4. ASSESSMENT MANAGER CONDITIONS
1. Submission to and approval by Council of building plans in accordance with the Building Act,
Council’s By-Laws and Policies, and generally in accordance with the plan approved in this
Consent and the Shire of Noosa Town Planning Scheme apart from where amendments are
required or dispensation have been granted in conjunction with this Consent.
2. The plans submitted for Building Approval following requirements are to comply with the
a. Amendment to car parking layout to accord with Council policies and to allow
satisfactory manoeuvring, to the satisfaction of the Shire Engineer.
b. Deleted
3. Provisions of at least three (3) off-street car parking spaces, comprising 2 covered spaces
and 1 uncovered spaces, and access thereto, which are to be provided with a sealed
pavement and designed, drained, constructed and maintained in accordance with the Town
Planning Scheme, Council’s Policies and to the reasonable satisfaction of the Shire
Engineer. Plans and Specifications for these works are to be submitted to the Shire Engineer
for approval in conjunction with the Building Application.
4. There is to be no detrimental effect upon the amenity of the neighbourhood by reason of the
creation of excessive noise, lighting nuisance or other emissions.
5. The open space and setback areas are to be landscaped in accordance with the Noosa
Design Manual and properly prepared landscaping plan to be submitted to and approved by
the Shire Planner, prior to the issue of a Building Approval. Such landscaping is to be
completed in accordance with the approval landscaping plan, prior to the premises being
occupied and maintained at all times thereafter to the reasonable satisfaction of the Shire
Planner.
6. Existing trees are to be retained, except where required to be removed due to building
operations or the conduct of the approved use. In this regard exiting trees proposed to be
retained at the rear of the site are to be noted on the landscaping plans submitted wit the
building application.
7. Construction work is permitting only during the hours of 7.00a.m. to 6.00p.m. Monday to
Saturday and no construction work is permitted on public holidays, except where extended
hours are approved by the Building Surveyor.
8. Payment of contributions in accordance with Council’s Policy on Water Supply and Sewerage
Headworks, current at the time of Building Approval. Calculations bases upon the current
Policy including Price Index variation as at November, 1988 are estimated as follows:-
Water Supply - $1220
Sewerage - $ 630
TOTAL: $1850
If Payment is not proposed to be made prior to the issue of Building Approval, a cash bond
or trading bank guarantee for the required amount is to be lodged prior to the release of that
Approval. The contribution is then required to be made with in fourteen (14) days of the issue
of Building Approval.
9. The footpath across the frontage of the site shall be generally upgraded involving reshaping,
grassing and topsoiling to the satisfaction of the Shire Engineer.
10. The developer shall bear the cost of alteration of any public utility or facilities necessitated
by the development of the land or associated construction works external to the site.
11. Connection to Council’s existing water supply reticulation systems at the developer’s
expense to the standards and requirements of Council’s Shire Engineer.
Page 2 of 6
Document Set ID: 22658807
Version: 2, Version Date: 10/11/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - 51988 2740 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 160 KB (small file)
- File type
No other editions are linked here.