               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Senior Development Engineer, Daniel Epps
                                       Development Assessment



                  APPLICATION DETAILS

                  Application No.                  OPW24/0151

                  Applicant                        Brennan Planning Pty Ltd

                  Proposal                         Operational Works - Frontage Work, Landscaping, Clearing
                                                   Vegetation under planning scheme, Vehicle Crossover

                  Properly Made Date               20 September 2024

                  Information Request Date         4 October 2024

                  Information Response Date        8 November 2024

                  Decision Due Date                2 January 2025

                  Report Reviewed &                Mark Lewis – 2 January 2025
                  Finalised By


                  PROPERTY DETAILS

                  Property Address                 41 Tallowwood Pl Black Mountain Qld 4563

                  RP Description                   Lot 36 RP 897845

                  Land Area                        24820.000 m²

                  Existing Use of Land             Residential


                  STATUTORY DETAILS

                  SEQRP Designation                Rural Living Area

                  Zone                             Rural Residential

                  Precinct                         Not applicable

                  Local Plan Area                  Not applicable

                  Overlays                         Biodiversity, Waterways and Wetlands
                                                   Bushfire Hazard
                                                   Landslide Hazard
                                                   Koala Habitat Area

                  Assessment Type                  Code




Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025
Full text of the other 12 pages

Page 2

               1.     PROPOSAL
               The application seeks approval for a Operational Works - Frontage Work, Landscaping, Clearing
               Vegetation under planning scheme, Vehicle Crossover.
               The locality and proposal plan are included below.




                                                       Figure 1 – Locality




                                                      Figure 2 – Site Plan




                                                                                               Page 2 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 3

                                                      Figure 3 – Driveway Plan

               2.     APPLICATION BACKGROUND
               The application sets out to address the conditions of the higher order approval (RAL24/0003).
               3.     SITE DETAILS
               3.1. Site Description
               The subject site is an irregular shaped, ~24,795m2 lot. The lot generally grades to the north towards
               an existing mapped waterway. Approximately 50% of the lot is densely vegetated.
               During an inspection, Council officers identified an existing stormwater pit within the Tallowwood
               Road Reserve that discharged within the subject site. The exact drainage outlet was unable to be
               identified. An investigation was conducted by the applicant’s Geotechnical Engineer who was
               unable to identify the outlet and determined the proposed work is unlikely to adversely affect the
               observable drainage conditions of the site.
               3.2. Surrounding Land Uses
               The surrounding lane uses are consistent with the subject subdivision.
               4.     ASSESSMENT
               4.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (25 September 2020).



                                                                                                      Page 3 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 4

               4.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •       Works Codes – Driveways and Parking, Water Quality and Drainage, Landscaping
               •       Overlay Code – Landside Hazard, Bushfire Hazard
               The application has been found to generally comply with all applicable statutory instruments.
               5.      CONSULTATION
               5.1. Referral Agencies
               Not Applicable
               5.2. Internal Council Referrals
               The application was forwarded to the following internal Council officers for review and/or comment:
               •       Senior Environment Officer, Development Assessment
               6.      CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW24/0151 for Operational Works - Frontage Work, Landscaping,
               Clearing Vegetation under planning scheme, Vehicle Crossover situated at 41 Tallowwood Pl Black
               Mountain Qld 4563 and described as Lot 36 RP 897845, it is recommended the application be
               approved in accordance with the following details for the Decision Notice:
               1.      APPLICATION DETAILS

                   Application No:               OPW24/0151

                   Street address:               41 Tallowwood Pl Black Mountain Qld 4563

                   Real property description:    Lot 36 RP 897845

                   Planning Scheme:              Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for an Approval Operational Works - Frontage Work, Landscaping,
                       Clearing Vegetation under planning scheme, Vehicle Crossover
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.   Plan/Document Name                        Date

                                                                                                      Page 4 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 5

                           2251-101          B       Cover Sheet and Drawing Index                  24   October
                                                                                                    2024
                                                     Prepared by Callaghan & Toth

                           2251-102          B       Layout and Notes Plan                          24   October
                                                                                                    2024
                                                     Prepared by Callaghan & Toth

                           2251-103          B       Setout and Details Plan                        24   October
                                                                                                    2024
                                                     Prepared by Callaghan & Toth

                           2251-104          B       Driveway Cross Sections and Longitudinal 24   October
                                                     Section Plan                             2024
                                                     Prepared by Callaghan & Toth

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 24 December 2026, unless an application to extend the currency
                      period is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Bonds
               3.     Prior to the prestart meeting for the rehabilitation works, a bank guarantee or a bond of
                      $10,000 must be lodged as security for the completion of the rehabilitation works and three
                      year performance maintenance period identified in the conditions of this approval.
               4.     A site control and/or compliance bond of $5,000 is to be submitted to Council prior to the pre-
                      start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               5.     Bonds must:
                      a.      have approval of the bond calculations and amount from Council prior to lodgement
                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               6.     Prior to requesting a prestart meeting:
                      a.      Submit to Council an amended Bushfire Management Plan in accordance with
                              Condition 9 of the higher order RAL24/0003.
                      b.      Submit to Council a rehabilitation species palette for the covenant area made up of
                              species selected from Regional Ecosystem 12.11.10 described as ‘notophyll vine
                              forest’
               7.     All necessary approvals from external service providers and external parties on which the
                      development works are proposed have been obtained and a copy supplied to Council.
               8.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.


                                                                                                       Page 5 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 6

               9.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               10.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Rehabilitation / Revegetation works;
                      d.      Erosion and sediment control works; and
                      e.      Other relevant parties.
               11.    A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      Traffic management during all phases of construction;
                      b.      Adequate parking arrangements for works and deliveries;
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD); and
                      d.      provision for safe vehicle and pedestrian access across the frontage of the site both
                              during daily construction and after daily construction has ceased.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Reconfiguration of Lot approval viz.
                              RAL24/0003 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.



                                                                                                      Page 6 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 7

                      Works within Road Reserve/Reinstatement
               17.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               18.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               19.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Site Access and Driveways
               20.    Driveway crossovers must be constructed in accordance with council’s Standard Drawings
                      RS-056 and any associated addendum.
               21.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               22.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete or an approved all-weather purpose material;
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway;
                      d.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path; and
                      e.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               23.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council.
               24.    Fall protection must be provided to retaining walls that are over 1m high.
               25.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;
                      c.      1 in 3 for planted areas; and
                      d.      1 in 2 for combined structural engineering and planting solutions.



                                                                                                        Page 7 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 8

                      Stormwater Drainage
               26.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               27.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g., by blocking or interfering with natural overland flows).
               28.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Retention of Existing Trees and Vegetation
               29.    All trees and vegetation identified for retention must be protected in accordance with AS
                      4970, Protection of trees on development sites.
                      Clearing of Vegetation
               30.    Prior to felling or pruning, all trees are to be inspected for wildlife (i.e. koalas, possums, birds’
                      nests etc). If wildlife is present, the tree must not be felled or pruned until the wildlife has left
                      the tree or has been removed by a qualified person*.
                      *(Refer to Advisory Note)
                      Plant Pest Management
               31.    A qualified person* must manage plant pest (weeds) to:
                      a.      Ensure plants listed as Class 1, 2 declared pests and environmental weeds within
                              Council’s Pest Management Plan are controlled and prevented from spreading.
                      b.      Oversee management techniques that minimise regrowth, prevent damage to non-
                              target species, retain conservation values and maintains site stability.
                      *(Refer to Advisory Note)
                      Land Rehabilitation
               32.    Rehabilitation works must be supervised, undertaken and certified by qualified persons*.
                      Where the removal of weed species creates cleared areas within the covenant, these areas
                      must be revegetated utilising native species from the local Regional Ecosystem 12.11.10.
                      Trees and shrubs must be planted in these cleared areas at a rate of one plant per metre.
               33.    A clause must be included in the contract of sale for proposed Lot 362 which provides
                      unlimited maintenance access to the Covenant for rehabilitation / revegetation works to take
                      place. This access must be granted until the rehabilitation works have met all performance
                      criteria and confirmed off maintenance by Council.
               34.    The following amounts of the bank guarantee/bond may be returned at the end of each
                      performance criteria year following Council approval as follows:
                      a. Year 1 - $5,000
                      b. Year 2 - $3,000
                      c. Year 3 - $2,000
               35.    The Rehabilitation supervisor must annually:
                      a.      Organise formal inspection with Council’s delegate*.
                      b.      Submit to Council (with each inspection request) a Rehabilitation Status Report (written
                              and photographic), mapping:
                              i.       The condition of the regeneration area.
                              ii.      Detailing works undertaken in the previous year.
                              iii.     The percentage cover of indigenous recruitment.
                              iv.      Measuring the works against the conditioned Performance Criteria.

                                                                                                            Page 8 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 9

                      *(Refer to Advisory Notes)
               36.    Rehabilitation works must meet the following Performance Criteria for:
                      a.      Year One – 12 months after installation:
                              i.       Planted trees have achieved an average height of 1m.
                              ii.      Planted shrubs have achieved an average height of 0.4m.
                      b.      Year Two - 24 months after the installation:
                              i.       Planted trees have achieved an average height of 2m.
                              ii.      Planted shrubs have achieved an average height of 1m.
                      c.      Year Three - Final acceptance installation:
                              i.       Planted trees have achieved an average height of 3m.
                              ii.      Planted shrubs have achieved an average height of 1.2m.
                              iii.     Canopy and / or vegetative strata must not be devoid for any area greater than
                                       1.0m2 within any 10m2 sample.
                              iv.      Plant density shading out and/or self-mulching.
                      d.      The duration of the establishment period:
                              i.       Adherence to maintenance regime for rehabilitation and revegetation areas.
                              ii.      No evidence of woody weeds reshooting from stumps, poisoned trees or the
                                       regrowth of cut stumps.
                              iii.     No evidence of over-weeding or impact on non-target species.
                              iv.      Signs of indigenous recruitment in rehabilitation areas.
                              v.       Weed infestations less than 5% of the rehabilitation areas.
                              vi.      Any failed plants within the previous 12 month period have been replaced.
                              vii.     Healthy and vigorous growth allowed to grow to full form.
                              viii.    Mulch layer sufficient to suppress weeds.
                      Erosion and Sediment Control
               37.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               38.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;
                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.


                                                                                                        Page 9 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 10

                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               39.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               40.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               41.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
               42.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term.
                      For the purpose of this condition, an effectively stabilised surface is defined as one that does
                      not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
                      or lead to sedimentation, or lead to water contamination.
                      Damage to Services and Assets
               43.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Bonds
               44.    Bonds must:
                      a.      Meet the requirements of the relevant Council Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      Be calculated using a schedule of works and relevant bond equation.
                      c.      Include GST.
                      d.      Have approval of the bond calculations and amount from Council, prior to lodgement.
                      e.      Be lodged with Council and accompanied by the Bond Administration Fee/s.
                      f.      Be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               45.    Performance Bonds must be lodged for:
                      a.      Rehabilitation.
                      On Maintenance
               46.    Maintenance periods* must be:


                                                                                                            Page 10 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 11

                      a.      36 months for Rehabilitation
                      *(Refer to Advisory Note)
               47.    Prior to requesting an On Maintenance inspection, the following information package
                      (prepared by respective qualified persons* and certifying compliance with approvals) must
                      be submitted to Council:
                      a.      All required bonds.
                      b.      Rehabilitation / Revegetation certification.
                      Off Maintenance
               48.    Prior to requesting an Off Maintenance inspection, the following must be provided:
                      a.      Completion of all rehabilitation works
                      b.      Written request of bond release.
               49.    Off Maintenance Inspection must be requested:
                      a.      By contacting Council.*
                      b.      Only after lodgement of a completed rehabilitation certification
                      *(Refer to Advisory Note)
                      Certification
               50.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               51.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               5.     REFERENCE DOCUMENTS

                Plan No.        Rev.    Plan/Document Name                                       Date

                2251-           B       Coversheet and Drawing Index, prepared by, 10/24
                101                     Callaghan & Toth

               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawings RS-056 and
                      any associated addendum.
               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.


                                                                                                        Page 11 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 12

               3.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               4.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance, Rehabilitation Inspections Request
               5.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               6.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               7.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Retention of Existing Trees
               8.     The existing trees on adjoining properties must be retained and protected during construction
                      wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
                      operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
                      construction of the development which is the subject of this development approval.
                      Removal of Existing Trees and Vegetation
               9.     Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
                      well as optimum weed seed sterilisation.
                      Qualified Person
               10.    Qualified Person, for the purpose of:
                      a.      Undertaking rehabilitation construction and establishment works is considered to be a
                              person with five years current experience in revegetation and regeneration.
                      b.      Preparing certification and managing declared plant pests, is considered to be:
                              i.       a landscape architect with a minimum of 3 years current experience in the field
                                       of pest plant management;
                              ii.      a botanist or ecologist with a minimum of 3 years current experience in the field
                                       of pest plant management;
                              iii.     an environmental consultant with a minimum of 3 years current experience in the
                                       field of pest plant management.
                      On Maintenance
               11.    Request for On Maintenance is the responsibility of the developer. No credit will be given
                      due to failure to request inspection. Maintenance works are the responsibility of the
                      developer and must include regular inspections, repairs, rectifications and establishment. A
                      single maintenance run immediately prior to inspection is not acceptable.
                      Off Maintenance
               12.    A re-inspection fee in accordance with Councils Fees and Charge Register will be charged
                      where:
                      a.      A Council inspection reveals works do not comply with approval requirements.
                      b.      Submitted certification falsely states works comply with approval requirements.
                      Environmental Advisory Notes

                                                                                                         Page 12 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Page 13

               13.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               14.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               15.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               16.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Performance Bond Agreement
               17.    An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                       Page 13 of 13

Document Set ID: 23391417
Version: 5, Version Date: 06/01/2025

Used in these records

About this file

File size
2.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW24_0151 (As published).pdf · 2.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.