Delegated Report - Code - Planning OPW23 0189 [As Published] · OPW23/0189
13. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
14. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserve/Reinstatement
15. Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
16. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
17. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Earthworks and Retaining Walls
18. All earthworks and associated retaining structures/batters, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
19. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as
defined in Appendix B. Test results as required by AS 3798.
20. All excavation and dewatering works must be undertaken in accordance with the
recommendations provided by ADG Consulting’s Dewatering Management Plan
(ADG1580.23, Rev. 0) dated 28 September 2023 and in a manner that will not cause
environmental harm or damage to surrounding infrastructure or property as a result of the
developments interaction with actual or potential Acid Sulphate Soils or groundwater.
21. All excavated material must be treated for Acid Sulfate Soils generally in accordance with
the recommendations provided by Pacific Geotechnical’s Acid Sulfate Soil Investigation
Report (PG-10899, Ver. 3) dated 28 November 2023.
Treated material must undergo verification testing at the rate of one sample per 250m3
throughout the duration of the excavation phase of the development. The verification testing
must be undertaken by a qualified person in accordance with the Queensland Acid Sulfate
Soil Technical Manual: Soil Management Guidelines v4.0, and the results must be submitted
to Council for appraisal when requested during construction and prior to commencement of
use and must demonstrate that the material has been adequately neutralised.
Certification of the verification results for compliance with this condition must be provided by
a suitably qualified Geotechnical Engineer prior to the issuing of the certificate of
classification for the dwelling.
Page 6 of 10
Document Set ID: 22822217
Version: 3, Version Date: 23/02/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW23 0189 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.8 MB (small file)
- File type
No other editions are linked here.