GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018



GENERAL COMMITTEE MEETING - LIVE RECORD MEETING NOTES
14 AUGUST 2017 – Crs. Frank Wilkie (Chair), Ingrid Jackson, Joe Jurisevic, Frank Pardon,
Brian Stockwell and Tony Wellington.
Apology: Cr Glasgow


1    MCU17/0028, OPW17/0120 & REC17/0012 DEVELOPMENT APPLICATION FOR A
     MATERIAL CHANGE OF USE FOR MULTIPLE HOUSING TYPE 1, RECONFIGURE A LOT
     (1 LOT INTO 2 LOTS) AND OPERATIONAL WORKS (ENGINEERING WORKS) 23
     TEWANTIN ROAD COOROY
     Committee Recommendation
     Moved:            Cr Stockwell
     Seconded:         Cr Wellington
     That Council note the report by the Coordinator Planning to the Planning & Environment
     Committee Meeting dated 8 August 2017 regarding Application No. MCU17/0028,
     OPW17/0120 and REC17/0012 for a Development Permit for Material Change of use of
     Premises Multiple Housing Type 1 – Duplex, Operational Works (Engineering Works) and
     Reconfigure a Lot 1 Lot into 2 Lots situated at 23 Tewantin Road, Cooroy described Lot 102
     C5604 and approve the application in accordance with the following conditions:
          MATERIAL CHANGE OF USE
          Approved Plans
     1.   Development undertaken in accordance with this approval must generally comply with
          the approved plans of development. The approved plans are listed in the following table
          unless otherwise amended by these conditions.
            Plan No.       Rev.    Plan/Document Name                             Date
            T42S1                  Site Plan                                      15.03.2017
            T42E1                  Elevations - Existing house                    15.03.2017
            1 of 6                 Site Plan drawn by Ausmar                      13.03.2017
            2 of 6                 Ground Floor drawn by Ausmar                   13.03.2017
            3 of 6                 Elevations drawn by Ausmar                     13.03.2017
            4 of 6                 Elevations drawn by Ausmar                     13.03.2017
          Dedication
     2.   Prior to the commencement of the use a two (2.0) metre wide strip extending across
          the full length of the frontage to Olivine Lane is to be dedicated to Council as ‘Road’.
          Roof pitch and eaves
     3.   The roof of the new dwelling must have a roof pitch of no less than 12 degrees and
          have minimum 600mm eaves to at least 75% of the perimeter of the building.
          Landscaping
     4.   The development site must be landscaped. The works must be undertaken in
          accordance with an Operational Works approval and the Noosa Plan for that specific
          area.


                                                                                    Page 1 of 25
Log in to download the original file

2017-08-14 General Committee Meeting Notes(PDF, 833KB).pdf · 853 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 24 sections

Section 2

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                       14 AUGUST 2018


    5.    All landscape works must be established and maintained in accordance with the
          approved design for the life of the development, and in a manner that ensures healthy,
          sustained and vigorous plant growth. All plant material must be allowed to grow to full
          form and be refurbished when its life expectancy is reached.
    6.    All landscape works must be maintained generally in accordance with the approved
          design for the life of the development.
          External Works
    7.    All works required in the Tewantin Road road reserve must be completed prior to the
          commencement of the use.
          Site Access and Driveways
    8.    A sealed access driveway must be provided from Tewantin Road and Olivine Lane to
          all parking and manoeuvring areas of the development. The works must include in
          particular driveway crossovers generally in accordance with Council’s standard
          drawings RS-049 and RS-050
          Tewantin Road.
    9.    Approval from the Department of Transport and Main Roads for the final design of the
          site access and driveway works in Tewantin Road must be submitted in writing to
          Council prior to the commencement of the works. All works must be completed and
          accepted by the Department of Transport and Main Roads prior to the commencement
          of the use.
          Olivine Lane
    10.   The existing access driveway from Olivine Lane may be retained provided that
          certification from a Registered Professional Engineer of Queensland (RPEQ) is
          submitted to Council. The certification must state that the driveway is in good order and
          is suitable for the intended use. If the certification cannot be provided the existing
          driveway must be removed and replaced with a compliant driveway.
          Performance Bond
    11.   Security in the form of a cash bond or trading bank guarantee to the sum of $5,000
          must be submitted to Council, to secure performance of all conditions of this approval,
          prior to the pre-start meeting. The cash bond or trading bank guarantee will be returned
          on performance of the conditions of approval less any costs incurred by Council in
          respect of enforcing performance of this permit. Council reserves the right to call upon
          the bond or guaranteed sum to effect compliance with conditions.
          Building Appearance
    12.   All air conditioning units or other mechanical equipment must be located at ground
          level, or otherwise fully enclosed or screened such that they are not visible from the
          street frontages nor adjoining properties.
          Fencing and Walls
    13.   Any street fencing must be set back an average of 1 metre from the front property
          boundary. Any fencing on the front boundary must either:
          a.    not exceed a maximum height of 1.2m
          b.    be of open construction.
    14.   The area of land between the fence and the front property boundary must be densely
          landscaped to screen any fencing from the street.

                                                                                     Page 2 of 25

Section 3

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                       14 AUGUST 2018


          Car Parking
    15.   Car parking spaces must be provided and marked on the site in accordance with the
          approved plans. The car parking must include in particular cross falls and gradients in
          accordance with Australian Standard AS/NZS2890.1:2004.
          Stormwater Drainage
    16.   The site must be provided with a stormwater drainage system connecting to a lawful
          point of discharge.
    17.   The development must be constructed so as not to concentrate or redirect stormwater
          runoff onto neighbouring properties.
          Electricity and Telecommunication Services
    18.   Reticulated electricity and telecommunication services must be provided to each lot in
          accordance with the standards and requirements of the relevant service provider.
    19.   Unless otherwise stipulated by telecommunications legislation at the time of
          construction, the development must be provided with all necessary conduits, pits and
          pipes to accommodate the future connection of optic fibre technology
          telecommunications.
    20.   Certification must be submitted to Council from all relevant service providers which
          certifies that the development has met the requirements of this Decision Notice and all
          applicable legislation at the time of construction.
          Easements
    21.   Unless otherwise agreed in writing by the relevant service provider, any public or third
          party infrastructure located on the subject site must be placed within an easement
          registered against the title of the property.
    22.   All easements must be designed in accordance with the planning scheme and granted
          at no cost to the Grantee. Where the Grantee is Council or a service authority, the
          easement documentation must be in accordance with the Grantee’s standard
          easement terms. Draft easement documentation must be submitted to Council for
          endorsement.
    23.   All works must be kept clear of any existing or proposed easements on the subject
          land, unless agreed otherwise in writing by the Grantee.
          Earthworks and Retaining Walls
    24.   All fill and associated batters must be contained entirely within the subject site unless
          written permission from the respective landowner(s) is provided to Council. All
          earthworks must be undertaken in accordance with the provisions of Australian
          Standard AS3798: Guidelines on Earthworks for Commercial and Residential
          Developments.
    25.   Where the development involves excavation or filling over, or adjacent to, drainage,
          water supply or sewerage infrastructure, all access chamber surface levels must be
          adjusted to provide a freeboard of 100mm above the finished ground surface level.
    26.   All retaining walls must be designed and constructed in accordance with the planning
          scheme and must be certified by an RPEQ where exceeding 1.0m in height. All
          retaining walls that are publicly accessible and exceed 1.0m in height must be fitted
          with a commercial grade safety fence.



                                                                                     Page 3 of 25

Section 4

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                              14 AUGUST 2018


          Damage to Services and Assets
    27.   Any damage caused to existing services and assets as a result of the development
          works must be repaired at no cost to the asset owner at the following times:
          a.      where the damage would cause a hazard to pedestrian or vehicle safety,
                  immediately; or
          b.      where otherwise, upon completion of the works associated with the development.
          Any repair work which proposes to alter the alignment or level of existing services and
          assets must first be referred to the relevant service authority for approval.
          Community Management Statement
    28.   Any proposed Community Management Statement required for the development
          pursuant to the Body Corporate and Community Management Act 1997 must be
          submitted to Council for endorsement at the same time as submission of the Building
          Format Plan (or similar) to Council for compliance assessment.
          RECONFIGURING A LOT
               Plan No.           Rev.   Plan/Document Name                                Date
               16-4325AA                 Plan showing details of Lot 102 on C5604 drawn    20.12.2016
                                         by Max Waterson and Associates
               16-4325AB                 Plan of proposed Reconfiguration of Lot 102 on    30.03.2017
                                         C5604 (Community Title Scheme) drawn by
                                         Max Waterson and Associates
    29.   Unless otherwise stated, all works required by the conditions of this Decision Notice
          must be completed prior to submission of the subdivision plan to Council for plan
          sealing.
          OPERATIONAL WORKS
          APPROVED PLANS
    30.   Development undertaken in accordance with this approval must generally comply with
          the approved plans of development. The approved plans are listed in the following table
          unless otherwise amended by these conditions.
               Plan No.    Rev.    Plan/Document Name                                           Date
               1622-01     C       Site Plan prepared by Callaghan and Toth for that part       June 2017
                                   within the subject site
               1622-02     C       Driveway Layout & Sediment Control Plan prepared by          June 2017
                                   Callaghan and Toth for that part within the subject site
               1622-03     C       Driveway Detail Plan prepared by Callaghan and Toth for      June 2017
                                   that part within the subject site
               1622-06     C       Structural Detail Plan prepared by Callaghan and Toth for    June 2017
                                   that part within the subject site
               1622-07     C       Driveway Longitudinal Section prepared by Callaghan          June 2017
                                   and Toth for that part within the subject site
               T42L1               Landscape Plan                                               15.03.2017




                                                                                               Page 4 of 25

Section 5

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018


          PRIOR TO COMMENCEMENT OF WORKS
          Engineering
    31.   All necessary approvals from external service providers (e.g. Unitywater) and external
          parties on which the development works are proposed have been obtained and a copy
          supplied to Council.
    32.   Copies of the approved plans, duly signed by the consultant Registered Professional
          Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
          Construction at the “pre start” meeting.
    33.   A condition report including photographs of the frontage of the site (Olivine Lane and
          Tewantin Road) must be completed and submitted to Council at the prestart meeting /
          prior to any works commencing.
    34.   Certificates demonstrating currency of public liability insurance and works insurance
          covering the works must be submitted to Council at the prestart meeting.
    35.   Council must be contacted at least 5 working days prior to any works commencing to
          organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245.
          The pre-start meeting must include the relevant parties for the following aspects of the
          works:
          a.    Civil engineering works;
          b.    Other relevant parties
    36.   A Construction Management Plan must be submitted to Council prior to the pre-start
          meeting and must specifically address the following:
          a.    Traffic Management during all aspects of the construct phase including:
                i.     A Traffic Management Control Plan in accordance with Manual of Uniform
                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                       control measures prior to construction;
                ii.    Maintenance of safe pedestrian access across the frontage of the site both
                       during daily construction and after daily construction has ceased;
                iii.   Proposed fencing to the site during the construction phase of the
                       development;
                iv.    Adequate parking arrangements for construction workers.
          b.    Maintenance and protection of water quality and existing drainage lines through
                the construction site through the implementation of appropriate erosion and
                sediment control measures.
          c.    Works programme identifying key components of the works and their respective
                durations.
          d.    Establishment of a communication protocol with the general public, adjoining
                owners, emergency services and local businesses to advise of agreed
                construction times, impacts on traffic and services and other relevant issues.
          e.    identification of complaint management procedures including:
                i.     contact details for the on-site manager;
                ii.    dispute resolution procedures.



                                                                                    Page 5 of 25

Section 6

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                        14 AUGUST 2018


    37.   Any changes to the details associated with the supervising RPEQ or Principal
          Contractor during construction must be notified to Council in writing within five business
          days of the change occurring.
    38.   Any conflict between the development and an existing or proposed service must be
          referred to the relevant service authority for determination prior to commencement of
          works.
          Landscaping Works
    39.   The development must be landscaped in accordance with these conditions and the
          approved landscape plans prior to the commencement of use.
    40.   A minimum pot sized 100L street tree must be installed in the Tewantin road frontage
          and:
          a.    Meet Specifying Trees – a guide to assessment of tree quality (NATSPEC).
          b.    Be located in accordance with engineering requirements for safe vehicle and
                pedestrian sight lines.
          c.    Be of an approved Council species suitable for the location and of local origin.
          d.    Planted in accordance with Planning Scheme Policy 3 Landscaping Plants and
                Guidelines.
    41.   Landscape works must be supervised, undertaken and certified by a horticulturist. All
          works must be completed in accordance with this Decision Notice.
          DURING CONSTRUCTION
          Engineering
    42.   The developer must meet any costs to repair damage to any Council asset during
          construction, where damage is a result of the development works. Damage to assets
          must be repaired immediately where it creates a hazard to the community. In
          circumstances where the damage does not create a hazard to the community, it must
          be repaired immediately on completion of the works associated with the development.
    43.   All works must be supervised by a Registered Professional Engineer of Queensland
          (RPEQ) who is independent of the Developer and Principal Contractor, and they must
          certify that all works conform to the Operational Works permit.
    44.   All works must be constructed and work procedure undertaken in accordance with:
          a.    The approved plans/documents and conditions detailed in this Decision Notice.
          b.    All relevant Noosa Council Planning Scheme Policies, standard drawings,
                standard specifications and guidelines.
          c.    The latest version of the Healthy Waterways document “Water Sensitive Urban
                Design Technical Design Guidelines for South East Queensland” for all water
                quality devices to be constructed on site.
          Pavement Design and Construction
    45.   Pavement design for privately owned works must be undertaken in accordance with
          the relevant standards. Structural integrity of the driveway and car park areas will
          remain the responsibility of the property owner/developer and must be certified by an
          RPEQ.



                                                                                      Page 6 of 25

Section 7

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018


          Works within Road Reserve/Reinstatement
    46.   Safe pedestrian access on all streets in the vicinity of the development must be
          maintained at all times. Should footpath/road closures be necessary to carry out
          construction works, Council’s Engineering Officer must be notified prior to the proposed
          closure and all requirements complied with.
    47.   All frontage works must match neatly with existing road and verge/footpath features.
          Additional works beyond the frontage may be required to provide an acceptable
          transition to existing road and verge/footpath profiles.
    48.   Electrical conduits or other services proposed to be installed within existing and
          proposed road reserves under existing sealed carriageways, concrete pathways,
          concrete/sealed driveways or significant vegetation must be installed by boring.
          Trenching is not permitted, unless specifically approved by Council.
          Site Access and Driveways
    49.   Any existing unnecessary or redundant property accesses must be removed, and the
          kerb, footpath and verge area reinstated to match the existing footpath and/or verge
          treatments. Grassed verge areas to be reinstated must be provided with 100 mm
          topsoil and grass seed or turf, and must be maintained by the developer until
          established.
    50.   The following must be complied with during the construction of the required
          crossovers/driveways:
          a.    The driveway surfacing must consist of either an approved hot mixed asphaltic
                concrete or patterned/plain concrete.
          b.    The driveway must be constructed so as not to concentrate or redirect
                stormwater runoff onto neighbouring properties.
          c.    Underground service conduits for water supply, electricity and any other services
                must be provided as part of the access driveway.
          d.    Where there is an existing pedestrian path, a matching crossfall must be provided
                for the driveway on the alignment of the path, for the full width of the path.
          e.    The property access must be located a minimum of 1m clear of existing power
                poles, streetlights or other signage. The developer is responsible for any
                necessary relocation of existing services to provide this clearance and must
                contact the relevant service authorities and comply with their requirements in
                relation to these works.
          Earthworks and Retaining Walls
    51.   All earthworks shall be undertaken in accordance with the provisions of AS 3798
          Guidelines on Earthworks for Commercial and Residential Development, with
          geotechnical testing undertaken in accordance with Section 8 of the Standard, and to
          a minimum of ‘Level 1’ as defined in Appendix B. Test results as required by AS 3798,
          and a certificate of quality and uniformity of fill shall be provided by a RPEQ and
          submitted to Council prior to Council signing the Plan of Survey.
          Stormwater Drainage
    52.   Appropriate scour protection must be provided at the outlet of all stormwater pipes
          including temporary outlets.



                                                                                    Page 7 of 25

Section 8

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                         14 AUGUST 2018


    53.   Works associated with this permit must not adversely impact on the existing drainage
          conditions on other properties (e.g. by blocking or interfering with natural overland
          flows).
    54.   Construction of all internal stormwater drainage works must comply with the relevant
          section/s of Australian Standard AS/NZS 3500.3.
          Environment
    55.   Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994)
          must not be released from the site or to waters within the site, or be likely to be released
          should rainfall occur, unless all reasonable and practicable measures are taken to
          prevent or minimise the release and concentration of contamination.
    56.   Erosion and sediment control measures must be installed and maintained to minimise
          erosion on the site and to minimise the export of sediment and associated pollutants
          from the site. The erosion and sediment control measures must be designed, installed
          and maintained in accordance with current best practice standards (refer to advisory
          notes).
    57.   Prior to the commencement of the use, all site surfaces must be effectively stabilised
          using methods which have achieved effective short-term stabilisation and which will
          continue to achieve effective stabilisation in the medium to long-term (refer to advisory
          notes). For the purpose of this condition, an effectively stabilised surface is defined as
          one that does not, or is not likely to result in visible evidence of soil loss caused by
          sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
          Damage to Services and Assets
    58.   Any damage caused to existing services and assets as a result of the development
          works must be repaired at no cost to the asset owner at the following times:
          a.    where the damage would cause a hazard to pedestrian or vehicle safety,
                immediately; or
          b.    where otherwise, upon completion of the works associated with the development.
          Any repair work which proposes to alter the alignment or level of existing services and
          assets must first be referred to the relevant service authority for approval.
    FOLLOWING CONSTRUCTION
          Certification
    59.   Upon completion of the work a certificate must be issued by an RPEQ certifying that
          the works have been constructed in accordance with the Operational Works permit.
    60.   A final inspection and approval of the new works and completed reinstatement works
          by Council’s Inspector is required. Please contact Council on 5329 6245 to arrange for
          the inspection.
                                                                                        Carried.




                                                                                       Page 8 of 25

Section 9

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                            14 AUGUST 2018


2   MCU17/0035 APPLICATION FOR A DEVELOPMENT PERMIT FOR A MATERIAL
    CHANGE OF USE OF PREMISES OPEN SPACE TYPE 2 CAMPGROUND FOR 240
    WILDERNESS TRACK AND ROAD 205 NOOSA NORTH SHORE
    Committee Recommendation
    Moved:               Cr Jurisevic
    Seconded:            Cr Stockwell
    That Council note the report by the Coordinator Planning to the Planning & Environment
    Committee Meeting dated 8 August regarding Application No. MCU17/0035 for a
    Development Permit for Material Change of Use of Premises - Open Space Type 2
    Campground situated at 240 Wilderness Track, Noosa North Shore and approve the
    application in accordance with the following conditions:
         When Conditions must be Complied With
    1.   Unless otherwise stated, all conditions of this Decision Notice must be complied with
         prior to the use commencing, and then compliance maintained at all times while the
         use continues.
         Approved Plans
    2.   Development undertaken in accordance with this approval must generally comply with
         the approved plans of development. The approved plans are listed in the following table
         unless otherwise amended by these conditions.
              Plan No.            Rev.    Plan/Document Name                               Date
              D-02174-01-C                Proposal Concept Plans                           24/04/2016
         Use
    3.   Resident guests of the campground must not stay longer than 12 weeks in a year.
    4.   The maximum number of camp sites permitted is 200 on site at any one time.
         Environmental Health
    5.   Sanitary Facilities are to be installed to the following requirements:
         a.      Unless an accommodation is fitted with a sanitary convenience, as a minimum
                 standard provide for the exclusive use of the park occupants separate sanitary
                 conveniences for each sex in accordance with the table below; and
                 No. of sites   No. of water closets      No. of water closets      Length of urinals
                                and pans for females      and pans for males        for males
                 Up to 40       1 for every 12 sites of   1 for every 15 sites or   0.6m
                                part thereof              part thereof
                 Above 40       An additional 1 for       An additional 1 for       0.6m for every 40
                                every 20 sites or part    every 20 sites or part    sites or part thereof
                                thereof                   thereof
         b.      Sanitary facilities must be located generally in the locations shown on the
                 approved plan and at least 6 metres from any camp site.
         c.      Where 10 or more water closet fixtures are provided, ensure that at least 1 such
                 closet fixture and its compartment or cubicle is constructed, equipped and
                 provided with access in accordance with AS1428, Code of Practice for Design
                 Rules for Access by the disabled; and


                                                                                            Page 9 of 25

Section 10

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018


          d.    Ensure all sanitary conveniences are constructed to ensure privacy to the
                satisfaction of an authorized person; and
          e.    Ensure shower facilities are installed:
                i.    With separate drainage points for the discharge of water into the drainage
                      system; and
                ii.   In a separate compartment or cubicle which is constructed to ensure
                      privacy to the satisfaction of an authorized person; and
          f.    Provide for suitable laundry facilities including laundry tubs, washing machines
                and clothes lines in a centrally located area; and
          g.    Provide sewage or a drainage system in conformity with the requirements of the
                local government for the carrying off and disposal of all wastes from every water
                closet fixture, urinal, ablutionary facility, laundry facility and site; and
          h.    Provide waste water disposal points throughout the site which are:
                i.    Provided with a water stand pipe; and
                ii.   Provided with an impervious paved area measuring not less than 1m x 1m
                      and graded to a central drainage inlet which is connected to sewage or
                      drainage system.
          Retention of Existing Trees
    6.    Existing trees on the site and in the road reserve must be assessed by a qualified
          arborist and retained and protected where possible. Where mature trees are to be
          removed, reasonable grounds must be given by the qualified arborist. Any tree
          removed must be replaced with a similar suitable tree species in a similar location,
          where practicable.as part of the restoration of the overall site.
    7.    In order to protect existing vegetation and natural habitat values, waste water must not
          be disposed of on-site and must be collected and appropriately treated or disposed of
          off-site.
    8.    Pest plant species, including “Undesirable species” as listed in Planning Scheme Policy
          3 Landscaping Plants and Guidelines and Noosa Council’s Pest Management Plan as
          amended from time to time, must be controlled on site.
    Bushfire and Natural Hazards
    9.    The development must be carried out in accordance with section 6 of the Bushfire Risk
          Assessment and Bushfire Risk Management Plan for the Noosa North Shore Beach
          Campground Upgrade Revision 1 March 2017 prepared by Ecological Natural Area
          Management.
    10.   A copy of the Bushfire Risk Assessment and Bushfire Risk Management Plan for the
          Noosa North Shore Beach Campground Upgrade Revision 1 March 2017 prepared by
          Ecological Natural Area Management must be provided to the nearest fire authority.
    11.   The development must be carried out in accordance with the Bushfire Risk Assessment
          and Bushfire Risk Management Plan for the Noosa North Shore Beach Campground
          Upgrade Revision 1 March 2017 prepared by Ecological Natural Area Management.




                                                                                   Page 10 of 25

Section 11

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                             14 AUGUST 2018


    Vegetation Management
    Works within Protected Land
    12.   The following works must be undertaken within the land generally located east of the
          site and to the north of the site to remedy historic camping encroachment on the dune
          system.
          a.     Restoration of the cleared areas of the dune system to a natural state similar to
                 dune vegetation structure found at immediately north of the Third Cutting.
          b.     Restoration works must occur between the latitudes of -26.3307 and -26.3357.
          c.     The establishment of restoration works must commence within 12 months from
                 date this development permit takes effect.
          d.     Restoration establishment works must be successfully completed within 36
                 months from date this development permit takes effect.
          e.     The restoration works must be maintained in good order for the life of the
                 development.
          f.     Public access from the camp ground, through the esplanade, to the beach must
                 be controlled to prevent disturbance to the restoration area.
          Fencing to Protected Land
    13.   A permanent fence must be constructed along the entire length of the eastern interface
          of the site. The fence must be constructed to protect the esplanade from public access
          generally in accordance with the alignment on the approved plan and include:
          a.     Controlled beach access points;
          b.     Signage promoting the restoration works.
                                                                                                 Carried.



3   MCU17/0014 APPLICATION FOR DEVELOPMENT PERMIT FOR MATERIAL CHANGE
    OF USE OF PREMISES MULTIPLE HOUSING TYPE 4 CONVENTIONAL 10 UNITS AND
    COMMERCIAL BUSINESS TYPE 1 OFFICE AND TYPE 2 MEDICAL FOR 30-32
    DOONELLA STREET TEWANTIN
    Cr Jurisevic declared a perceived conflict of interest in this matter (as defined in section 173 of the
    Local Government Act 2009) due to the applicant being a family friend. Cr Jurisevic left the meeting
    room for the debate and decision on this matter.
    Committee Recommendation
    Moved:             Cr Wellington
    Seconded:          Cr Stockwell
    That Council note the report by the Coordinator Planning, Patrick Murphy to the Planning &
    Environment Committee Meeting dated 8 August 2017 regarding Application No.
    MCU17/0014 for a Development Permit for Material Change of Premises – Multiple Housing
    Type 4 Conventional (10 units) and Commercial Business Type 1 Office and Type 2 Medical
    situated at 30 and 32 Doonella Street Tewantin described as Lot 903 on T1631 and Lot 32
    on RP893427, and:
    A.    Approve the application in accordance with the following conditions:



                                                                                          Page 11 of 25

Section 12

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018


        PLANNING
        When Conditions must be Complied With
        1.   Unless otherwise stated, all conditions of this Decision Notice must be complied
             with prior to the use commencing, and then compliance maintained at all times
             while the use continues.
        APPROVED PLANS
        2.   Development undertaken in accordance with this approval must generally comply
             with the approved plans of development. The approved plans are listed in the
             following table unless otherwise amended by these conditions.
              Plan No.      Rev.    Plan/Document Name                               Date
              1646-SD01     11      Site Plan By Archiology                          11/05/2017
              1646-SD02     10      Ground/Carpark Plan By Archiology                02/05/2017
              1646-SD03     8       Level 1 Plan By Archiology                       02/02/2017
              1646-SD04     7       Level 2 Plan By Archiology                       02/02/2017
              1646-SD05     7       Level 3 Plan By Archiology                       02/02/2017
              1646-SD07     7       Northern and Eastern Elevations By Archiology    02/02/2017
              1646-SD08     7       Southern and      Western     Elevations    By   02/02/2017
                                    Archiology
              1646-SD09     7       Section Plans By Archiology                      02/02/2017
              1646-SD10     7       Section Plans By Archiology                      02/02/2017
              SD-1          B       Landscape Concept Strategy by Project Urban      15.02.2017
              SD-2          B       Landscape Concept Strategy by Project Urban      15.02.2017
              2630-001      A       Entry Driveway Long Section – Western Side,      02/05/2017
              (Sheet 01)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)
              2630-001      A       Entry Driveway Long Section – Western Side,      02/05/2017
              (Sheet 01)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)
              2630-001      A       Entry Driveway Long Section – Eastern Side,      02/05/2017
              (Sheet 02)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)
              2630-001      A       Exist Driveway Long Section – Western Side,      02/05/2017
              (Sheet 03)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)
              2630-001      A       Exist Driveway Long Section – Western Side,      02/05/2017
              (Sheet 04)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)
              2630-001      A       Front Boundary Long Section – Western Side,      02/05/2017
              (Sheet 05)            prepared Greys Consulting
                                    (certified by Brett Franklin RPEQ 18447)




                                                                                  Page 12 of 25

Section 13

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   14 AUGUST 2018


        Amended plans
        3.   The development must be amended in accordance with the following
             requirements:
             a.    The built form presentation of the commercial building and undercroft car
                   parking area to Doonella Street must maintain the 3 building forms, but the
                   façade treatments must be amended to reflect and complement the
                   heritage character of the locality by incorporating materials, finishes and
                   colours consistent with the Tewantin domestic vernacular. The façade
                   treatment of the 3 building forms must also complement and be compatible
                   with each other.;
             b.    The eastern and western elevations of the residential building must be
                   provided with roof overhangs that are a minimum 600mm wide, with
                   sunhoods provided to lower storey windows; and
             c.    The full extent of the walkway adjacent to the western elevation of the
                   residential building must be covered with an awning or the like. The device
                   must be situated at least 2.40 metres above the height of the walkway.
             Amended plans demonstrating compliance with this condition must be lodged
             with Council prior to issue of a Development Permit for Operational Works.
        4.   Additional details of the proposed finished ground levels and treatment to
             boundaries must be lodged with Council prior to issue of a development permit
             for operational works. These additional details must demonstrate that the
             basement and car parking areas are appropriately screened and landscaped to
             the adjoining properties.
        Building Height
        5.   The maximum height of the development must not exceed 8 metres above the
             natural ground level and finished ground level (with the exception of the driveway
             entrance to the basement carpark and refuse store area).
        6.   Certification must be submitted to Council from a Licensed Surveyor which
             certifies that the building does not exceed the maximum height requirement of
             this Decision Notice.
        Performance Bond
        7.   Security in the form of a cash bond or trading bank guarantee to the sum of
             $20,000 must be submitted to Council, to secure performance of all conditions of
             this approval, prior to the site pre-start meeting. The cash bond or trading bank
             guarantee will be returned on performance of the conditions of approval less any
             costs incurred by Council in respect of enforcing performance of this permit.
             Council reserves the right to call upon the bond or guaranteed sum to effect
             compliance with conditions.
        Street Identification
        8.   The street address of the development must be clearly visible and discernible
             from the primary frontage of the site by the provision of a street number and,
             where appropriate, the building name.




                                                                                Page 13 of 25

Section 14

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    14 AUGUST 2018


        Water & Sewer Connections
        9.    An underground connection to reticulated water and sewerage must be provided
              to the development site in accordance with the standards and requirements of
              Northern SEQ Distributor–Retailer Authority (Unitywater).
        10.   A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
              (Unitywater) must be submitted to Council that certifies an underground
              connection to reticulated water and sewerage has been provided to the
              development site.
        Building Appearance
        11.   All air conditioning units or other mechanical equipment must be fully enclosed
              or screened such that they are not visible from the street frontages nor adjoining
              properties.
        12.   All deck and balcony areas above ground floor must not be enclosed by
              permanent fixtures such as shutters, louvres, glass panelling or the like.
        13.   Undercroft areas toward the building’s Doonella Street frontage shall be
              screened/battened to the reasonable satisfaction of Council and Condition 3.
        14.   Balustrading to balcony areas must be glazed, as indicated on the approved
              plans.
        Fencing and Walls
        15.   Any street fencing must be set back an average of 1 metre from the front property
              boundary. Any fencing on the front boundary must either:
              a.   not exceed a maximum height of 1.2m
              b.   be of open construction.
        16.   The area of land between the fence and the front property boundary must be
              densely landscaped to screen any fencing from the street.
        Clothes Drying Areas
        17.   A common access outdoor clothes line shall be provided for resident’s use, which
              is screened from public view.
        Storage
        18.   Each dwelling unit must be provided with an allocated secure storage area(s)
              within the basement carpark.
        Community Management Statement
        19.   Any proposed Community Management Statement required for the development
              pursuant to the Body Corporate and Community Management Act 1997 must be
              submitted to Council for endorsement at the same time as submission of the
              Building Format Plan (or similar) to Council for compliance assessment.
        20.   All clauses and by-laws of the proposed Community Management Statement
              must accord with the requirements of this Decision Notice.




                                                                                 Page 14 of 25

Section 15

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                      14 AUGUST 2018


        Landscaping Works
        21.   The development site must be landscaped. The works must be undertaken in
              accordance with an Operational Works approval and the Noosa Plan and must
              include:
              a.   The works generally shown on the approved plans numbered SD-01(B),
                   SD-02[B] titled “Landscape Concept Strategy” by Project Urban dated
                   15/02/17.
              b.   Local species suitable for the location and generally consistent with
                   requirements of Planning Scheme Policy 3 – Landscaping Plants &
                   Guidelines.
              c.   Retention of exiting trees toward the eastern boundary and south-eastern
                   corner of the site as shown on the approved Landscape Concept Plan (with
                   consideration to be given to the viability of retaining the tree(s) close to the
                   building in the context of the likely construction disturbance).
              d.   Retention of existing street trees (with consideration to be given to the
                   viability of retaining the tree(s) close to the new vehicle crossover(s)in the
                   context of the likely construction disturbance).
              e.   Replacement for any street tree proposed to be removed with advanced
                   ex-ground street tree(s).
              f.   Screening vegetation along the western boundary and front setback.
              g.   The all-weather pedestrian surface treatment to the 3m wide access
                   easement at the north of the site.
              h.    Clearly detail any proposed front fencing.
        22.   All landscape works must be maintained generally in accordance with the
              approved design for the life of the development.
        External Works
        23.   Roadworks must be provided within the proposed 3.0m wide “Public
              Thoroughfare” easement adjacent to the northern boundary of the site, extending
              from the eastern side of the bin area to remaining length of the northern
              boundary. The works must be undertaken in accordance with an Operational
              Works approval and must include in particular:
              a.   2.0m wide concrete pavement along full length of the easement. The
                   formation must be designed to cater for the potential future use by vehicles
                   and be in accordance with Council’s Planning Scheme Policy 5 –
                   Engineering Design Standards – Roads, Drainage and Earthworks.
              b.   Landscaping works to provide a suitable visual screening buffer between
                   the building and the easement with a minimum garden bed width of
                   800mm.
              c.   Pram ramps where required.
              d.   Any necessary alteration and reinstatement works beyond the boundary of
                   the site to connect and match existing public carparks or pathways
                   pavements.




                                                                                   Page 15 of 25

Section 16

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                     14 AUGUST 2018


        Site Access and Driveways
        24.   A sealed access driveway must be provided from Doonella Street to all parking
              and maneuvering areas of the development generally in accordance with the
              approved plans (16416–SD02 dated 02/05/2017 by Archicology). The works
              must be undertaken in accordance with an Operational Works approval and must
              include in particular:
              a.    A driveway crossover 4.0m wide with grades generally in accordance with
                    IPWEAQ standard drawings SEQ R-049 and R-050 with line marking and
                    modified driveway tapers at 45 degree at the kerb line to encourage left-in
                    and left-out from the site (refer to Parking & Traffic Impact Assessment
                    Report – Addendum 1, Reference 210442017TIA-Add, dated 21 April 2017
                    by Greys Australia Pty Ltd).
              b.    Signage and linemarking in accordance with Manual of Uniform Traffic
                    Control Devices (MUTCD) installed within the site to indicate left-out only
                    traffic.
              c.    Grades to allow for a compliant concrete pathway along the frontage.
              d.    Any landscaping, fences and fixtures near the access entry point must
                    comply with AS 2890.1 requirements for sight visibility for pedestrians and
                    cyclists at driveways.
        Frontage Reinstatement Works
        25.   All redundant driveways and existing kerb laybacks along the frontage of the site
              must be removed and the kerb, footpath and verge area reinstated to match the
              balance of the site frontage, including the provision of topsoil and turf where the
              existing verge is grassed. The works must be undertaken in accordance with an
              Operational Works approval and must include in particular:
              a.    The existing driveway layback be removed and the kerb reinstated to match
                    the type and alignment of the adjoining existing sections of kerb line. The
                    driveway layback must be saw-cut and removed to allow for a smooth and
                    neat join finish between the new and the existing kerb.
              b.    Reinstatement of concrete footpath to provide even and consistent
                    gradients in longitudinal and across profiles generally in compliance with
                    IPWEAQ standard drawing SEQ R-065 Concrete Pathway Construction
                    Details, this may necessitate replacement of sections of the existing
                    footpaths beyond the edges of the redundant driveways and the frontage
                    of the site.
              c.    Any affected trees within the grassed verge must be replaced with similar
                    species in accordance with the landscaping conditions of this permit.
        Car Parking
        26.   A minimum of 54 car parking spaces must be provided and marked on the site
              generally in accordance with the approved plans. The works must be undertaken
              in accordance with an Operational Works approval and must include in particular:
              a.    3 disabled parking spaces within the total.
              b.    3 visitor parking spaces within the total, which are clearly marked for that
                    purpose and accessible at all times for visitor use.



                                                                                 Page 16 of 25

Section 17

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                     14 AUGUST 2018


              c.    18 bicycle parking spaces.
              d.    Dimensions, crossfalls, gradients and vehicle headroom in accordance
                    with Australian Standard AS2890: Parking Facilities.
        27.   All car parking areas and access driveways must be maintained exclusively for
              vehicle parking and maneuvering and kept in a tidy and safe condition at all times.
        28.   All car and bicycle parking areas must be line marked in accordance with
              approved plans, no dividing walls be constructed unless a further application for
              amendment is approved by Council.
        Stormwater Drainage
        29.   The site must be provided with a stormwater drainage system connecting to a
              lawful point of discharge. The works must be undertaken in accordance with an
              Operational Works approval, and must include in particular:
              a.    Stormwater system that caters for all storms up and including 1 in 100 years
                    storm event.
              b.    No adverse impact on other properties and the road’s footpath and grassed
                    verge (eg by diverting flows and/or blocking flows and causing additional
                    ponding).
              c.    Where applicable, extension of the site stormwater system to
                    accommodate stormwater from external site, including registration of
                    drainage easements.
              d.    The use of gravity stormwater drainage only and not surcharge pits or
                    pumps.
        30.   Stormwater runoff from the development must be disposed of without causing
              scour or damage to the subject site or any adjoining property.
        Electricity and Telecommunication Services
        31.   Unless otherwise stipulated by telecommunications legislation at the time of
              construction, the development must be provided with all necessary conduits, pits
              and pipes to accommodate the future connection of optic fibre technology
              telecommunications.
        32.   Certification must be submitted to Council from all relevant service providers
              which certifies that the development has met the requirements of this Decision
              Notice and all applicable legislation at the time of construction.
        Easements
        33.   A 3 metre wide easement for “Public Thoroughfare” purposes must be registered
              against the title of the property in favour of Council. The easement must be
              located adjacent to the northern boundary of the subject property. The easement
              must:
              a.    Be clearly shown on all plans submitted for Operational Works.
              b.    Be registered prior to the commencement of the use.
              c.    The terms of the easement must allow for the use of the easement by the
                    public whether in vehicles, cycles or on foot.




                                                                                  Page 17 of 25

Section 18

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    14 AUGUST 2018


        34.   Unless otherwise agreed in writing by the relevant service provider, any public or
              third party infrastructure located on the subject site must be placed within an
              easement registered against the title of the property.
        35.   All easements must be designed in accordance with the planning scheme and
              granted at no cost to the Grantee. Where the Grantee is Council or a service
              authority, the easement documentation must be in accordance with the Grantee’s
              standard easement terms. Draft easement documentation must be submitted to
              Council for endorsement.
        36.   All works must be kept clear of any existing or proposed easements on the
              subject land, unless agreed otherwise in writing by the Grantee.
        Earthworks and Retaining Walls
        37.   All earthworks, associated batters and retaining walls must be undertaken in
              accordance with an Operational Works approval, and must in particular:
              a.   Be undertaken in compliance with the provisions of Australian Standard
                   AS3798: Guidelines on Earthworks for Commercial and Residential
                   Developments.
              b.   Be carried out in accordance with a site-specific Geotechnical Investigation
                   Report prepared by a suitably qualified person* that addresses, in
                   particular:
                   i.    the impact of excavation and the construction works on the stability
                         of nearby building and infrastructures
                   ii.   Acid Sulfate Soil assessment report in accordance with State
                         Planning Policy 2/02 Planning and Managing Development Involving
                         Acid Sulfate Soils and supported by appropriate testing and
                         documentation.
              c.   Have all access chamber surface levels for drainage, water supply or
                   sewerage infrastructure within the work site be adjusted to provide a
                   freeboard of 100mm above the finished ground surface level or be in
                   accordance with the requirements and directions of the service provider.
              d.   All fill and associated batters must be contained entirely within the subject
                   site unless written permission from the respective landowner(s) is provided
                   to Council.
                   (*) refer to Advisory Notes
        Acid Sulfate Soils
        38.   Where excavations of non-imported soils below the elevation of 5m AHD are
              necessary for construction, the application for Operational Works for Bulk
              Earthworks, Stormwater and /or Landscaping must demonstrate and include
              certification from a suitably experienced and qualified geotechnical engineer of
              methods necessary to ensure construction and operation of the development:
              a.   Shall be consistent with Queensland Acid Sulphate Soil Technical Manual:
                   Soil Management Guidelines; and
              b.   will not result in the release of acid or associated metals; and
              c.   will not cause localised lowering of groundwater.



                                                                                 Page 18 of 25

Section 19

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                     14 AUGUST 2018


        Erosion and Sediment Control
        39.   Prior to the completion of the development, all site surfaces must be effectively
              stabilised. For the purpose of this condition, an effectively stabilised surface is
              defined as one that does not, or is not likely to result in visible evidence of soil
              loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to
              water contamination.
        Water Quality and Quantity
        40.   Except as otherwise modified herein, the development must be designed,
              constructed and maintained to achieve the stormwater quality and quantity
              outcomes detailed in the Site Based Stormwater Management Plan for 30-32
              Doonella Street, Tewantin Rev C by Bornhorst and Ward dated May 2017.
        41.   The development must include measures to prevent oils, hydrocarbons or other
              pollutants likely to be released in basement areas from being released into
              Council’s Stormwater system or other receiving waters.
        42.   Water quality treatment devices must be shaped and designed to be low
              maintenance, and integrate into the landscape. Where bioretention devices are
              proposed, the Operational Works Application for Stormwater Drainage,
              Landscaping and Earthworks must demonstrate how the design is consistent
              with the most current version of the Water by Design Bioretention Technical
              Design Guidelines.
        43.   Water Quality Treatment devices must be operated and maintained in
              accordance with manufacturer’s specifications and relevant maintenance
              manuals.
        44.   Prior to commencement of use the Community Management Statement must
              include provision for the engagement of personnel to operate and maintain Water
              Quality Treatment devices in accordance with manufacturer’s specifications,
              relevant maintenance manuals and the Site Based Stormwater Management
              Plan for 30-32 Doonella Street, Tewantin Rev C by Bornhorst and Ward dated
              May 2017.
        Water Reuse
        45.   Detail design plans submitted with the Operational Works Application must
              demonstrate how waters will be reticulated from the rainwater storage tank to
              reuse areas with a minimum water use of 342KL per annum.
        46.   A suitable backflow prevention device must be installed on water reuse facilities
              to protect the potable water within the reticulated water supply in accordance with
              AS/NZS 3500:2003 Plumbing and Drainage.
        WASTE MANAGEMENT
        Waste Storage
        47.   The development must provide waste storage and disposal facilities in
              accordance with Planning Scheme Policy 9, Waste Management, including an
              external imperviously paved area correctly sized for all refuse and recycling
              containers and suitably screened from public places and neighbouring
              properties.




                                                                                  Page 19 of 25

Section 20

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                       14 AUGUST 2018


              The waste management facilities should ensure recyclables bins are
              appropriately sited and accessible, and/or provided with their own waste shute,
              to ensure recyclable waste is not placed in the general waste shute.
        48.   The site must be provided with a bin wash area with a cold-water tap, hose and
              drain outlet connected to sewer, via a bucket trap. The drain outlet is to be
              designed to prevent storm water entry to the sewerage system which can be
              achieved by a bunded area, with a nib wall height of 100mm maximum, enclosing
              a wash area of 700mm x 700mm minimum (max 0.7m²). Alternatively, the waste
              area can be roofed, or any other appropriate design approved by Council.
        Building Demolition/Removal/Relocation
        49.   A Waste Management Plan (construction and demolition) must be submitted and
              approved by Council’s Environmental Health Officer prior to issue of a
              development permit for operational works for demolition, removal or relocation of
              any building other than a shed.
              The purpose of the Waste Management Plan is to facilitate the segregation of
              waste for the effective reuse and recycling of such materials. Segregated wastes
              attract significantly reduced disposal fees at the landfill with some items free.
              Higher gate fees are charged for mixed waste.
              Waste Management Plans (construction and demolition) are required to be
              submitted in accordance with Planning Scheme Policy 11, Waste Management
              Plans.
              Waste storage areas must provide adequate separation of all reusable,
              recyclable and waste materials. These must be located so that they are
              convenient and safe to use.
              The Plan must contain the following information:
                  The site area for the storage and separation of waste is to be shown on the
                    plan drawings accompanying the application.
                  A waste management table as indicated below is to be completed showing
                    how waste material is to be segregated - recycled – reused or disposed.
              Table – Waste Management Table

               MATERIALS ON-SITE                    DESTINATION
                                                    Re-use and Recycling              Disposal
               Expected        waste   Estimated    On-site          Off-site         *specify
               materials                                                              contractor and
                                       volume(m³)   *specify         *specify
                                                                                      landfill site or
                                                    proposed re-     contractor
                                                                                      other disposal
                                                    use or on-site   and recycling
                                                                                      site
                                                    recycling        outlet
                                                    methods
               Excavation material
               Green waste
               Bricks
               Concrete
               Timber-please specify

                                                                                     Page 20 of 25

Section 21

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                         14 AUGUST 2018



                  Plasterboard
                  Metals - please specify
                  Asbestos
                  Other - please specify
          Note * If a demolition contractor is undertaking works, then the Waste Management
          table is to be completed by the demolition contractor.
          ENVIRONMENTAL HEALTH
          Noise
          50.    Written certification is required from a suitably qualified person confirming that
                 sound pressure levels from all mechanical plant and equipment comply with the
                 following:
                 Air-conditioning and Refrigeration:
                     7am to 10pm: Maximum level allowable = background + 5dB(A)
                     10pm to 7am: Maximum level allowable = background + 3dB(A)
                 Pumps:
                     7am to 7pm: Maximum level allowable = background + 5dB(A)
                     7pm to 10pm: Maximum level allowable = background + 3dB(A)
                     10pm to 7am: No audible noise.
                 Assessment and certification is required immediately after installation of the
                 equipment and prior to any occupation of the building. All equipment should be
                 operating at the same time to test the overall noise level created, with the
                 measurement location at either the residential boundary or outside the most
                 exposed part of an affected building - whichever is the closest to the
                 plant/equipment.
                 The certification must be submitted to Council, which certifies that operational
                 noise from any fixed plant and equipment complies with the requirements of this
                 Decision Notice.
    B.    Find the following are sufficient grounds to justify the decision despite conflict with the
          Planning Scheme:
          1.     The multiple dwelling use is existing on the site.
          2.     The development will provide centrally located small dwelling units with access
                 to Tewantin’s facilities and services.
          3.     The development’s small dwelling units will increase residential housing options
                 in the locality and are likely to be relatively affordable.
          4.     There is no identified need for further community or infrastructure facilities within
                 Tewantin and the development will not unduly constrain land available for
                 commercial or community uses consistent with the site’s zoning provisions.
                                                                                             Carried.
    Cr Jurisevic re-joined the meeting.




                                                                                      Page 21 of 25

Section 22

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                       14 AUGUST 2018


4   NOOSA DOG BEACH EROSION
    Committee Recommendation
    Moved:            Cr Pardon
    Seconded:         Cr Jurisevic
    That Council note the report by the Project Officer to the Services & Organisation Committee
    meeting dated 8 August 2017 providing an update on erosion at Noosa Dog Beach and
    request staff seek expert advice on the management of this area into the future, with a further
    report to come to Council once that advice has been received.
                                                                                          Carried.


5   PROPOSED MOTION TO THE LOCAL GOVERNMENT ASSOCIATION OF
    QUEENSLAND 2017 ANNUAL CONFERENCE - REPEAL OF WASTE MANAGEMENT
    LEGISLATION
    Committee Recommendation
    Moved:            Cr Stockwell
    Seconded:         Cr Jurisevic
    That Council note the report by the Manager Waste and Environmental Health to the General
    Committee Meeting dated 14 August 2017 and submit the following Proposed Motion to the
    Local Government Association of Queensland for consideration at its 2017 Annual
    Conference:
    “That the LGAQ lobby the State Government to:
    A.    Oppose the potential repeal Part 2A Section 7 of the Waste Reduction and Recycling
          Regulations 2011 dealing with the areas that may be designated by a local government
          for the collection of waste which require local government to develop local laws to
          replace legislation; and
    B.    Oppose the potential repeal of Part 5A of the Environmental Protection Regulations
          2008 dealing with the operational requirements for the collection of waste, which would
          require local governments to develop local laws to replace Part 5A of the legislation,
          when the current requirements of Part 5A adequately satisfy the requirements of Local
          Government.”
                                                                                         Carried.


6   PROPOSED MOTION            TO THE LOCAL GOVERNMENT ASSOCIATION OF
    QUEENSLAND 2017            ANNUAL CONFERENCE - SHORT TERM VISITOR
    ACCOMMODATION
    Motion
    Moved:            Cr Stockwell
    Seconded:         Cr Jurisevic
    That Council note the report by the Chief Executive Officer to the General Committee Meeting
    dated 14 August 2017 and submit the following Proposed Motion to the Local Government
    Association of Queensland for consideration at its 2017 Annual Conference:




                                                                                   Page 22 of 25

Section 23

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                       14 AUGUST 2018


    “That considering the global concerns about the impact of unfettered growth of online booking
    agencies on housing affordability and supply of worker accommodation in tourist towns and
    cities around the world, the Local Government Association of Queensland:-
    A.   investigate international best practice in terms of data sharing between local authorities
         and service providers that help to ensure properties comply with appropriate planning
         schemes and rating requirements;
    B.   negotiate with online booking agencies on behalf of Queensland Councils to establish
         best practice arrangements;
    C.   make representations to the State Government seeking action to formulate a clear
         policy and response to the use of residential properties for short term accommodation
         where facilitated by on-line booking agencies including:-
         1.     Requiring the on-line booking agencies to provide Councils with property
                addresses so that they can appropriately rate the properties and ensure
                appropriate compliance with town planning scheme requirements; and
         2.     Consideration of the long-term impact on local communities including putting
                upward pressure on housing prices; reduced availability of rental accommodation
                stock, impact on local amenity and potential impact on existing tourism
                properties.”
                                                                                          Lost.

    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Jurisevic
    That Council note the report by the Chief Executive Officer to the General Committee Meeting
    dated 14 August 2017 and submit the following Proposed Motion to the Local Government
    Association of Queensland for consideration at its 2017 Annual Conference:
    “That the Local Government Association of Queensland make representations to the State
    Government seeking action to formulate a clear policy and response to the use of residential
    properties for short term accommodation where facilitated by on-line booking agencies
    including:
    A.   Requiring the on-line booking agencies to provide Councils with property addresses so
         that they can help to ensure properties comply with appropriate planning schemes and
         rating requirements appropriately rate the properties and ensure appropriate
         compliance with town planning scheme requirements;
    B.   Consideration of the long-term impact on local communities including the availability of
         rental accommodation stock, impact on housing affordability, impact on local amenity
         and potential impact on existing tourism properties.”
                                                                                          Carried.




                                                                                   Page 23 of 25

Section 24

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                             14 AUGUST 2018


7   NOOSA COUNCIL SIGNAGE POLICY
    Committee Recommendation
    Moved:             Cr Wellington
    Seconded:          Cr Jackson
    That Council note the report by the Acting Infrastructure Planning, Design & Deliver Manager
    to the General Committee Meeting dated 14 August 2017 and adopt the Noosa Signage
    Policy provided at Attachment 1 with the following change:
    Page 1 Paragraph 3 of the Policy: replace the words “guidance and procedures” with
    “direction”.
                                                                              Carried.



8   1617T113 CLEANING OF PUBLIC OPEN SPACE AND AMENITIES
    Committee Recommendation
    Moved:             Cr Pardon
    Seconded:          Cr Stockwell
    That Council note the report by the Civil Operations Manager to the General Committee
    Meeting dated 14 August 2017 and:
    A.   Award tender 1617T113 for Cleaning of Public Open Space and Amenities to the
         following contractors:
            Contract                                                                   Price per Year
                       Contractor
            Group                                                                      (GST Exclusive)
                       Harvent Pty Ltd      t/as   Total Building   Maintenance   -
            1                                                                              $71,191.12
                       Queensland

            2          IM Tattersall & KM Tattersall                                      $138,000.00

            3          Just Tha Clena Pty Ltd                                             $315,486.00

                       Harvent Pty Ltd t/as Total Building Maintenance -
            4                                                                             $335,062.00
                       Queensland
                       JK Nicholson & S Nicholson t/as Laguna Contracting
            5                                                                              $84,815.00
                       Services

    B.   Award tender 1617T113 for Cleaning of Public Open Space and Amenities for an initial
         period of three (3) years, with options to extend the contract for three (3) terms of up
         to twelve (12) months each. Options to extend will be at Council’s sole discretion and
         subject to Council’s review of Contractor performance under the Contract and
         proposed pricing.
                                                                                         Carried.




                                                                                        Page 24 of 25

Section 25

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                             14 AUGUST 2018


9    ASSESSMENT OF EXPRESSIONS OF INTEREST FOR A COMMERCIAL HIGH USE
     PERMIT (1718E013) - BEACH MASSAGE
     Committee Recommendation
     Moved:             Cr Jackson
     Seconded:          Cr Jurisevic
     That Council note the report by the Property Manager to the General Committee Meeting
     dated 14 August 2017 and issue a Commercial High Use Permit to Amanda Obara to conduct
     beach massage activities on Noosa Main Beach for the period 1 September 2017 - 30 June
     2020.
                                                                                                 Carried.


10   ASSESSMENT OF EXPRESSIONS OF INTEREST FOR COMMUNITY ACTIVATION OF
     LOT 5 LOWER MILL ROAD, COOROY (1617E131)
     Cr Pardon declared a material personal interest in this matter (as defined in section 172 of the Local
     Government Act 2009) as he is a Director of Cooroy Farmers and Artisans Market Pty Ltd who have
     submitted an application to run a community market on the site. Cr Pardon left the meeting room for
     the debate and decision on this matter.
     Committee Recommendation
     Moved:             Cr Stockwell
     Seconded:          Cr Jackson
     That Council note the report by the Property Advisor to the General Committee Meeting dated
     14 August 2017 and agree to issue a Community Market Permit to Cooroy Farmers and
     Artisans Market Pty Ltd as detailed in the report.
                                                                                        Carried.
     Cr Pardon re-joined the meeting.




                                                                                          Page 25 of 25

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.