Building Approval · MCU22/0116.01

of 82

Text shows just the words. Original shows the document exactly as it was published.

Original PDF page 18, section 1. The text section number identifies this passage in the reader.

                      f.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               38.    All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               39.    A condition report including photographs of the frontage of the site must be completed and
                      submitted to council prior to the prestart meeting.
               40.    Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               41.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
               42.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction
                              ii.      Maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
               43.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               44.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               45.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               46.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice.
                      b.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines.




                                                                                                        Page 7 of 19
Document Set ID: 22234003
Version: 3, Version Date: 10/01/2023

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Building Approval.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.