GENERAL CONDITIONS OF APPROVAL FOR BUILDING WORK
RESIDENTIAL
Building Approval Number: 240156.01
Property Address: 22 Delorme Street, NOOSA HEADS QLD 4567
Scope of work: Duplex & x2 pools
1. CURRENCY PERIOD
The currency period is that stipulated in clause 2 of the attached Decision Notice. This permit will lapse
if building work covered by this approval has not been commenced and or completed within the period
specified.
2. MANDATORY INSPECTIONS REQUIRED AT THE FOLLOWING STAGES:
Inspection Private Certifier Competent Person
Footing – excavation of foundation material
☐
and before footings are laid
Slab – after placement of formwork and steel
☐
for slab and before concrete is poured
Frame – before cladding or lining is fixed to the
☐
frame
Reinforced masonry construction – before wall
☐ ☐
cavities are filled
Final - at completion of all aspects of building
☐
work
Fire Wall - before work is covered or enclosed ☐ ☐
Swimming pool fencing - prior to placing more
☐
than 300mm of water into pool
Swimming pool final - at completion of all
☐
aspects of building work
3. MINIMUM CONSTRUCTION REQUIREMENTS
All building work shall comply with the provisions of the Building Act 1975 and shall be in
accordance with the approval documents including any amendments or conditions shown in
red.
4. SWIMMING POOL BARRIER
The swimming pool must NOT be filled with more than 300mm of water until it is enclosed by a barrier that
meets with state government pool safety legislation under chapter 8 of the Building Act 1975 Including but
not limited to.
a. Building Regulation 2021 - Queensland Government legislation
b. Australian Standards 1926 series as amended
c. Queensland Development Code (QDC) MP 3.4.
Safety barriers must comply with the current standards and be;
a. not higher than 2m above ground level or:
b. if built on a retaining wall or other structure, is not higher than 2m above the wall or structure, and
no part of the fence that is higher than 2m above ground level is within 1.5m of a boundary.
The pool barrier must be inspected by the Certifier for compliance with the pool safety standard prior to
filling with water.
5. ENGINEERING DRAWINGS
Pursuant to Section 70 of the Building Act 1975 no work is to commence on any footings until amended
engineer drawings and details are submitted to, and approved by, the Building Certifier. A stage of
building work must not be started until the drawings and details for the stage have been approved by
the Building Certifier.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Building Approval.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.