GENERAL COMMITTEE MEETING                                                                           12 MAY 2025


8.1     FINANCIAL PERFORMANCE REPORT – APRIL 2025



Author                Financial Services Manager, Pauline Coles
                      Financial Services | Corporate Services Department
Index                 ECM/ Subject / 22.09 – Monthly Financial Performance Report
Attachments           1.   Attachment 1 Statement of Income and Expenditure - Apr 2025
                      2.   Attachment 2 Statement of Financial Position - Apr 2025
                      3.   Attachment 3 Statement of Cashflows - Apr 2025
                      4.   Attachment 4 Key Materials & Services Expenditure - Apr 2025


EXECUTIVE SUMMARY
Year-to-date (YTD) performance against current budget as at 30 April 2025 is positive with
operating revenues outperforming forecast and operating expenditure slightly under forecast
YTD.

Capital revenues are above forecast with capital expenditure behind forecast due to delays and
rescheduled timing of project delivery.
   YTD Financial Performance Summary
                                           Budget         Actual     Variance       Variance
                                                                                                    Status
                                              $m             $m           $m              %
   Operating Revenue                        $132.1        $134.3           $2.2        1.7%      Above Budget
   Operating Expense                        $112.3        $112.0           $0.3        0.3%        On Track
   Operating Position                        $19.8         $22.3           $2.5
   Capital Revenue                           $46.7         $56.4          $9.7         20.8%      On Track
   Capital Expenditure*                     $115.7         $67.0         $48.7         42.1%    Behind Budget
* Reflects constructed assets and intangibles only (excludes contributed assets).


The $2.5 million full year positive interim operating variance comprises $1.6 million general
operating surplus from activities that are funded through Council’s general rate, regulatory fees
and sales of goods and services; Waste operations contributed an additional $0.8 with a further
$0.1 million from unspent levy and separate charge funds, which are constrained in reserve for
future use where they are not fully utilised in a given year. Holiday Parks are tracking to forecast
YTD noting the closure of the holiday parks, during Tropical Cyclone Alfred and higher than
anticipated waste and maintenance charges.

                                                                                  Budget       Actual   Variance
 Item                                                                               YTD          YTD         YTD
                                                                                     $m           $m          $m
 General business operating position (unconstrained funds)                         $11.8        $13.4        $1.6
 Commercial operations (constrained funds) *                                        $6.1         $6.9        $0.8
 Unspent levies (constrained funds)                                                 $1.9         $2.0        $0.1
 Total Council Operating Position                                                  $19.8        $22.3        $2.5
* Includes Waste and Holiday Park operations as shown in the table below
Log in to download the original file

10 Financial Performance Report - Apr 2025(PDF, 587KB).pdf · 601 KB (small file)

Full text of the other 11 pages

Page 2

GENERAL COMMITTEE MEETING                                                          12 MAY 2025




Council elects to apply National Competition Policy (NCP) reforms to its Waste Management and
Holiday Parks which provides greater transparency and assists with removing anti-competitive
conduct and ensures the best allocation of Councils limited resources. A summary of the YTD
operational performance of these business activities are outlined below.

                                         Waste Operations                  Holiday Parks
                                     Budget  Actual Variance         Budget   Actual Variance
                                       YTD      YTD       YTD          YTD      YTD       YTD
                                        $m       $m        $m           $m       $m        $m
 Revenue                               24.4     24.8       0.4          3.6      3.9       0.3
 Expenditure                           19.0     18.6       0.4          2.9      3.2     (0.3)
 Net Operating Position                 5.4      6.2       0.8          0.7      0.7       0.0

Financial statements including Statement of Income & Expenditure, Statement of Financial Position
(balance sheet), and Statement of Cash Flows are included as attachments for information for
Council.

Figure 1: Actual Performance Compared to Budget




Council’s performance against key measures of financial sustainability has been calculated as at
April 2025. These statutory indicators enable the reader to assess Council’s success in managing
its budget, cash and debt as well as undertaking sustainable asset management. The table below
contains a snapshot of a number of key measures, with full detail included in the report.


 YTD Measures of Financial Sustainability
                                                        Current
                                             Target                 Actual YTD       Status
                                                        Budget
 Operating Surplus Ratio                      0-10%       0.1%         16.6%        On Track
 Net Financial Liabilities Ratio              <60%        -7.0%       -38.5%        On Track
 Cash Cover Ratio                           3 months   9.5 months   11.8 months     On Track
 Asset Sustainability Ratio                   > 90%      116.6%        66.3%      Behind Budget

RECOMMENDATION
That Council note the report by the Financial Services Manager to the General Committee
Meeting dated 12 May 2025 outlining the April 2025 year to date financial performance against
budget, including changes to the financial performance report with the inclusion of key financial
sustainability indicators.

Page 3

GENERAL COMMITTEE MEETING                                                                   12 MAY 2025


REPORT
Operating Revenue (YTD Benchmark 83.3%)
Council has received 95.1% ($134.3 million) of its operating revenue budget ($141.3 million).
Commentary on each revenue category is provided below.

 Category          Summary                   Comments
 Rates and         $94.1 million (99.7%)        •   Waste utility charges $86.9k above YTD budget
 Levies            of the annual budget of          (100.1% or $17.1 million of $17.0 million annual
                   $94.3 million has been           budget earned)
                   earned
                                                •   General rate (net of discounts) $248.6k below
                                                    YTD budget (99.6% or $70.9 million of $71.2
                                                    million annual budget earned)


 Fees and          $8.5 million (77.2%) of      •   Waste $57.4k above budget (174.4% or $99.3k
 Charges           the annual budget of             of $56.9k annual budget earned)
                   $10.9 million has been
                   earned                       •   Cemeteries $35.2k above budget (93.4% or
                                                    $326.7k of $349.8k annual budget earned)
                                                •   Development Assessment $586.7k below
                                                    budget (69.9% or $2.5 million of $3.6 million
                                                    annual budget earned)
                                                •   Local Laws $172.6k below budget (72.8% or
                                                    $1.6 million of $2.1 million annual budget earned)
                                                •   Building & Plumbing Compliance $69.7k below
                                                    budget (79.6% or $2.1 million of $2.6 million
                                                    annual budget earned)


 Sale of Goods     $13.9 million (87.0%)        •   Holiday Park revenue $258.4k above budget
 and Services      of the annual budget of          (90.0% or $3.9 million of $4.3 million annual
                   $15.9 million has been           budget earned). Any revenue upside will be
                   earned                           generally offset by a corresponding increase in
                                                    associated operating costs
                                                •   Sports facility revenue $202.0k above budget
                                                    (94.7% or $2.8 million of $2.9 million annual
                                                    budget earned)


 Interest          $5.6 million (151.3%)        •   Interest revenues have continued to track above
 Received          of the $3.7 million              budget with investment in higher yielding term
                   annual budget has                deposits maximising the return on surplus cash
                   been earned                      holdings. Cash holdings remain high due to the
                                                    advanced payment of grants & subsidies,
                                                    restricted levy balances, future provision
                                                    balances and delays in the delivery of the capital
                                                    works program.

 Other Revenue     $3.1 million (95.6%) of      •   Plant recharge revenue is $114.5k above budget
                   the $3.2 million                 due to internal plant being utilised for the delivery
                   annual budget has                of disaster funded capital projects.
                   been earned
                                                •   Recoupment of Utility charges on commercial
                                                    properties $22.1k above budget (142.9% or
                                                    $73.1k of $51.1k annual budget earned.

Page 4

GENERAL COMMITTEE MEETING                                                                     12 MAY 2025


 Category           Summary                   Comments


 Operating          $5.2 million (72.7%) of        •    Operating Grants and subsidies are in line with
 Grants,            the $7.1 million                    budget expectations at this stage of the year.
 Subsidies          annual budget has
                    been received                  •    $1.4 million of the FY 2025 financial assistance
                                                        grant allocation was received in July 2024. This
                                                        is a change from the previous approach of
                                                        prepaying part or all of the grant in the preceding
                                                        year. This prepayment approach had been
                                                        consistent over the past 7 years.
                                                   •    Council has received notification of the approved
                                                        FY 2024/25 financial assistance grant allocation
                                                        which is less than budgeted. As such there is
                                                        potential for this to impact the FY 24/25 operating
                                                        position if payment of future years allocations are
                                                        not paid in the preceding year.


 Unitywater         On track                       •    Unitywater distributions are fixed each year so
 Distributions                                          there is limited budget variance risk


Figure 2: Operating Revenue Position by Type (Excluding Rates)




Operating Expenditure (YTD Benchmark 83.3%)
Actual operating expenditure is currently 79.3% ($112.0 million) of the full year budget ($141.1
million). Detailed commentary for each expenditure category is provided below.

 Category           Summary                            Comments
 Employee Costs     $43.0 million (80.9%) of the          •    Expenditure for permanent staff salaries
                    annual budget of $53.1                     and wages underspent ($2.1 million) due to
                    million has been expended                  position vacancies and the recoupment of
                                                               YTD vacancy dividend. This underspend is
                                                               offset by additional spend on casual staff
                                                               and external labour hire ($1.4 million).
                                                          •    The renegotiation of the Council's certified
                                                               agreement is still ongoing; accordingly the
                                                               forecast salary increases commencing
                                                               March 2025 have not yet taken effect. This
                                                               is also contributing to the YTD underspend

Page 5

GENERAL COMMITTEE MEETING                                                               12 MAY 2025


Category         Summary                        Comments
                                                      in employee costs. Once the agreement is
                                                      finalised and backpay is approved, these
                                                      savings will be used to cover these costs.
                                                   • Training costs are at $357.9k YTD or 92.7%
                                                      of the annual budget spent ($386.1k)
Materials and    $48.7 million (77.5%) of the      • Civil Operations $760.7k above YTD budget
Services         $62.8 million annual budget          (90.2% or $8.6 million of $9.5 million annual
                 has been expended.                   budget spent)
                                                   • Holiday Parks $234.0k above YTD budget
                                                      (88.6% or $2.3 million of $2.6 million annual
                                                      budget spent) offset by additional revenue
                                                   • Streetlighting $161.1k above YTD budget
                                                      (94.4% or $1.0 million of $1.1 million annual
                                                      budget spent)
                                                   • Disaster Management $68.9k above YTD
                                                      budget (151.9% or $94.0k of $61.9k annual
                                                      budget spent) This includes costs relating to
                                                      local     disaster     coordination    centre
                                                      established for Tropical Cyclone Alfred.
                                                   • Information Technology & Communications
                                                      $118.9k above YTD budget (83.3% or $4.4
                                                      million of $5.3 million annual budget spent)
                                                   • Local Laws $53.9k above YTD budget
                                                      (95.0% or $516.2k of $543.3k annual
                                                      budget spent)
                                                   • Fleet $31.3k above YTD budget (85.1% or
                                                      $1.4 million of $1.6 million annual budget
                                                      spent)
                                                   • Waste Management $316.4k below YTD
                                                      budget (77.3% or $11.5 million of $14.8
                                                      million annual budget spent)
                                                   • Arts & Culture $122.2k below budget
                                                      (67.4% or $1.8 million of $2.6 million annual
                                                      budget spent)
                                                   • Properties $102.2k below budget (76.6% or
                                                      $2.2 million of $2.8 million annual budget
                                                      spent)
                                                   • Buildings and Facilities $96.8k below
                                                      budget (69.3% or $856.0k of a $1.2 million
                                                      annual budget spent)
                                                   • Development Assessment $77.1k below
                                                      budget (83.6% or $1.1 million of a $1.3
                                                      million annual budget spent)
                                                   • Sports & Active lifestyles $60.1k below
                                                      budget (75.8% or $1.3 million of a $1.6
                                                      million annual budget spent)

Finance Costs    Currently on track                   •   Whilst existing loan borrowings are set with
                                                          fixed interest rates, any further RBA rate
                                                          rises will impact finance costs on new loan
                                                          borrowings. YTD underspend also relates
                                                          to the timing of drawdown of forecast
                                                          borrowings for FY 2025.
Depreciation     Currently on track             Nil
Other Expenses   Currently on track             Nil

Page 6

GENERAL COMMITTEE MEETING                                                                   12 MAY 2025



Figure 3: Operating Expenditure Position by Type




Tourism and Economic Development Investment Summary
Council resolved to report on a monthly basis, investment details for tourism and economic
development. Tourism and economic development activity is funded through the general rates
revenue. Expenditure at 30 April 2025 is outlined below:
 Expenditure                                             YTD Budget        YTD Actual          Variance
                                                              $’000             $’000             $’000
 Tourism Noosa Funding Agreement                             $2,520.0          $2,520.0               -
 Economic Development                                          $923.9              $901.1         $22.8
 Total                                                       $3,443.9          $3,421.1           $22.8

All instalments payable under the Tourism Noosa agreement for the 2024-25 financial year have
been made. The Tourism Noosa agreement is due for renewal in June 2025.

   •     Employee Costs are $26.5k below budget (78.7% or $515.4k of $654.6k annual budget
         spent)
   •     Materials & Services are in line with budget at this stage of the year.

Capital Revenue
Year to date Capital revenue of $56.4 million received comprises cash contributions from
developers ($1.2 million) and capital grants ($53.4 million). Note that the timing of capital grant
receipts are generally dependent on the timing of grant conditions and also capital delivery
performance, and that the timing of the receipt of developer contributions (both cash and
contributed) is unpredictable.
Grants and subsidies are higher than prior years due to the receipt of funding from the
Queensland Reconstruction Authority for reconstruction works relating to the Black Mountain
landslip and several other flood impacted sites, which are currently under construction.
Figure 6: Capital Revenue by Type

Page 7

GENERAL COMMITTEE MEETING                                                          12 MAY 2025




Capital Program
Actual capital expenditure (excluding commitments and disaster projects) is $22.5 million (YTD
budget $38.3 million). Expenditure on disaster projects (excluding commitments) is $44.5 million
(YTD budget $77.4 million).

Detailed discussion of progress in the delivery of the capital works program is provided through
a separate quarterly report by the infrastructure team.

Figure 7: Capital Program Delivery Performance




Cash Management and Investment Performance
Total cash on hand at the end of April was $114.5 million. Included in this balance are funds
held in trust and for restricted purposes (e.g. unexpended levy and grant funds), prepaid grants
including the financial assistance grant, QRA disaster funding and other capital works grants,
prepayment of Waste Levy subsidy (3 years), and unspent monies committed for funding capital
projects which are underway and will continue during the financial year.

The following pie charts present the mix of cash held at April 2025 by agency (graph on the left)
and by credit risk rating (graph on the right). All funds have been invested in accordance with
the Investment Policy and in consideration of the principles of ethical investment, preservation
of capital, return on investment and counterparty thresholds.

Figure 8: Closing Cash Held by Agency and Credit Rating

Page 8

GENERAL COMMITTEE MEETING                                                               12 MAY 2025




The following chart monitors the 12 month trend on total cash and the agencies invested. To
maximise the return on in its cash holdings Council has invested $25.5 million in higher yielding term
deposits. These investments were made in line with Council’s Investment of Surplus Funds policy.

Figure 9: 12 Month Trend of Cash Invested by Agency




Measures of Financial Sustainability
The following table incorporates a set of financial sustainability indicators to further assist in
managing Council financial performance. There are no significant emerging risks regarding
performance identified at this stage, however the delay in the delivery of the capital program
may impact Council’s asset sustainability and renewal targets.




 Category                                                     Comments
 Operating Surplus Ratio                                          •   Intent: Identifies the extent to
                                                                      which      revenues        cover

Page 9

GENERAL COMMITTEE MEETING                              12 MAY 2025


Category                     Comments
                                  operational expenses, to ensure
                                  community       equity   is   not
                                  degraded
                                • Target: Greater than 0%
                                • Result: 16.6%
                                • Comment: With the second
                                  rates cycle occurring in January,
                                  this ratio will slowly decline as
                                  expenditure      on    operations
                                  occurs through to the end of the
                                  financial year at 30 June 2025.

Cash Expense Cover               •   Intent: Indicates     how    long
                                     council can continue paying its
                                     day-to-day expenses from cash
                                     at     bank    without    needing
                                     additional cash flows
                                 • Target: > 3 months
                                 • Result: 11.8 months
                                  • Comment: Council is forecast
                                       to remain above target for the
                                       financial year. Business as
                                       usual expenditure through to 30
                                       June 2025 will continue to
                                       diminish     Council’s     cash
                                       holdings, albeit not below the
                                       target range of 3 – 6 months.
                                Cash reserves also include working
                                capital requirements and funding for
                                capital programs, unspent grant
                                monies paid in advance, Waste Levy
                                subsidy prepayments and QRA
                                advance payments for disaster
                                projects which are restricted for
                                specific purposes and inflate the
                                ratio.

Asset Sustainability Ratio       •   Intent: Measures the extent to
                                     which assets are being replaced
                                     as their condition degrades to
                                     ensure service potential is
                                     maintained
                                 •   Target: 80% of depreciation
                                     budget spent on renewals
                                     annually
                                 •   Result: 66.3%         achieved,
                                     however below forecast result
                                     due to project delays and
                                     scheduling.
                                 •   Comment: The       ratio    will
                                     progressively increase each
                                     month as expenditure on
                                     renewals occurs as part of the
                                     capital works program. For
                                     transparency QRA disaster
                                     projects have been excluded
                                     from          the          ratio
                                     calculations.   Should capital

Page 10

GENERAL COMMITTEE MEETING                                    12 MAY 2025


Category                          Comments
                                       works continue to fall below
                                       forecast for the remainder of the
                                       year this may impact the
                                       achievement of Council’s asset
                                       sustainability    and     renewal
                                       targets
Net Financial Liabilities Ratio      • Intent: Outlines the level that net
                                       Council debt can be serviced by
                                       operating revenues. A ratio
                                       below zero implies that liabilities
                                       are less than cash (and other
                                       current assets) and there is
                                       adequate borrowing capacity
                                       available if needed.
                                     • Target: less than 60%
                                     • Result: -38.5%
                                     • Comment: Council has low debt
                                       levels and strong cash holdings.
                                       The advance payment of rates,
                                       grants and subsidies also
                                       inflates the YTD actual outcome.
Investment Return                    • Intent: Ensure        appropriate
                                       return on investment yield for
                                       cash at bank.
                                     • Target: 0.25% above current
                                       Bloomberg commonwealth 10-
                                       year bond rate yield (4.45%)
                                     • Result: 5.40%
                                     • Comment: Council continues
                                          to invest surplus cash in
                                          higher yielding term deposits
                                          to                  maximise
                                          returns.            Council’s
                                          investment returns remain
                                          above target.
Rates in Arrears                      •   Intent: Ensuring that the amount
                                          of    unpaid     rates    remains
                                          sustainable and does not
                                          negatively impact cash flows
                                      •   Target: 5% industry benchmark
                                      •   Result: 6.4%
                                      •   Comment: Rates             arrears
                                          continue to decline from the high
                                          point in the cycle with payments
                                          coming            due           in
                                          February. Reminder notices
                                          were issued, and arrears will
                                          continue to stabilise through to
                                          June as they are collected, and
                                          payment             arrangements
                                          implemented.

Page 11

GENERAL COMMITTEE MEETING                                                                   12 MAY 2025



Link to Corporate Plan

Theme No. 5. - Excellence
This theme focuses on customer experience, financial sustainability, innovation and technology,
levels of service, governance, our employees and volunteers, funding streams and asset
management practices.


Objective 5.2 - Continue to deliver a financially sustainable Council that has the resources now and
into the future to achieve its strategic objectives. This will be supported through the introduction of
enhanced sustainability reporting and performance indicators, as well as ESG (environment social
and governance) accounting practices as guided by statutory requirements.


Previous Council Consideration
Nil


Finance
As above.


Risk & Opportunities
Council’s risk register identifies a number of risks that could impact on its ongoing financial
sustainability. In order to manage and mitigate these risks Council uses various tools which include
monthly ongoing financial reporting to identify and address emerging issues, conservative budgeting,
compliance with the Financial Sustainability Policy, regular budget reviews, effective liquidity
management to ensure sufficient fiscal flexibility, as well as adhering to the Reserves and Restricted
Cash policy which requires that Council maintains both a disaster management reserve and a
minimum 3 months cash cover to fund emergent matters.

Some examples of potential risks that may impact on Council’s operational performance, capital
program delivery, cashflow and cash reserves include:
•     Substantial damage to or failure of Council infrastructure due to natural disaster or other
      emergent issue that may require significant unplanned investment;
•     An extended closure of Council facilities impacting operational revenues;
•     A prolonged IT system failure affecting Council’s ability to deliver services or issue rates notices;
•     Economic conditions affecting ratepayers’ ability to pay rates;
•     Market driven increases in construction and operational costs significantly above estimates;
•     Labour and material shortages and delays;
•     Fraud attempts may result in financial impacts to Council if funds cannot be recovered;
•     Reliance on non-recurrent revenue streams (i.e. interest revenue on grants and short term cash
      holdings) to fund business as usual operations may result in higher rate increases in future years
      or service level cuts to fund potential shortfalls;
•     Strategies, plans and projects deliverables that have not been accurately costed.

Page 12

GENERAL COMMITTEE MEETING                                                                       12 MAY 2025



Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with Council’s
Human Rights Policy.

Consultation
External Consultation - Community & Stakeholder
Nil


Internal Consultation
All areas of Council are consulted as part of the regular monitoring of budget performance.

Departments consulted:

      Office of the CEO, Mayor &               Community Services               Corporate Services
              Councillors
       Mayor & Councillors               X   Director                    X   Director
  X    Chief Executive Officer               Community Development       X   Financial Services
       Executive Officers                    Sport & Active Lifestyles       Fleet
       Community Engagement                  Arts & Culture                  Revenue Services
       People & Culture                      Community Connection            ICT
       Governance                            Customer Experience             Procurement

                                                                             Commercial Property

       Strategy & Environment                Development & Regulation        Infrastructure Services
  X    Director                          X   Director                    X   Director
       Strategic Land Use Planning           Development Assessment          Infrastructure Planning, Design
                                                                             and Delivery
       Economic Development          &       Local Laws                      Civil and Asset operations
       Destination Management
       Environmental Services                Environmental Health            Waste
       Innovation & Digital Hub              Building & Plumbing             Building & Facilities
                                             Property / Permits              Disaster Management

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.