Part 22 of 37 Appendix 20 - Earthcheck MCU12/0208

of 127

Text shows just the words. Original shows the document exactly as it was published.

Very large file (86.5 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

         Contracts      for      building, civil      engineering and regional infrastructure operations
         amounting       to      an    estimated      $250 million over the life of the implementation
         programme;

         Approximately 2,000 direct construction and enabling related jobs generated during
         construction phase with             a   high expectation that the construction force will come from
         the local communities;

         Predicted full time equivalent positions will number 306 new                              long term permanent
         employment opportunities;

         Direct     economic          contribution             the
                                                   region through long term employment
                                                         to

         opportunities and possible indirect full time equivalent positions arising from the
         related businesses;

         Training programs regarding environmental, social and operational job opportunities
         partly aimed at the disabled and young persons in roles in age care, landscape &
         environmental maintenance, and Body Corporate management;

         Economic        equity        by    commitment          to       maintain    a   wide     range     of   affordable
         accommodation.

Indicators and measures evaluation

The    development has been                  independently assessed              using    an     indicator   benchmarking
evaluation matrix based               on measures       that reflect internationally accepted good sustainable

 practice. The development achieved ’Industry                                  Best   Practice’ in       46 of the         SO

measures         noted      in    the assessment               matrix       {See Appendix}.          This    achievement

places Noosa on Weyba at the forefront of sustainable large/medium mixed-use
precinct development.

Of the remaining 4 measures several of these cannot be fully benchmarked and certified at
this stage of precinct planning and                design evolution.          For example, predicted         percentages of
green components and systems used cannot be fully ascertained until detailed                                   design work
on    individual     buildings        is   completed     at    the    works    application stage. Accordingly, the
certification of Noosa           on   Weyba adjusts       as the      development progresses through its various
future phases. The remaining measures will be revisited and benchmarked accordingly under
the EC3 Earthcheck               programme, which              has    a   requirement for yearly recertification           as

 projects proceed through construction to the operational phase.

Conclusion and Recommendation

Some lessons taken from the planning and design process

The    Client-Developer Northbrook challenged ’business as usual’ process                                     norms   whilst

 recognizing that sustainable agendas require considerable inputs to a development. Noosa
on Weyba has achieved a high rating due in part to the implementation of an innovative

delivery strategy and by Northbrook’s long-term commitment to the precinct. Also by
showing willingness to put forward a sustainable agenda of its own making, the result has
been a more effective and sustainable development process. This indicates a continuing role
for involvement as a result of recognizing that many sustainable inputs and their impacts
take place over time and may come about by adjustment to aspects of the development.

This    phenomenon will           most      likely be    seen    in the critical social and economic              areas.   To
accommodate          this     factor the         power    of    specifically developed           ecological performance

                                                                                                                           19
EC3 (Earthcheck)Prec nct Plann ng and Des gn Standard (PPDS)for Prec ncts. Cert cat on Report
@ 2007 EC3 Asia Pacific. All rights reserved. Version EC3 PPOS 2012.

Used in these records

About this file

File size
86.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 22 of 37 Appendix 20 - Earthcheck MCU12_0208.pdf · 86.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.