SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 11 FEBRUARY 2020
This report relates to the second quarter of the 2019/20 financial year for the Operational Plan
and some management KPIs.
1. OPERATIONAL PLAN UPDATE
Only the major initiatives are included in the Operational Plan with day to day “business as usual”
activities included in Branch Plans.
The Branch Plans are being used by Managers to manage day to day activities. They are an
effective tool for ensuring that all of the “business as usual” activities are undertaken and that any
minor projects are followed through. They are reported to Council by Directors on a quarterly
basis and those reports are on this round of Council meetings.
Details of each Operational Plan project is set out in Attachment 1 with an assessment of
whether the issue in completed, on track or behind schedule. Comments are also provided for
the information of Councillors about the status of each issue. It is important to note that this is
“as at 31 December” i.e. the end of the first quarter and in some instances, the actions have been
advanced further since that time.
There are 32 initiatives in the 2019/20 Operational Plan. The current status of those projects is:
Status Quarter 1 Quarter 2
(July – Sept 2019) (Oct – Dec 2019)
Not started 3 3
Behind Schedule 4 3
On Track 24 21
Completed 1 5
The table below highlights some specific Operational Plan issues that may be of interest to
Council. The first three items listed are those that have not yet commenced while the next three
are those that are behind schedule.
Initiatives Comment
Update Local Economic Plan This is scheduled to commence in the third quarter.
Investigate options for the This will only commence once the Council enters into a binding contract
future use of the former with the State government. Negotiations with the State continue.
Tewantin TAFE Site
Establish a place making This will be commenced following the completion of the new Noosa
team and commence pilot Plan.
project
Adoption of the Noosa River The draft Noosa River Plan was put to the community for consultation in
Management Plan and the second quarter. Responses are currently being assessed.
commence implementation
Commence construction of The Council appointed contractor has gone into liquidation so we will
the new Peregian Beach need to re-tender the works which will delay the project.
Community House
Develop Community This project may be best considered in the 20/21 financial year. That is
Sustainability Indicators when the Council is likely to review its Corporate Plan and consider the
option of developing a Community Plan.
Page 99 of 112
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.