Slope Stability Report
Dean & Vanessa McDonald 21505-001-Rev0
4 February 2022
structures or fill batters and not as concentrated discharge upslope of any neighboring
structures/embankments. The platform should be graded slightly (minimum 1V:100H) back ‘into’ the
exposed rock batter slope to drain appropriately to the diversion drainage system and not allow over topping
of the downslope fill batters.
Subsurface drainage must be installed behind any retaining walls (e.g. slotted ‘aggi’ pipe wrapped in filter
‘sock’ placed in gravel backfill). Depending on matters such as the extent of drainage installed and site-
specific groundwater conditions, the designer must make an assessment of hydrostatic pressure to be
accounted for in the design of the retaining structure.
It would be prudent to construct a rock dissipator or rock contour drain at the drainage outlet point(s) to
minimise erosion. Drains should be directed to discharge towards the natural drainage lines.
Subsurface disposal of stormwater must not be undertaken (including infiltration pits).
5.0 SUMMARY & CONCLUSIONS
Based on the findings of our assessment we consider that there would be a Low Risk of slope instability
affecting the proposed shed, subject to implementation of the recommendations given in this report.
6.0 LIMITATIONS
Your attention is drawn to the document Limitations, which is attached to this letter report.
Please contact the undersigned should you wish to discuss any of the above matters.
Yours faithfully,
TECTONIC GEOTECHNICAL PTY LTD
Jarrad McVey BEng (Civil) (Hons) Ashley Davey RPEQ 8159
Geotechnical Engineer Director/Principal Geotechnical Engineer
Attachments: DCP Reports
Qualitative Terminology for Use in Assessing Risk to Property
Some Guidelines for Hillside Construction
Limitations
12/12
[OCR of page images]
Dean & Vanessa McDonald 21505-001-RevO
4 February 2022
structures or fill batters and not as concentrated discharge upslope of any neighboring
structures/embankments. The platform should be graded slightly (minimum 1V:100H) back ‘into’ the
exposed rock batter slope to drain appropriately to the diversion drainage system and not allow over topping
of the downslope fill batters.
Subsurface drainage must be installed behind any retaining walls (e.g. slotted ‘aggi’ pipe wrapped in filter
‘sock’ placed in gravel backfill). Depending on matters such as the extent of drainage installed and site-
specific groundwater conditions, the designer must make an assessment of hydrostatic pressure to be
accounted for in the design of the retaining structure.
It would be prudent to construct a rock dissipator or rock contour drain at the drainage outlet point(s) to
minimise erosion. Drains should be directed to discharge towards the natural drainage lines.
Subsurface disposal of stormwater must not be undertaken (including infiltration pits).
5.0 SUMMARY & CONCLUSIONS
Based on the findings of our assessment we consider that there would be a Low Risk of slope instability
affecting the proposed shed, subject to implementation of the recommendations given in this report.
6.0 LIMITATIONS
Your attention is drawn to the document Limitations, which is attached to this letter report.
Please contact the undersigned should you wish to discuss any of the above matters.
Yours faithfully,
TECTONIC GEOTECHNICAL PTY LTD
MM
Jarrad McVey BEng (Civil) (Hons) Ashley Davey RPEQ 8159
Geotechnical Engineer Director/Principal Geotechnical Engineer
Attachments: DCP Reports
Qualitative Terminology for Use in Assessing Risk to Property
Some Guidelines for Hillside Construction
Limitations
tectenic
12/12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.