Delegated Report - Code - Planning OPW25/0036 (As Published)

of 8

Page text shows just the words. Original shows the document exactly as it was published.

                   Street address:               45 Cormorant Cres Peregian Beach Qld 4573

                   Real property description:       Lot 75 P 9317

                   Planning Scheme:              Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works – Vehicle Crossover
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                            Plan No.            Rev.    Plan/Document Name                        Date

                            S25-023-C02         C       “Civil Works Plan”                        28/02/2025
                                                        Prepared by Westera Partners
                                                        (AS ANNOTATED IN RED BY COUNCIL)

               CURRENCY PERIOD
               2.      The Currency Period for this development approval lapses if the development has not
                       substantially started by 20 March 2027, unless an application to extend the currency period
                       is approved by Council.
               SITE SPECIFIC CONDITIONS
                       Bonds
               3.      A site control and/or compliance bond of $5,000 is to be submitted to Council prior to the
                       prestart meeting. The prestart meeting will only be held once Council's Construction
                       Engineering Officer has confirmation that the bond monies have been received by Council.
                       The bond will be refunded less any costs incurred by Council in ensuring compliance with
                       these conditions or any additional inspections incurred for substandard work or work
                       undertaken not in accordance with this permit.
               4.      Bonds must:
                       a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                               and uncompleted works;
                       b.      be lodged with Council; and
                       c.      be requested for release by writing to Council, when relevant approval requirements
                               have been met.
                       Stormwater Bund
               5.      Location and alignment of the proposed 200mm high bund (to direct runoff into existing
                       stormwater pit), as shown in the approved plan, is to be agreed upon at prestart meeting and
                       must be constructed to avoid the creation of trip hazards.


                                                                                                      Page 4 of 8

Document Set ID: 23638693
Version: 3, Version Date: 19/03/2025
Log in to download the original file

Delegated Report - Code - Planning OPW25_0036 (As Published).pdf · 2.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.