Table 2-1: Summary of Existing Catchment Parameters
Sub-catchment Downstream Area (ha) Imperviousness (%)
Catchment
Ex2 SUB3 1.960 50
Ex1 SUB1 0.287 50
SUB3 SUB4 2.085 21
SUB1 SUB2 2.079 11
SUB2 SUB4 1.354 5
SUB4 SINK 0.511 5
Ex1 (<10% AEP) 0.0* -
Ex1 (5% AEP) 0.049* 50
Ex1 (2% AEP) 0.093* 50
Ex1 (1% AEP) 0.116* 50
Ex1 (1% AEP CC) 0.152* 50
Ex2 (<10% AEP) 0.0* -
Ex2 (5% AEP) 0.300* 50
Ex2 (2% AEP) 0.618* 50
Ex2 (1% AEP) 0.782* 50
Ex2 (1% AEP CC) 1.032* 50
* area factored based on flow rate for events greater than 10% AEP
The WBNM model has been run for events from 1 to 100-year ARI and for durations of 20 minutes to 3
hours. A WBNM catchment lag factor of 1.6 was applied which is within the recommended range. An initial
and continuing loss of 35mm and 2.4mm/hr in line with ARR2019 datahub values. The resulting peak flows
for the critical duration are provided in Table 2-2 for each event at the outlet reporting locations.
Table 2-2: Existing Catchment Peak Flows
Event AEP 63.20 50% 20% 10% 5% 2% 1% 1%CC
%
Existing (m3/s) – SUB3 0.13 0.16 0.30 0.38 0.47 0.58 0.68 0.88
Existing (m3/s) – SUB4 0.33 0.43 0.72 0.92 1.21 1.55 1.86
2.1.2. Rational Method Check
Pre-development peak flows have been checked against peak flows determined using the Rational Method
(RM) for SUB3, as shown in
23-0167SMP01-V3 | Stormwater Management Plan | 33 Pavilion Street, Pomona Page 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.