Skip to the record
The gold standard in government transparency.

Original source · versioned page text

Combined Approved Plans RAL21/0003

of 115

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (12.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                Total Concept Homes                                                                            20332-001-Rev1
                                                                                                                22 March 2021

                2.3     Groundwater
                No signs of groundwater seepage (‘springs’) were observed during our walk-over, and neither was any
                seepage encountered during borehole drilling. Groundwater conditions may vary seasonally, and could
                rise to shallower depths, particularly following periods of prolonged or heavy rainfall.

                2.4     Surface Drainage
                Broadly, the natural surface drainage follows the ground surface contours, which over the proposed
                development areas tended to fall to the north. Surface water flows affecting the proposed residence and
                eastern part of the driveway alignment would be considered negligible, given the topographical position
                towards the crest of a well developed spur. The natural ground does rise above the western part of the
                driveway alignment, where a catchment over the area of an existing residence may proliferate.

                No significant erosion was noted during our walkover inspection.
                Surface water is expected to drain well from the site considering the moderate to steep natural gradients
                and low permeability of the soils in the immediate subsurface, and relatively shallow depth to rockhead.

                2.5     Vegetation
                The immediate periphery of the proposed driveway consisted of periodically slashed grass, which was quite
                long at the time of our inspection. Small to medium size mature trees were noted on the sloping ground to
                the north of the proposed driveway, which were observed to be relatively ‘plumb’.

                Around the area of the proposed residence, slashed grass was also present over most of the area, with
                some large mature trees just to the west of the proposed building location. These were also noted to be
                quite straight at the time of our inspection, with no tilting or distorted growth present, which can be an
                indicator of slope instability.

                2.6     Buildings and Other Structures
                The existing residence comprised a one storey, low set, masonry walled structure, constructed over a cut
                and fill earthworks pad. The residence was mostly on cut to the south, which ranged up to around 1.5 m
                depth. Fill on the northern side of the residence was supported by a grouted rock wall and ranged up to 2 m
                height. The grouted rock facing supporting the fill did not show any signs of global instability having affected
                the structure; with the residence generally being in good structural condition, other than some minor cracking
                to the concrete apron to the slab. It was noted that the cracking was coincident with the daylighting point for
                underslab pipework (assumed to be for wastewater and water).

                Although not within the subject site, a retaining wall was present along the south-western boundary, which
                would be adjacent to the proposed driveway access. This was estimated to be in the order of about 4 m
                height, and was constructed of large concrete blocks, spread over two tiers. This is shown below in Text
                Figure 8.




                Text Figure 8: Looking south-west over retaining wall on neighbouring allotment

                It was presumed that this had been recently constructed, and it was not clear whether upslope surface water
                flows were being captured by the structure, and if so, where discharge was being directed to.




                                                                          6/14
Document Set ID: 21426326
Version: 1, Version Date: 24/03/2021
Log in to download the original file

Combined Approved Plans RAL21_0003.pdf · 12.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.