ORDINARY MEETING AGENDA 19 MAY 2016
Stormwater Drainage
27. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. All stormwater drainage must be collected and discharged so
there is no net increase in stormwater runoff from the site. The works must be
generally in accordance with drawing number 26041-SW1 prepared by SCG
Consulting and be undertaken in accordance with an Operational Works approval.
Electricity and Telecommunication Services
28. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
Earthworks and Retaining Walls
29. All fill and associated batters must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council.
30. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All
retaining walls that are publicly accessible and exceed 1.0m in height must be fitted
with a commercial grade safety fence.
Damage to Services and Assets
31. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
31.1 where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
31.2 where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
RECONFIGURING A LOT CONDITIONS (REC15/0024)
Approved Plans
1. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
- B Proposed Reconfiguration 33 & 35 Grant Street, -
Noosa Heads
2. All lot numbering on the subdivision plan to be submitted to Council for compliance
assessment must remain as shown on the Approved Plans.
Water & Sewer Connections
3. An underground connection to reticulated water and sewerage must be provided to
each lot in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
4. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to each lot.
Page 9 of 48
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.