SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 MAY 2022
21-22 Capital Projects
27%
Non Grant Capital Projects
Projects with Grant Funding
73%
Figure 1
Figure 2 detail Percentage of CWP Value of CWP
Non grant projects 27% $11.4m
Grant funding revenue 39% $25m
Councils contribution to projects with grant funding 34% $17.2m
21-22 Capital Projects
27%
Non Grant Capital Projects
34%
Grant Funding Revenue
Noosa Councils Contribution to
Grant funded projects
39%
Figure 2
4. Completed Projects
While the third quarter has been impacted by flood and continued to experience a heated
construction market with ongoing material shortages, lengthy lead times, pricing increases and
contractor availability issues; 22.6% of capital expenditure has been completed this quarter
bringing total expenditure to 49.6% of the 2021/2022 budget. Moving forward into the final quarter
Page 11 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.