing must taper down to a maximum height of 1.2 metres at the
                              revetment wall and have a height not exceeding 1.5 metres at a distance of 2.25 metres
                              from the revetment wall.
                      (e)     Any retaining structures, planter boxes or the like must be finished with natural
                              materials such as timber or rock rather than manufactured materials.
               5.     No shore side anchor points are permitted within 4.5m of the revetment wall.
                      Bonds
               6.     A site compliance bond of $5,000 is to be submitted to Council prior to the commencement
                      of works. The commencement of works can only commence once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               7.     Bonds must:


                                                                                                       Page 2 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 3

                      a.      Meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works;
                      b.      Be lodged with Council and accompanied by the Bond Administration Fee/s; and
                      c.      Be requested for release by writing to Council, when relevant approval requirements
                              have been met.
                      Earthworks
               8.     All earthworks and associated retaining structures/batters must be contained entirely within
                      the subject site unless written permission from the respective landowner(s) is provided to
                      Council. All earthworks must be undertaken in accordance with the provisions of Australian
                      Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
               9.     Earthworks carried out on site must not affect the structural integrity of the revetment wall,
                      existing fences or other structures that border the subject site. Fences that are affected must
                      be replaced in a timely manner and in consultation and agreement of the owners of the
                      related properties.
                      Revetment Wall / Flood Storage
               10.    All works within the 4.5m setback from the revetment wall must be carried out generally in
                      accordance with Linday Consulting’s Flood Storage Model Site Plan (24-1071-F1, Rev. A)
                      and Flood Storage Model Perspective Model (24-1071-F2, Rev. A) dated 29 December 2024.
               11.    All works for the purpose of increasing available flood storage must be located within the
                      4.5m setback from the revetment wall.
               12.    Certification of the completed works within the 4.5m setback from the revetment wall must
                      be submitted to Council within 3 months of the completion of the works. The certification must
                      be prepared by a RPEQ (Registered Professional Engineer of Queensland) and state that
                      the works:
                      (a) Have not reduced the amount of available flood storage within the 4.5m setback from the
                          revetment wall;
                      (b) Have not negatively impacted the stability of the revetment wall or negatively impacted
                          the associated membrane;
                      (c) Have not reduced the available flood storage within the lot from the profile as described
                          in The Noosa Plan 2020 – Low Density Residential Zone Code; and
                      (d) Meet the relevant conditions of this approval.
                      Stormwater Drainage
               13.    Stormwater runoff from the development must be discharged to Masthead Quay or disposed
                      of on-site without causing scour or damage to the subject site or any adjoining property.
                      Damage to Services and Assets
               14.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      Where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      a.      Where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               Demolition of Building
                      Codes of Development




                                                                                                        Page 3 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 4

               15.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               16.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               17.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               18.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               19.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.
                      Water Quality and Drainage
               20.    Erosion and sediment control is to be undertaken in accordance with the requirements of the
                      Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
                      maintained until soils are stabilised by vegetation or sealed.
                      NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).
                      Health and Safety
               21.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               22.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               23.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               24.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      Clearing of Vegetation
               25.    This development approval does not authorise the removal/clearing of vegetation from the
                      site.
               26.    Existing vegetation on Council controlled land must not be trimmed, pruned or otherwise
                      impacted without prior written approval from Council.
                      General
               27.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.


                                                                                                       Page 4 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 5

               28.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
                      Plumbing and Drainage
               29.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               5.     REFERENCE DOCUMENTS

                Plan No.        Rev.   Plan/Document Name                                        Date

                241071          -      Flood Storage Calculations                                no date
                                       Prepared by Lindsay Consulting

                24-1071-        A      Flood Storage Model Site Plan                             29 December 2024
                F1
                                       Prepared by Lindsay Consulting

                24-1071-        A      Flood Storage Model Perspective View                      29 December 2024
                F2
                                       Prepared by Lindsay Consulting

               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Aboriginal Cultural Heritage Act 2003
               1.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Equitable Access and Facilities
               2.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and



                                                                                                             Page 5 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 6

                      c.      the Disability (Access to Premises – Buildings) Standards.




                                                                                           Page 6 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 7

                      Fires in Urban Areas
               3.     In urban areas fires are prohibited except where in an appliance is used for domestic heating
                      or cooking purposes, which must comply with particular standards. Any area identified as a
                      fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
                      Law No. 3, Schedule 3. Refer to the following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
                      Infrastructure Charges
               4.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required             Subject of the required Development Permit

                Development Permit for Operational Works        Driveway crossover.

                Development Permit for Building Works           All building work.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,



               Tiani Bird
               Development Planner


               Enc:   Appeal Rights
                      Approved Plans/Documents




                                                                                                      Page 7 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

Page 8

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 8 of 8
Document Set ID: 23708137
Version: 1, Version Date: 28/04/2025

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.