Delegated Report - Code - Planning OPW23 0189 [As Published] · OPW23/0189

of 10

Text shows just the words. Original shows the document exactly as it was published.

               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW23/0189 for a Operational Works - Earthworks situated at 30
               Mossman Ct Noosa Heads Qld 4567 and described as Lot 149 N 21859, it is recommended the
               application be approved in accordance with the following details for the Decision Notice:
               1.      APPLICATION DETAILS

                   Application No:                  OPW23/0189

                   Street address:                  30 Mossman Ct Noosa Heads Qld 4567

                   Real property description:       Lot 149 N 21859

                   Planning Scheme:                 Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Approval for Operational Works - Earthworks
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.     Plan/Document Name                          Date

                          OW3.1                 .        Earthworks Plan                             October 2023
                                                         Prepared by SCG Consulting

                          SW1.1                 .        Basement Stormwater Management Plan         October 2023
                                                         Prepared by SCG Consulting

                          SW1.2                 .        Ground Level Stormwater Management          October 2023
                                                         Prepared by SCG Consulting

               CURRENCY PERIOD
               2.      The Currency Period for this development approval lapses if the development has not
                       substantially started by 23 February 2026, unless an application to extend the currency
                       period is approved by Council.
               SITE SPECIFIC CONDITIONS
                       Bonds
               3.      A site control and/or compliance bond of $5,000 is to be submitted to Council prior to the pre-
                       start meeting. The pre-start meeting will only be held once Council's Construction
                       Engineering Officer has confirmation that the bond monies have been received by Council.


                                                                                                        Page 4 of 10

Document Set ID: 22822217
Version: 3, Version Date: 23/02/2024

Used in these records

About this file

File size
1.8 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW23 0189 [As Published].pdf · 1.8 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.