Council archive · source document
16844 CAR notice · OPW14/0370
Attached to the e-mail OPW14/0370 - Concurrency Agency Response with conditions.
SARA reference: SDA-1214-016844
Council reference: OPW14/0370
12 February 2015
Noosa Shire Council
PO Box 141
TEWANTIN QLD 4565
Dear Mark Lewis
Concurrence agency response—with conditions
Cnr William Street and Gympie Terrace, Noosaville QLD 4566
(Given under section 285 of the Sustainable Planning Act 2009)
The referral agency material for the development application described below was received
by the Department of State Development, Infrastructure and Planning under section 272 of
the Sustainable Planning Act 2009 on 23 December 2014.
Applicant details
Applicant name: Noosa Shire Council
Applicant contact details: PO Box 141
TEWANTIN QLD 4565
[email protected]
Site details
Street address: Cnr William Street and Gympie Terrace, Noosaville
Real property description: Lot 1 RP65319
Local government area: Noosa Shire Council
Application details
Proposed development: Development Permit for Operational Works (Prescribed tidal
works – Revetment wall and footpath upgrade)
Referral triggers
Page1
SEQ North Region
Level 8, Mike Ahern Building
12 First Avenue
PO Box 1127
Maroochydore QLD 4558
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 5 pages
Page 2
SDA-1214-016844
The development application was referred to the department under the following
provisions of the Sustainable Planning Regulation 2009:
Referral trigger Schedule 7, Table 2, Item 13 – Tidal works, or development in a
coastal management district (Coastal management)
Schedule 7, Table 2, Item 15 – Tidal works, or development in a
coastal management district (Maritime safety)
Conditions
Under section 287(1)(a) of the Sustainable Planning Act 2009, the conditions set out in
Attachment 1 must be attached to any development approval.
Reasons for decision to impose conditions
Under section 289(1) of the Sustainable Planning Act 2009, the department must set out the
reasons for the decision to impose conditions. These reasons are set out in Attachment 2.
Approved plans and specifications
The department requires that the following plans and specifications set out below and as
enclosed must be attached to any development approval.
Drawing Title Prepared by Date Reference no. Revision
Aspect of development: Operational works
Project Cover Sheet Noosa Shire 22 October 0000009 01 N/A
Council 2014
Existing Features Noosa Shire 22 October 0000009 02 N/A
Council 2014
Plan and Cross Sections Noosa Shire 22 October 0000009 03 N/A
Council 2014
Long Section Alignment 1 Noosa Shire 22 October 0000009 04 N/A
Council 2014
Long Section Alignment 2 Noosa Shire 22 October 0000009 05 N/A
Council 2014
Long Section Alignment 2 (2) Noosa Shire 22 October 0000009 06 N/A
Council 2014
Typical Construction Detail 1 Noosa Shire October 2014 0000009 07 N/A
Council
Typical Construction Detail 2 Noosa Shire 22 October 0000009 08 N/A
Council 2014
Plan and Cross Sections Noosa Shire 23 October 0000009 03 Revision A
Council 2014
Department of State Development, Infrastructure and Planning Page 2
Page 3
SDA-1214-016844
A copy of this response has been sent to the applicant for their information.
For further information, please contact Tracey Smith, Senior Planning Officer, on 07 3882 8409, or
email [email protected] who will be pleased to assist.
Yours sincerely
Garth Nolan
Manager (Planning)
cc: Noosa Shire Council, [email protected]
enc: Attachment 1—Conditions to be imposed
Attachment 2—Reasons for decision to impose conditions
Approved Plans
Department of State Development, Infrastructure and Planning Page 3
Page 4
SDA-1214-016844
SARA reference: SDA-1214-016844
Council reference: OPW14/0370
Attachment 1—Conditions to be imposed
No. Conditions Condition timing
Operational works
7.2.13 Tidal works (coastal management)—Pursuant to section 255D of the Sustainable Planning
Act 2009, the chief executive administering the Act nominates the Director-General of the
Department of Environment and Heritage Protection to be the assessing authority for the
development to which this development approval relates for the administration and enforcement of
any matter relating to the following condition(s):
1. The development must be carried out generally in accordance At all times
with the following plans:
Project Cover Sheet, prepared by Noosa Shire Council,
reference no. 0000009 01, dated 22 October 2014.
Existing Features, prepared by Noosa Shire Council,
reference no. 0000009 02, dated 22 October 2014.
Plan and Cross Sections, prepared by Noosa Shire
Council, reference no. 0000009 03, dated 22 October
2014.
Long Section Alignment 1, prepared by Noosa Shire
Council, reference no. 0000009 04, dated 22 October
2014.
Long Section Alignment 2, prepared by Noosa Shire
Council, reference no. 0000009 05, dated 22 October
2014.
Long Section Alignment 2 (2), prepared by Noosa Shire
Council, reference no. 0000009 06, dated 22 October
2014.
Typical Construction Detail 1, prepared by Noosa Shire
Council, reference no. 0000009 07, dated October 2014.
Typical Construction Detail 2, prepared by Noosa Shire
Council, reference no. 0000009 08, dated 22 October
2014.
Plan and Cross Sections, prepared by Noosa Shire
Council, reference no. 0000009 03, dated 23 October
2014, revision A.
2. During the construction phase of the works: For the duration of
a) Install and maintain all measures, plant and equipment the works the subject
necessary to ensure compliance with these conditions. of this approval
b) Only use materials which are:
i) Clean and free of silt;
ii) Free from pests, chemicals and other
contaminants as defined under section 11 of the
Environmental Protection Act 1994; and
iii) Suitable for the purpose; and
c) Promptly remove any material or debris which has been
deposited within the coastal management district or tidal
waters, other than in accordance with this approval.
3. Erosion and sediment control measures must be installed and Prior to
maintained to prevent the release of sediment into tidal waters. commencement of
the works and
Department of State Development, Infrastructure and Planning Page 4
Page 5
SDA-1214-016844
No. Conditions Condition timing
maintained until their
completion
4. Should the works become damaged as a result of erosion, At all times
flooding or storm tide inundation, the registered landowner(s) of
the land to which the works are attached, shall be responsible for
the collection and removal of all debris, previously being a part of
the works, at their own expense.
5. Any disturbed or oxidised acid sulfate soil must be treated and For the duration of
managed in accordance with the current Queensland Acid Sulfate the works the subject
Soil Technical Manual: Soil Management Guidelines v4.0, of this approval.
prepared by the Department of Science, Information Technology,
Innovation and the Arts, 2014.
7.2.15 Tidal works (maritime safety)—Pursuant to section 255D of the Sustainable Planning Act
2009, the chief executive administering the Act nominates the Director-General of the Department
of Transport and Main Roads to be the assessing authority for the development to which this
development approval relates for the administration and enforcement of any matter relating to the
following condition(s):
6. Provide written notice to the Regional Harbour Master (Brisbane), When the
Maritime operations Base, MacArthur Avenue East, PINKENBA development
QLD 4008, when the development authorised under this approval authorised under this
has started, and when it has been completed. approval has started
These notices must state this permit number, the location and and when it has
name of registered place and the condition number under which been completed
the notice is being given.
7. “As constructed” drawings must be provided to the Regional Within two weeks of
Harbour Master (Brisbane), Maritime operations Base, MacArthur the completion of the
Avenue East, PINKENBA QLD 4008. works
8. The structure must be lit/marked in accordance with section 3 of At all times
AS4282-1997 ‘Control of the obtrusive effects of outdoor lighting’,
such that it does not cause a risk to the safe navigation of other
ships.
9. Any navigational aid that is damaged due to the construction, At all times
operation or maintenance of the approved development must be
promptly repaired or replaced at the applicant’s cost. In the event
that any damage is caused to any aid to navigation, the Harbour
Master must be immediately contacted on 07 3305 1700.
10. The construction, operation or maintenance of the structures, and At all times
any ship moored at this structure, must not impede the safe
navigation of other ships or restrict safe access to or from
neighbouring structures.
11. Any debris or similar obstruction encountered whilst undertaking Prior to the
the work must be promptly and suitably disposed of at the completion of the
applicant’s cost. works.
Department of State Development, Infrastructure and Planning Page 5
Page 6
SDA-1214-016844 SARA reference: SDA-1214-016844 Council reference: OPW14/0370 Attachment 2—Reasons for decision to impose conditions The reasons for this decision are: To ensure the development is carried out generally in accordance with the plans of development submitted with the application. To ensure the development avoids or minimises adverse impacts on coastal resources and their values. To ensure landowners are aware they must take responsibility for their damaged property s they can impact on coastal resources and public safety. To ensure any acid sulfate soils present are managed to protect the coastal environment. To facilitate the monitoring of the development works for compliance purposes. To ensure the development does not encroach on the navigable waterway in a way that impedes the safe passage of vessels. To ensure that at all times, all lights on or above the development site do not interfere with safe navigation in surrounding waterways. Department of State Development, Infrastructure and Planning Page 6
Used in these records
16844 CAR notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 224 KB (small file)
- File type
No other editions are linked here.