Table 2-4: External catchment overland flow (entering site) and pipe flow (diverted around site via Pavilion St)
Flow 10% AEP 5% AEP 2% AEP 1% AEP 1% CC AEP
Area Flow Area Flow Area Flow Area Flow Area Flow
(ha) (m3/s) (ha) (m3/s) (ha) (m3/s) (ha) (m3/s) (ha) (m3/s)
TOTAL 1.960 0.437 1.960 0.534 1.960 0.671 1.960 0.768 1.960 0.982
EX2 Overland - - 0.300 0.097 0.618 0.234 0.782 0.331 1.032 0.545
Pipe 0.437 0.437 0.437 0.437 0.437
TOTAL 0.287 0.165 0.287 0.093 0.287 0.114 0.287 0.130 0.287 0.165
EX1 Overland - - 0.049 0.018 0.093 0.039 0.116 0.055 0.152 0.091
Pipe flow 0.075 0.075 0.075 0.075 0.075
Table 2-5: Summary of Developed Catchment Parameters
Sub-catchment Downstream Area (ha) Imperviousness (%)
Catchment
Ex2 SUB3 1.960 50
Ex1 SUB1 0.287 50
SUB3 SUB2 1.780 50
SUB1 SUB2 2.079 50
SUB2 SUB4 1.354 5
SUB4 SINK 0.819 5
Ex1 (<10% AEP) 0.0* -
Ex1 (5% AEP) 0.049* 50
Ex1 (2% AEP) 0.093* 50
Ex1 (1% AEP) 0.116* 50
Ex1 (1% AEP CC) 0.152* 50
Ex2 (<10% AEP) 0.0* -
Ex2 (5% AEP) 0.300* 50
Ex2 (2% AEP) 0.618* 50
Ex2 (1% AEP) 0.782* 50
Ex2 (1% AEP CC) 1.032* 50
* area factored based on flow rate for events greater than 10% AEP
The increased imperviousness and changes to catchment areas associated with the development resulted
in an increase in peak flows to the sites outlet as shown in Table 2-6. Mitigation will be required to ensure
non-worsening downstream and satisfy the lawful point of discharge requirements.
Table 2-6: Comparison of Peak Flows At Site Outlet (Existing Vs. Developed)
Event AEP 63.20% 50% 20% 10% 5% 2% 1% 1%CC
Existing (m3/s) 0.33 0.43 0.72 0.92 1.21 1.55 1.86 2.57
Developed (m3/s) 0.34 0.43 0.73 0.94 1.25 1.66 2.04 2.63
Change (m3/s) 0.01 0.00 0.01 0.02 0.04 0.11 0.18 0.06
23-0167SMP01-V3 | Stormwater Management Plan | 33 Pavilion Street, Pomona Page 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.