20210153 - Maple Street SWMP
Original PDF page 12, section 1. The text section number identifies this passage in the reader.
Table 3.2 Existing and proposed mitigated site peak discharge rates
Maple Street
Qchange
A.E.P Qexisting Qmitigated Qchange (%)
(m³/s) (m³/s) (m³/s)
1EY 0.045 0.038 -0.007 -16%
50% 0.054 0.045 -0.009 -17%
0.2 EY 0.103 0.09 -0.013 -13%
10% 0.129 0.116 -0.013 -10%
5% 0.159 0.14 -0.019 -12%
2% 0.196 0.167 -0.029 -15%
1% 0.215 0.184 -0.031 -14%
As the total peak flows are equal to or below the existing site conditions, the proposed OSD area will
provide the mitigation required for the peak flow storm events from the development.
The stormwater pit on Myall Street is proposed as the lawful point of discharge for the development.
As the existing site run-off drains towards Myall Street and is conveyed through the kerb and channel
to the existing kerb inlet pit in Myall Street, the stormwater system capacity of this drainage network
is not considered to be worsened by the development. Peak flows from all storm events are reduced
through the implementation of the stormwater attenuation measures, therefore the proposed
stormwater discharge will reduce the demand on the downstream network.
.
Project number 20210153
File RECOR Preliminary Stormwater Management Report - 20210153.docx, 2022-03-31 Page 12 of 26
Revision 0
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (20210153 - Maple Street SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.