Decision Notice - 010.2009.00000928.001 [As Published] · 142009.928

of 6

Text shows just the words. Original shows the document exactly as it was published.

                                                                                         2009/928



4.    A site control and/or compliance bond of $500 is to be submitted to Council prior to the pre-
      start meeting. The pre-start meeting will only be held once Council's Construction Technical
      Officer has confirmation that Council has received the bond monies.
      The bond will be refunded less any costs incurred by Council in ensuring compliance with
      these conditions or any additional inspections incurred for substandard work or work
      undertaken not in accordance with this permit.
5.    Council’s Construction Technical Officer (phone 0410 512 505) shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of those works.
6.    The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any subcontractors also have the appropriate insurance and public liability documentation.
7.    Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
8.    Council standards shall apply to these works unless otherwise modified herein.
9.    The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture, etc.) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify Council’s CEO and shall forthwith rectify the damage to that property or facility
      at its cost and to the satisfaction of Council’s CEO.
      All rectification works are to be completed prior to the commencement of the use or,
      alternatively, the Applicant may request Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
      of the use.
      In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
      the Applicant, such cost being paid prior to the commencement of the use.
10.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
11.   Construction work and other associated activities are permitted only during the hours of 7.00
      am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
      except where extended hours are approved by Council’s CEO.
12.   All signage, including that for safety during construction, shall be in accordance with the
      Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
13.   Safe pedestrian access in the vicinity of the development shall be maintained at all times. If
      footpath / road closures are necessary to carry out construction works, Council’s Construction
      Technical Officer (phone 0410 512 505) must be notified prior to the proposed closure.
14.   Sediment and erosion control measures must be in place prior to works commencing. If such
      measures are not in place or are not satisfactory, “on the spot “ fines may be issued. Such
      fines can be issued if sediments from the site are found to enter or have the potential to enter
      Council’s stormwater system or natural waterways. Although the sediment and erosion control
      measures have been approved, it is the site Supervising Engineer who is responsible for
      ensuring that the sediment and erosion control measures have:


                                                                                       Page 2 of 6

Used in these records

About this file

File size
54 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2009.00000928.001 [As Published].pdf · 54 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.