Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

Geotech

of 33

Page text shows just the words. Original shows the document exactly as it was published.

                                PROPOSED UNIT DEVELOPMENT
                                27 BOTTLEBRUSH AVENUE, NOOSA HEADS

If any soil conditions encountered during construction are found to differ from those noted in the geotechnical
investigation, Tectonic should be notified immediately and an inspection carried out to determine if changes
to footing design are required.

6.5       Temporary and Permanent Retention
Excavations are expected to range up to around 6 m BGL (existing ground levels) and, given that the
planned excavation extends close to some of the site boundaries and underground infrastructure (e.g.
sewer), some form of temporary shoring will be required to support the excavation.
Based upon our experience with similar sites, we anticipate that temporary shoring may be achieved by use
of sheet piles, however Unitywater requirements for the sewer may restrict the use of sheet piles. Shoring of
deeper cuts would likely require lateral restraint, and this is conventionally achieved by helical steel anchors
(similar to screw piles). However, the proximity to neighbouring properties would require permissions to be
obtained for subterranean access. Therefore, where lateral support by cantilever only is not feasible, it is
suggested that internal struts/propping be considered to provide lateral restraint for the shoring system.

Anchored or propped sheet piles may require pre-drilling to prevent adverse vibrations during sheet pile




                                                           T
installation.

Other shoring methods that could be considered include bored contiguous or secant piles. Non-contiguous
or soldier pile walls are not feasible for the proposed development due to the likelihood that loose sands
would ‘flow’ through gaps between the piles.
                            AF
An advantage of contiguous or secant pile wall retention systems is that they are ultimately used for the
permanent walls, whereas sheet piles would be temporary to provide retention during construction only,
therefore requiring a permanent structural wall to be constructed. Bored pile walls generally require greater
width (horizontally) for installation as compared to sheet piles and are often more expensive.

The advice of a specialist shoring contractor must be sought regarding feasibility, design and installation of
the proposed retention and subsurface drainage system. It will be necessary to conduct numerical analysis
to optimise the retention system. Detailed design will also need to account for relevant factors of safety to
maintain the temporary and long-term stability of the retention system.

Retaining structures greater than 1 m high, or those required to support surcharge loads or sloping backfill,
        R
will require engineer design and certification of construction. Retaining wall design should be carried out in
accordance with AS4678-2002 Earth retaining structures.

Design for temporary and permanent retaining structures could be carried out using a trapezoidal (for
propped or anchored walls) pressure distribution applicable to the wall type and based on the parameters
listed in Table 4. These values do not include allowance for hydrostatic pressures nor transient (e.g.
D

construction) or adjacent footing loadings.
Table 4: Retaining Structure Design Parameters
                                                                     Lateral earth pressure coefficients
                              Unit
                                         Friction
 Retained material           weight
                                         angle (°)            Ka                        Ko
                             (t/m3)                                                                        Kp
                                                       (Cantilever wall)        (Non-yielding wall)


 Very Loose/ Loose
                               1.8           28               0.36                     0.53                2.77
 Sands


 Medium Dense (or
                               1.9           34               0.28                     0.44                3.54
 Denser) Sands


 Future Controlled Fill*        *            *                   *                       *                  *

Note:    * Depends on fill material type and level of compaction.


10 November 2021
Report No. 21286-001-Rev0                                   13
Log in to download the original file

Geotech.pdf · 7.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.