               4.     ASSESSMENT MANAGER CONDITIONS

                                 STANDARD CONDITIONS FOR MULTIPLE DWELLINGS – TPC808
               1.     Compliance with all relevant by-laws and policies.
               2.     Minimum disturbance to natural flora. No vegetation to be removed other than that which
                      would impede building operations. Where practicable, re-vegetation to be carried out
                      following cessation of building activity.
               3.     Permanent covered car parking to be provided on the site for three vehicles, together with
                      space sufficient for one visitors' vehicles. Areas on which vehicles will be driven and/or
                      parked to be provided with a flexible or other pavement surfaced with bitumen seal coat,
                      asphaltic or other concrete properly constructed and maintained to good engineering
                      standards to the satisfaction of the Council's Engineer. Plans and specifications for such
                      areas including footpath crossings to be submitted prior to issue of a building permit.
                      Vehicular access to and from the site to be designed so as to ensure that sufficient area is
                      available for manoeuvring and turning to permit forward movement to and from the road.
               4.      A concrete invert and paved access to connect to the existing bitumen road pavement to be
                      constructed to the satisfaction of the Council's Engineer.
               5.     a) deleted
                      b) deleted
                      OR
                      (c) Connection to Council’s sewerage system.
               6.     Connection to Council's water supply facility at the applicant's expense.
               7.     Stormwater, including that from roofed and paved areas to be disposed of by underground
                      means to Council’s existing disposal facilities in the adjacent kerb and channel.
               8.     No earthworks or filling are to be carried out on the site until the requirements of the Council's
                      Engineer have been obtained in writing. Such requirements to be obtained prior to the issue
                      of a building permit.
               9.     Comply with the reasonable requirements of the Regional Fire Safety Officer.
               10.    The approval given herein is for Town Plan Consent only and does not imply either the issue
                      of a building permit or Council consent to an application under the Group Titles Act or Building
                      Unit Titles Act.
               11.    This approval will lapse if not availed of within two (2) years in accordance with clause 3 (2)
                      of Part II of Council By-laws Chapter XLIV - Town Planning.
               12.    A certificate of alignment to be submitted with the application for a building permit and/or an
                      identification survey to be carried out by an authorised surveyor at the time of the foundation
                      inspection.
               13.     To ensure compliance with any and all conditions of this approval, Council will require that
                      you enter into a Bank Bond to guarantee performance.
                      The value of such bond would be determined and would need to be lodged prior to issue of
                      a building permit and any costs incidental thereto will be the applicant's responsibility.
               14     The conditions of this consent are to be completed prior to occupancy of the building and if
                      this is not done, Council reserves the right to call on bond moneys lodged to carry out the
                      works involved.
                                        ADDTIIONAL CONDITIONS - 19 November 2004
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are titled Location of Spas - Exclusive
                      use Areas on GTP472 County March Parish Weyba Sketch Plan “A” dated 29.9.04 and
                      prepared by by D.R. Redman and as may be amended by these conditions.


                                                                                                          Page 2 of 5
Document Set ID: 24338657
Version: 3, Version Date: 27/11/2025
Log in to download the original file

Minor Change Existing Approval 51901 4147 05 - [As Published].pdf · 151 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.