ORDINARY MEETING AGENDA 19 MAY 2016
Landscaping
14. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan and Council’s
Planning Scheme Policy 3 – Landscaping Plants & Guidelines and must include in
particular:
14.1. The open space and landscaped areas the works shown on the Approved
Plans;
14.2. Retention of existing trees, as generally indicated on the approved plans;
14.3. Native screening trees and shrubs to partially screen the building bulk; and
14.4. Details of proposed fencing;
15. All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
16. All landscape works must be established and maintained in accordance with
horticultural best practice with construction techniques that allow for healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to
full form.
Waste
17. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy “Waste Management Multi-Dwellings and Commercial and
Industrial Premises”, including an external imperviously paved area correctly sized for
all refuse and recycling containers and suitably screened from public places and
neighbouring properties.
Noise Nuisance
18. Noise emission from mechanical equipment shall comply with the following
requirements:
18.1. Air-conditioning and Refrigeration
7am to 10pm: Maximum background + 5dB(A)
10pm to 7am: Maximum background + 3dB(A)
18.2. Pumps
7am to 7pm: Maximum background + 5dB(A)
7pm to 10pm: Maximum background + 3dB(A)
10pm to 7am: No audible noise.
19. Submission of written certification from a suitably qualified person confirming that the
noise levels from all mechanical equipment comply when measured at either the
residential boundary or outside the most exposed part of an affected building,
whichever is the closest to the equipment. The assessment and certification is
required immediately after installation of the equipment and prior to any occupation of
the building, and in a format approved by Council. All equipment should be operating
at the same time to test the overall noise level created.
Advice: It is recommended the person you engage to certify the installation is
involved at the plan development stage so they can recommend where equipment is
best located. They can also advise about noise enclosures and make other
suggestions to avoid noise problems that are is costly deal with post-construction.
Page 7 of 48