Council archive · source document
Delegated Report - Code - Planning OPW21 0315 · OPW21/0315
7uthor Development Engineer, Diogo Carrico Development Assessment APPLICATION DETAILS Application No. OPW21/0315 Applicant Franco De Pasquale Proposal Operational Works – Earthworks, Vehicle Crossover Properly Made Date 3 November 2021 Information Request Date 25 November 2021 Information Response Date 4 February 2022 Decision Due Date 16 March 2022 Report Completed Date 7 March 2022 Report Reviewed By Mark Lewis PROPERTY DETAILS Property Address 33 Wyuna Dr Noosaville Qld 4566 RP Description Lot 16 N 10576 Land Area 615m² Existing Use of Land Residential STATUTORY DETAILS SEQRP Designation Urban Footprint Zone Low Density Residential Precinct Not Applicable Local Plan Area Not Applicable Overlays Acid Sulphate Soils (Area 1); Flood Assessment Type Code PROPOSAL The application seeks approval for Operational Works – Earthworks, Vehicle Crossover. The proposed works plans are included below. Figure 1 – Earthworks Figure 2 – Driveway Plan Figure 3 – SWMP site details Background Subject application follows up on the requirements of higher order approval RAP21/0020. The works include the construction of a basement which will require detailed dewatering procedures to ensure the water quality of the Noosa River – Council’s external stormwater consultant was engaged to review and provide comments and conditions for this component of the works. Site Description Surrounding Land Uses assessment Instruments for Statutory Assessment Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development: State Planning Policy; South East Queensland Regional Plan; Planning Regulation 2017; and Noosa Plan 2020. Noosa Plan 2020 The following codes from the Noosa Plan 2020 are applicable to this development: Driveways and Parking Code; Earthworks Code; Water Quality and Drainage Code. cONSULTATION Referral Agencies Not Applicable Internal Council Referrals Not applicable Other Referrals The application was forwarded to the following external experts for review and/or comment: Stormwater and water quality consultant. conclusion & reasons for decision The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval. The report is provided in accordance with Section 63(5) of the Planning Act 2016. RECOMMENDATION With regard to Application No OPW21/0315 RAP21/0020 for Operational Works – Earthworks, Vehicle Crossover situated at 33 Wyuna Dr Noosaville Qld 4566 and described as Lot 16 N 10576, it is recommended the application be approved in accordance with the following details for the Decision Notice: application details Application No: OPW21/0315 Street address: 33 Wyuna Dr Noosaville Qld 4566 Real property description: Lot 16 N 10576 Planning Scheme: Noosa Plan 2020 (25 September 2020) Decision details Council decided to issue the following type of approval: Development Permit for Operational Works – Earthworks, Vehicle Crossover CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 31073-OW3.1 B Earthworks & Piling Plan Prepared by SCG Engineering 02/02/2022 31073-OW3.2 . Earthworks & Piling Details Prepared by SCG Engineering August 2021 31073-OW4.1 A Driveway Crossover Plan Prepared by SCG Engineering 19/10/2021 31073-OW4.2 A Driveway Long Section & Details Prepared by SCG Engineering 19/10/2021 31073-SW1.1 B Stormwater Management Plan Prepared by SCG Engineering CURRENCY PERIOD The Currency Period for this development approval lapses if the development has not substantially started by 10 March 2024, unless an application to extend the currency period is approved by Council. PRIOR TO COMMENCEMENT OF WORKS Engineering All necessary approvals from external service providers (eg Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. A condition report including photographs of the frontage of the site must be completed and submitted to council prior to the prestart meeting. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Erosion and sediment control works; Other relevant parties A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction; Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased; Proposed fencing to the site during the construction phase of the development; Adequate parking arrangements for construction workers; No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off. Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures; Works programme identifying key components of the works and their respective durations; Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues; Include a post out to the local residents and businesses advising of the proposed development, the expected time frames and the site contact details; Include signage in prominent locations on the boundaries of the site advising of the proposed development, the expected time frames and the site contact details; identification of complaint management procedures including: contact details for the on-site manager; dispute resolution procedures. At least 5 business days prior to commencing works on site, the applicant is to provide to Council the location where excavated material is proposed to be transported for treatment of acid sulphate soils, and for final placement as fill. The location for final placement as fill is to have a lawful entitlement for the placement of the fill, with details to be provided to Council. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice; The relevant conditions of the higher order approval viz. RAP21/0020 to which this approval relates; All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. Pavement Design and Construction Pavement design for privately owned works must be undertaken in accordance with the relevant standards. Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and must be certified by an RPEQ. Works within Road Reserve/Reinstatement Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Site Access and Driveways Driveway crossover must be constructed in accordance with council’s Standard Drawings RS-049 and RS-050. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete; The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties; The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Acid Sulphate Soils and Dewatering All excavated material must be treated for acid sulphate soils generally in accordance with the recommendations provided by Douglas Partners letter dated 1st February 2022 headed ‘Additional geotechnical Investigation’. Treated material must undergo verification testing at the rate of one sample per 250 m3 throughout the duration of the excavation phase of the development. The verification testing must be undertaken by a qualified person in accordance with the Queensland Acid Sulphate Soil Technical Manual: Soil Management Guidelines v4.0, and the results must be submitted to Council for appraisal when requested during construction and prior to commencement of use and must demonstrate that the material has been adequately neutralised. Certification of the verification results for compliance with this condition must be provided by a suitably qualified Geotechnical Engineer prior to the issuing of the certificate of classification for the dwelling. Groundwater management is to be undertaken throughout construction generally in accordance with the ”Dewatering Management Plan Rev 1” prepared by ADG Consulting dated 2nd February 2022, except where the plan conflicts with any conditions of approval, in which case the conditions are to take precedence. Specific additional requirements are as follows: Construction is not to proceed beyond the hold points specified in Section 5.7 until a site inspection is held with Council’s delegate and agreement to proceed has been received in writing; A groundwater monitoring bore is to be established in the frontage of the site outside of the secant piling for the purposes of compliance with Conditions 27 and 28 of referral agency response RAP21/0020. The final location is to be discussed and agreed with Council’s Delegate at the pre-start meeting; The release point from the groundwater treatment system for the site is to be in a visible location over the revetment wall and not into the enclosed stormwater drainage system, with the final location to be discussed and agreed with Council’s Delegate at the pre-start meeting; The requirements of Section 6.5.2 (Water Quality Monitoring) are to be increased to include continuous monitoring of pH and dissolved oxygen at the release point from the treatment system. Total iron and aluminum are to be sampled where identified in the document as ‘if required’. Earthworks and Retaining Walls All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and uniformity of fill must be provided by a RPEQ and submitted to Council prior to commencement of use. Slope and batters are a maximum grade of: 1 in 6 where in proximity to waterbodies 1 in 4 for grassed areas. 1 in 3 for planted areas 1 in 2 for combined structural engineering and planting solutions. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods, Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods, Been revised to address predicted rainfall events, and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring. The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. FOLLOWING CONSTRUCTION Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. Final Inspection A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6245 to arrange for the inspection. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: General Advisory Notes Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart and Inspections Request Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the final inspection: Methods of stabilisation are: appropriate for slopes and slope lengths; and are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. If at the time of request for the final inspection, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability: evidence that the site has been effectively stabilised in the short term; evidence that soil has been adequately ameliorated; evidence that seed of annual and perennial grass species has been applied at an adequate rate; and that grass seed has germinated at a density that is likely to achieve an effective grass cover. VARIATION approval details Not applicable. further development permits required Type of Development Permit Required Subject of the required Development Permit Development Permit for Building Works All building work. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. [word/footer1.xml] Page 2 of 13 [word/header1.xml] 3 [word/header2.xml] DEVELOPMENT ASSESSMENT DELEGATED REPORT [Attachment: image1.png (image text)] SSESERoay a ETS: i z vals 1g HETEEEEE eRe: Seaideral: [Attachment: image2.png (image text)] \s DWELLING “a oh ages SUE eve [Attachment: image4.png (image text)] « tanpparces = i] EB a ee > LAND PARCELS 101 Sica | Property 138110 House Number 33 s wyuna Dr Let 16 Plan 10576 Lot Pian sen10576 Tenure Freehold Feature Name Locality Noosaville ParcelType Lot Type Parcel DAHistory —_DAHistory SARALink —_SARALLink Perimeserm 101.39371446464 Area m? 614.25497643587 Address 3 NOOSAVILLE QLD 4566 Thursday day Recycling Week Week? Thursday, 10 Mar 2022 (click on image to visit) [Attachment: image5.png (image text)] zone Ares Boundary OW Boundary 4 4 \ Zones Low Density = \ 4 Tourist Accommodation of Mejor oS 5 District Centre Centre Neighbourhood Centre @ Low Impact industry impact of Recreation and Open Space a Managem > \bane =. Je Innovation . Rural Residential Label Le 4 Local Supersedes 1985 Zone Superseded 2006 Scheme Pien 2020 4 ES
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW21 0315Related documentApplication case desk ↗
About this file
- File size
- 2.9 MB (large file)
- File type
- DOCX
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.