Council archive · source document
Decision Notice - Approved by Delegation of Authority OPW24 0103 (As Published) · OPW24/0103
FOLLOWING CONSTRUCTION
Certification
39. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
40. Prior to commencement of use the following (prepared by respective qualified persons* and
certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification confirming all works have been constructed in accordance
with conditions of approval.
41. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
SBSMP C Site Based Stormwater Management Plan 26 August
2024
Prepared by JFP Consulting
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed in accordance with standard drawings RS-051.
2. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
3. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
4. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance, Rehabilitation Inspections Request
5. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days’ notice of preferred inspection time.
6. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
Page 8 of 11
Document Set ID: 23291220
Version: 3, Version Date: 09/10/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority OPW24 0103 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 175 KB (small file)
- File type
No other editions are linked here.