Appendix C - Ecological Assessment Report
PO5 AO5 AO5
Development is designed and operated to Development is designed and operated to maintain Complies with AO5 - All existing ecological
maintain and enhance connectivity between ecological linkages and maximise opportunity for linkages will be retained.
and across ecologically important areas and connectivity and the movement of fauna by:
connecting habitat and support unimpeded a) ensuring protection of wildlife refuges;
and safe movement of terrestrial and b) maintaining vegetation in patches of the greatest
aquatic fauna. possible size and within the smallest possible
edge-to-area ratio;
c) enhancing connectivity through planting and
rehabilitation works, including across property
boundaries, to areas of national park, state forest
or reserve;
d) avoiding the creation of physical barriers and
safety hazards (such as roads, pedestrian access
and instream structures) along and within the
ecological linkage;
e) providing mitigation measures such as wildlife
movement infrastructure, fauna exclusion and
directional fencing, underpasses/overpasses and
traffic calming devices, signage and lighting; and
f) where offsets are necessary, delivering offsets that
support and enhance ecological linkages.
Waterways and Wetlands
PO6 AO6.1 Development cannot avoid being undertaken
The biodiversity and ecosystem values of Development and clearing of vegetation does not occur within the mapped Riparian Buffer Area which
waterways, drainage lines, wetlands and within: covers the entire site. Therefore, the application
adjacent riparian zones are protected by: a) a riparian buffer area; cannot meet Acceptable Outcome 6.1. In this
a) avoiding any new development in a b) a wetland area; or regard, an assessment against the purpose and
riparian buffer area and wetland c) 10 metres either side of the centre line of other overall outcomes of the Biodiversity Wetlands and
area; waterways identified on a Biodiversity, Waterways Waterways Overlay Code has been undertaken
b) retaining aquatic and terrestrial and Wetlands Overlay Map. and presented in Section 7.2 below.
habitat in riparian zones;
c) maintaining and enhancing wildlife AO6.2 AO6.2
corridors and connectivity along Development provides for the rehabilitation of land within: A Riparian Rehabilitation Plan has been prepared
watercourses and drainage lines for a) a riparian buffer area; which details the proposed rehabilitation strategy
native fauna movement; b) a wetland area; and within the waterway corridor which is the
d) avoiding edge effects and damage c) 10 metres either side of the centre line of any other predominant ecologically important area located
from adjacent land uses; waterway identified on a Biodiversity, Waterways within the site.
and Wetlands Overlay Map.
APRIL 2023 ECOLOGICAL ASSESSMENT REPORT Page: 14
157 LAWNVILLE ROAD, BLACK MOUNTAIN
See the original