8. Existing trees on the site must be retained, except where required to be removed to
accommodate the approved dwelling. In this regard, the removal of vegetation must not
extend beyond 5 metres of the building footprint.
9. Existing vegetation in the road reserve must be retained, unless written authorisation from
Council is granted for the clearing.
10. Trees to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape
b. installing protective fencing around the drip line of the vegetation
c. restricting stockpiling, storage and vehicle parking to those areas which are already
cleared
d. using low impact construction techniques around vegetation.
Earthworks
11. All cut and fill must not exceed 1.5 metres in depth relative to natural ground level.
12. All excavation/fill and associated batters must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
13. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height.
14. All earthworks must include the installation and maintenance of appropriate erosion and
sediment control measures. Prescribed Water Contaminants (as defined in Schedule 10 of
Environmental Protection Regulation 2019) must not be released from the site or to waters
within the site, or be likely to be released should rainfall occur, unless all reasonable and
practicable measures are taken to prevent or minimise the release and concentration of
contamination.
15. Earthworks required on site must be carried out in accordance with Council’s Planning
Scheme Policy PSP6 - Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or concentrate or direct overland flow on to an
adjoining property.
Water Supply
16. The approved dwelling must be serviced with a rainwater tank having a minimum storage
capacity of no less than 45,000 litres.
Waste Water Treatment and Disposal
17. The dwelling must be provided with an on-site wastewater treatment and effluent disposal
system having a capacity sufficient for the use*.
*(Refer to Advisory Note)
Bushfire Management
18. An accessible dam, swimming pool or water tank (in addition to day to day water supply) with
an onsite water volume of not less than 5,000 litres must be available for firefighting
purposes, located within reasonable proximity to building.
19. A water supply outlet pipe 50 millimetres in diameter and fitted with a standard fire brigade
fitting must be connected to the water supply (other than where the water supply is in a
swimming pool or dam).
Page 3 of 11
Document Set ID: 25142963
Version: 3, Version Date: 09/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - MCU25 0025 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 367 KB (small file)
- File type
No other editions are linked here.