Minor Change Existing Approval 51901 4147 05 - [As Published]
4. ASSESSMENT MANAGER CONDITIONS
STANDARD CONDITIONS FOR MULTIPLE DWELLINGS – TPC808
1. Compliance with all relevant by-laws and policies.
2. Minimum disturbance to natural flora. No vegetation to be removed other than that which
would impede building operations. Where practicable, re-vegetation to be carried out
following cessation of building activity.
3. Permanent covered car parking to be provided on the site for three vehicles, together with
space sufficient for one visitors' vehicles. Areas on which vehicles will be driven and/or
parked to be provided with a flexible or other pavement surfaced with bitumen seal coat,
asphaltic or other concrete properly constructed and maintained to good engineering
standards to the satisfaction of the Council's Engineer. Plans and specifications for such
areas including footpath crossings to be submitted prior to issue of a building permit.
Vehicular access to and from the site to be designed so as to ensure that sufficient area is
available for manoeuvring and turning to permit forward movement to and from the road.
4. A concrete invert and paved access to connect to the existing bitumen road pavement to be
constructed to the satisfaction of the Council's Engineer.
5. a) deleted
b) deleted
OR
(c) Connection to Council’s sewerage system.
6. Connection to Council's water supply facility at the applicant's expense.
7. Stormwater, including that from roofed and paved areas to be disposed of by underground
means to Council’s existing disposal facilities in the adjacent kerb and channel.
8. No earthworks or filling are to be carried out on the site until the requirements of the Council's
Engineer have been obtained in writing. Such requirements to be obtained prior to the issue
of a building permit.
9. Comply with the reasonable requirements of the Regional Fire Safety Officer.
10. The approval given herein is for Town Plan Consent only and does not imply either the issue
of a building permit or Council consent to an application under the Group Titles Act or Building
Unit Titles Act.
11. This approval will lapse if not availed of within two (2) years in accordance with clause 3 (2)
of Part II of Council By-laws Chapter XLIV - Town Planning.
12. A certificate of alignment to be submitted with the application for a building permit and/or an
identification survey to be carried out by an authorised surveyor at the time of the foundation
inspection.
13. To ensure compliance with any and all conditions of this approval, Council will require that
you enter into a Bank Bond to guarantee performance.
The value of such bond would be determined and would need to be lodged prior to issue of
a building permit and any costs incidental thereto will be the applicant's responsibility.
14 The conditions of this consent are to be completed prior to occupancy of the building and if
this is not done, Council reserves the right to call on bond moneys lodged to carry out the
works involved.
ADDTIIONAL CONDITIONS - 19 November 2004
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are titled Location of Spas - Exclusive
use Areas on GTP472 County March Parish Weyba Sketch Plan “A” dated 29.9.04 and
prepared by by D.R. Redman and as may be amended by these conditions.
Page 2 of 5
Document Set ID: 24338657
Version: 3, Version Date: 27/11/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original