RFI - Attachment D - Callaghan and Toth IR response
ISSUE: Road Reserve area has not been tested for contaminated land
Item 23: Provide information regarding the likelihood of the Maple Street road reserve containing traces of
chemicals associated with previous uses of the site.
In response to Item 23 above the following information is offered:
Core Consultants have undertaken further testing in the area of playground that overlaps into the road
reserve. See attached Core report J001102-001-L-Rev0 dated 1 July 2020. The results showed one
borehole BH07 in the road reserve exceeding the available guidelines. It is proposed to do validation
testing during works to remove any contaminated materials in this area.
If you require any further information please contact me on 5474 9081 or 0401 570 753.
Yours faithfully,
Callaghan & Toth
Jane Davissen BE Environmental
Senior Environmental Engineer
Please view www.callaghanandtoth.com.au for all information on our company profile and terms and conditions for services rendered
X:\JOBS\CT Projects in progress\2001 env reports for cooroy playground
carparks\Correspondence\Applications\MCU\ResponseLetter_MCU20_0013_Playground_C&Tresponse_July2020.doc
4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (RFI - Attachment D - Callaghan and Toth IR response.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.