Decision Letter - Change to an Existing Approval - 010.2006.00000676.003 [As Published] · 142006.676.03
2006/676
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. All bonds and contributions as required by the conditions of the Material Change of Use
Approval (2006/1148) shall be paid to Council prior to the issue of a Development Permit for
Operational Works. No Building Works approval is to be issued or work undertaken on the site
until a Development Permit for Operational Works has been obtained.
2. The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines
and the approved plan of development. The approved plan is titled and numbered Landscape
Plan Drawing No. 0221 Revision A prepared by Tom Walsh - Yardart dated 8 May 2006 and
may be amended by these conditions
3. Provide 2 x 45 litre Banksia integrifolia trees to replace the 2 x Pandanus pendunculatum
located in the road reserve of Park Crescent. All street trees are to be provided with 1 metre
mulch collars. Refer to the amended landscape plan for details and location.
4. All manholes, inspection pits and grates are to be raised to finish surface level and kept free of
cover and be visible at all times to ensure prompt access in case of emergency.
5. The landscape construction is to be implemented in accordance with the amended landscape
plan, planting schedule and horticultural industry best practices.
6. Prior to the commencement of all works, all trees to be retained except where required to be
removed due to footpath construction and building operations must be protected with
barricade fencing to prevent damage from soil stockpiling and compaction of the root zone,
parked cars and machinery
7. All native plant species located in group plantings shall not be subjected to any hedging
maintenance regimes.
8. All environmental weeds located east of the building line are to be removed prior to the
commencement of all revegetation works
9. All street trees and internal trees 45 litres and greater must be securely staked and tied to
assist their growth during the establishment period
10. The density of planting must achieve the set out requirements as detailed on the approved
landscape plan.
11. The applicant must ensure that all landscaping treatment does not unduly restrict/prevent
access to service meters within the site.
12. All trees must be located a minimum of a minimum of 1.0 metres from all services to prevent
root/service conflict and to provide future ease of maintenance requirements.
13. This Preliminary Approval for Operational Works lapses on 2 February 2012, unless
application to extend the currency is approved by Council.
Land Development
14. The development shall be carried out in accordance with Drawing Nos. 05/236-OP1 dated
December 2006 and 05/236-OP2 dated January 2006 prepared by John Norden & Associates
or as modified herein.
15. Roof and surface runoff connection to on site disposal and kerb and channel shall be as
shown on John Norden & Associates Drawing Nos. OP1 and OP 2. Kerb adapters shall be
used in the kerb.
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval - 010.2006.00000676.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.