CONDITIONS AND STATEMENT OF REASONS

Application type: Material change of use

 

Councit: Noosa Shire Main Roads File No: 92/145/D7950
Council Ref: 2007/2398 Road: Cooroy Connection Road
Development Number: 7950
Response Date: 16 January 2008
ISSUES / CONDITIONS OF DEVELOPMENT FOR | THE REASONS, INFORMATION,
CONCERNS THE SUBJECT APPLICATION STUDIES, FINDINGS, USED IN
SETTING OF CONDITIONS
INCLUDED:

 

Management of access
to a State-controlled
Toad.

There shall be no direct access to Cooroy
Connection Road, All access is to be via
Pearsons Road or Lamonts Road.

By minimising the number of points of
access to the State-controlled road
network, safety and efficiency are
maximised.

 

Works within the State-
controlled road reserve.

The applicant is to upgrade the Cooroy
Connection Road / Pearsons Road intersection
to incorporate a channelised right tum lane
(Type CHR) as shown on Figure 13.60 of
Main Roads' document, "Road Planning and
Design Manual".

The applicant is to upgrade the Cooroy
Connection Road / Lamonts Road intersection
to a Type BAR standard as shown on Figure
13.58 of Main Roads’ document, "Road
Planning and Design Manual".

Prior to the commencement of any works
within the State-controlled road, the applicant
must arrange for detailed engineering plans
and specifications for the proposed works to
be submitted to Main Roads for assessment
and be approved.

The engineering design, plans and
specifications submitted must be certified by
an appropriate Registered Professional
Engineer Qld (RPEQ).

Note: Further approvals will be required for
construction in accordance with the
requirements of section 33 of the Transport
Infrastructure Act 1994.

Main Roads’ Road Planning and Design
Manual, Chapter 13 — Intersections at
Grade.

Traffic study submitted by McConmick -
Rankin Cagney.

Works to be in accordance with Main
Roads Technical Manuals, Policies and
Guidelines together with relevant State
and National Standards.

 

 

Cost of works.

 

All works associated with this proposal,
including relocation of services, lighting, etc.
must be carried out at no cost to Main Roads.

 

The works are required to enable the
development to proceed without
compromising the safety and efficiency
of the State-controlled road network.

 

 

Used in these records

About this file

File size
6.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2398 - Revised Noise Report and cover letters to referral agencies [As Published].pdf · 6.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.