6.3 Operational Phase
The proposed development has been assessed against the latest State Planning Policy 2017 (SPP
2017). The proposed development will entail the material change of use for urban purposes, which
will involve a land area greater than 2,500m2. Consequently, State Planning Policy 2017 (SPP 2017)
is triggered and stormwater quality treatment is will be required for this development.
Water quality objectives (WQO’s) for South East Queensland as set out in State Planning Policy 2017
(SPP 2017) should be achieved by identifying and adopting best practise techniques in accordance
with the abovementioned guidelines. Refer to Table 6.3 for the target WQO’s.
Table 6.3 – Minimum Mean Annual Load Reductions
Minimum Mean Annual
Contaminant
Load Reductions
Total Suspended Solids (TSS) ≥ 80%
Total Phosphorus (TP) ≥ 60%
Total Nitrogen (TN) ≥ 45%
Gross Pollutants (GP) ≥ 90%
6.3.1 Sources of Contaminants
Potential sources of contaminants and stormwater quality improvement devices identified for the
operational phase of the development are outlined in Table 6.4
Table 6.4- Sources of Contaminants
Pollutant
Target Pollutant Type Acceptable Treatment Examples
Size
Primary Screening of gross Litter baskets, swales, buffer strips,
>5000um
Pollutants pollutants GPT’s, Bio-retention basins
Sedimentation of
Secondary 125um -
coarse to medium Swales, sedimentation basins, ponds
Pollutants 5000um
sediment
Bio-retention basins, constructed
Enhanced
10um – wetland macrophyte zones, other bio
sedimentation of fine
125um technologies, proprietary tertiary
particulates
stormwater treatment dvices
Tertiary Adhesion and filtration Constructed wetland macrophyte zones,
0.45um –
Pollutants of very fine / colloidal other bio technologies, proprietary
10um
sediment tertiary stormwater treatment dvices
Biological uptake of Constructed wetland macrophyte zones,
<0.45um
dissolved particles other bio technologies
Site Based Stormwater Management Plan
Proposed Townhouse Development at 99, 101 & 105 Eumundi Noosa Road, Noosaville
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.