Council archive · source document
001 ECM_21443089_v2_Minor Change Existing Approva · 172007.545.02
4. ASSESSMENT MANAGER CONDITIONS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
WD.101 C1 Cover sheet, prepared by CT Design as 10/02/2021
annotated by Council
WD.201 C1 Existing Lower Level Floor Plan, prepared 10/02/2021
by CT Design
WD.205 C1 Prop. Ground Floor Plan, prepared by CT 10/02/2021
Design
WD.206 C1 Proposed Upper Level Floor Plan, prepared 10/02/2021
by CT Design
WD.207 C1 Proposed Roof Plan, prepared by CT 10/02/2021
Design as annotated by Council
WD.501 C1 East Elevations, prepared by CT Design 10/02/2021
WD.502 C1 North Elevations, prepared by CT Design 10/02/2021
WD.503 C1 West Elevations, prepared by CT Design as 10/02/2021
annotated by Council
WD.504 C1 South Elevations, prepared by CT Design 10/02/2021
as annotated by Council
WD.601 C1 Section A, prepared by CT Design 10/02/2021
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
4. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
not constructed under overhead electricity transmission lines, or within any easements.
5. A geotechnical report, prepared by a registered professional engineer shall be obtained, and
it should either:-
a. certify that the site is not at risk from landslide emanating from the site or from other
land; or
b. identify methods of stabilising all buildings, accessways and uses areas; and where
the geotechnical report identifies methods of stabilising buildings, accessways and
uses areas. The development shall implement those methods, which are
recommended.
6. The Preliminary Approval for a building works lapses if the use has not happened by 23 April
2009, unless an application to extend the currency is approved by Council
Page 2 of 5
Document Set ID: 21443089
Version: 2, Version Date: 13/04/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001 ECM_21443089_v2_Minor Change Existing Approva.pdfRelated documentApplication case desk ↗
About this file
- File size
- 185 KB (small file)