001 ECM_22816452_v8_Decision Notice - Other Change - Council Meeting Decision 132005 638 03
Attached to the e-mail Representations to Development Approval (132005_638_03) - Material Change of Use -Expansion of Special Purpose (Waste Disposal &.
26. The sites supervising engineer must ensure that the sediment and erosion control
measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with
"best practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in
the projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
27. The erosion and sediment control measures must be designed, installed, and
maintained in accordance with the current best practice standards.
28. Certification must be submitted to Council from a qualified person* which certifies that
the subject works have been undertaken in accordance with the Sediment and Erosion
Control Plan.
*(Refer to Advisory Note)
29. A Vegetation Removal & Fauna Management Plan must be prepared by a suitably
qualified person to mitigate the risk of clearing impacts to all native fauna and adjoining
vegetation. The sequential clearing requirements specified under the Nature
Conservation (Koala) Conservation Plan 2017 are to be adopted in the Plan.
30. A suitably qualified person must be engaged to manage flora and fauna prior and during
clearing to ensure works are carried out in accordance with the Vegetation Removal and
Fauna Management Plan (required as part of this approval) and the Nature
Conservation Act 1992.
31. Certification must be submitted to Council from a qualified person* which certifies that
the subject works have been undertaken in accordance with the approved Vegetation
Removal & Fauna Management Plan.
*(Refer to Advisory Note)
32. An Arborist Assessment must be completed by a suitably qualified and experienced
Level 5 consulting arborist of the trees likely to be impacted along the edge of the
earthworks footprint and any recommendations made are adopted. Disturbance to
retained remnant vegetation and tree root protection zones of large, retained habitat
trees (trees with dbh >300mm) that occur next to the clearing area is to be avoided as
far as practicable.
33. Certification must be submitted to Council from a qualified person* which certifies that
the subject works have been undertaken in accordance with the approved Arborist
assessment.
*(Refer to Advisory Note)
Bushfire management
34. A bushfire hazard assessment must be prepared in accordance with the SPP 2019
Guidelines: Natural hazards Risk and Resilience Bushfire 2019 and the QFES Bushfire
Resilience Community 2019 for the development.
35. The development must be carried out in accordance with the requirements and
recommendations of the Bushfire Management Plan. Certification must be submitted to
Council from a qualified person* which certifies that the subject works have been
undertaken in accordance with the approved Bushfire Management Plan.
*(Refer to Advisory Note)
36. A copy of the Bushfire Management Plan must be provided to the nearest fire authority
Page 5 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024