                       CIVIL ENGINEERING PROJECT MANAGEMENT
                            SEDIMENT AND EROSION CONTROL




                          HYDRAULIC IMPACT ASSESSMENT
                        at 332 Eastern Branch Road, KIN KIN
                                    for QRE Constructions


     DATE:         22.03.23                    REF:     304-001-01


     ATT:          Development Officer         EMAIL: [email protected]
                   Noosa Council
     REV:          A




2261 david low way, peregian beach, qld 4573   acn: 626 671 092      [email protected]
Log in to download the original file

Hydraulic Assessment_compressed.pdf · 4.8 MB (large file)

The download may take up to a minute.

Full text of the other 24 pages

Page 2

CONTENTS PAGE




                    Topography ............................................................................................................... 11
                    Hydraulic Roughness Coefficients.............................................................................. 11
                    Boundary Conditions and 1d infrastructures ............................................................. 11


                    Base case and Post Development hydraulic model results........................................ 12
                    Flood Extents ............................................................................................................. 13




                                            Page 2 of 17
 2261 david low way, peregian beach, qld 4573      acn: 626 671 092                                   [email protected]

Page 3

LIST OF FIGURES
Figure 1 - Locality Plan Source: Queensland Globe ............................................................................................. 5
Figure 2 – Existing Waterways Source: Noosa Council ........................................................................................ 6
Figure 3 – Existing Flood Risk Source: Noosa Council .......................................................................................... 7
Figure 4 – Proposed Nature Based Tourism Layout............................................................................................. 8
Figure 5 – Point inspection location................................................................................................................... 12

LIST OF TABLES
Table 1 – Peak Discharge at Culvert Crossing .................................................................................................... 13
Table 2 –Culvert Crossing Capacity .................................................................................................................... 13
Table 3 - General Construction Pollutants ......................................................................................................... 14

LIST OF APPENDICES
 Appendix A                Development layout
 Appendix B                WBNM Catchment Plan
 Appendix C                Tuflow Model Extent
 Appendix D                Pre-Development Flood Maps
 Appendix E                Post-Development Flood Maps




                                               Page 3 of 17
    2261 david low way, peregian beach, qld 4573      acn: 626 671 092                                         [email protected]

Page 4

            INTRODUCTION



Bax Engineering has been commissioned by QRE Constructions to provide a Hydraulic Impact Assessment for
the Proposed Nature Based Tourism application at 322 Eastern Branch Road , Kin Kin Queensland.


The existing site covers a site area of 0.75ha and is located in 332 Eastern Branch Road , Kin Kin. The proposed
development consists of an access road and four (4) Glamping Tent/Cabin style accommodation units to be
constructed around the property.


This report has been developed to address the hydraulic impact assessment and stormwater management.
The report investigates the flood constraints and details in relation to water levels and flood depths across the
site, the management of stormwater during the operational phase of the project as well as emergency access
requirements during major storm events.


This HIA and SMP has been prepared in accordance with:
        •   Noosa Council 9.4.8 Water Quality and Drainage Code,
        •   The Queensland Urban Drainage Manual (QUDM), and
        •   Australian Rainfall and Runoff (2019)




                                              Page 4 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092            [email protected]

Page 5

           THE SITE AND ITS CONTEXT

                   SITE LOCATION

The site is formally described as Lot 218 on MCH186 and is located at 332 Eastern Branch Road in Kin Kin. The
site covers an area of 19.65ha and is covered by grass with heavy vegetation along the creek and throughout
the site. The site is zoned rural under the Noosa Plan (2020).

Figure 1 presents the site and its surroundings.




                                Figure 1 - Locality Plan Source: Queensland Globe

                   SITE CHARACTERISTICS

The total area of the subject lot is 19.65ha with the elevation range between 175m AHD in the south west to
80.0m AHD towards the south east boundary. Based on the provided survey and aerial information, any
stormwater runoff from the site overland flows to the existing creek systems that runs through the property.


                                              Page 5 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092               [email protected]

Page 6

Several existing culvert crossings are noted throughout the property to enable vehicle access across these
waterways.


The defined drainage paths over the property Figure 2 and consist of both ephemeral and constantly running
waterways. It is noted that the waterway crosses the Eastern Branch Road in numerous locations to the north
and south of the property and is prone to flooding during prolonged rain events (Refer Figure 3). During such
times, the risk of temporary isolation to residents living in these surrounds is well recognised.


Twenty-four external upstream catchments to the south east of the site drain to the watercourse as overland
flow. These catchments are identified in Appendix A (Project: BAX22100 Drawing: C01)




                              Figure 2 – Existing Waterways Source: Noosa Council




                                              Page 6 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092            [email protected]

Page 7

                              Figure 3 – Existing Flood Risk Source: Noosa Council



                   EXISTING VEGETATION AND USE

The project site is covered by grass with heavy vegetation along the creek and throughout the site. Several
cleared areas with long grass are scattered throughout the property along with vehicle tracks access to each
of these areas. Cattel yards are present on the property and an existing residential dwelling is located in the
north at an elevation of approximately 98m AHD. A non-habitable shed is located to the south of the dwelling
at approximately 86m AHD. Both structures are connected to the Eastern Branch Road by a gravel access road.
This road traverses the waterway via an existing concrete culvert crossing.




                                              Page 7 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092                [email protected]

Page 8

                   PROPOSED DEVELOPMENT

The proposed development will consist of 4 glamping style tents/cabins with a driveway connection to each
from the main property entrance. The cabins will be located in the existing cleared areas on the property and
linked via a single access driveway. The existing concrete culvert crossings over the creek will also be utilised
to limit disturbance to the riparian area.
Each cabin will be connected to a rainwater harvesting tank for water re-use and the tanks will discharge via a
level spreader to the surrounding grassed area and discharge as sheet flow to the creek. This system will be
clear of the wastewater effluent disposal system (refer Ground Drill Effluent Disposal Report 22/388 dated
11.11.22).
The proposed layout has been designed to provide privacy for each user while minimising the environmental
footprint by utilising existing cleared areas and vehicle access locations across the waterways. The proposed
layout is shown in Figure 4 and a detailed concept of the access driveways and unit localities are provided in
the civil plans prepared by BAX Engineering (Ref: 304-001) in Appendix B.




                              Figure 4 – Proposed Nature Based Tourism Layout

                                              Page 8 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092            [email protected]

Page 9

                   PROPOSED DRAINAGE CONCEPT

It is proposed that the runoff from the cabins be captured for reuse and diverted to a proposed rainwater tank
located adjacent to each cabin. In accordance with Council Planning Scheme Policy for Development Works,
a development type MCU for purposes other than industrial use and for lot sizes greater than 2500m 2 and
with a fraction impervious of less than 25% will require vegetated buffers to waterways and drainage lines.
It is noted on the proposed layout that large open zones allow a natural buffer from each cabin to the creek
line. This buffer along with the proposed rainwater tanks would deem to comply with the stormwater quality
requirements of the Noosa Council.


                   RAINFALL DATA

Rainfall intensity data has been obtained from the Australian Bureau of Meteorology’s 2016 Design IFD Rainfall
System. The IFD data and average rainfall intensities used in this report are in accordance with the procedures
outlined in Geosciences Australia, Australian Rainfall and Runoff 2019.




                                              Page 9 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092           [email protected]

Page 10

            DATA

Data which has been sourced or provided, in order to prepare this report for the site, was gathered from the
following sources:

        •   Proposed site layout provided by BAX Engineering civil plans, (Ref: 304-001);
        •   LIDAR data for the subject site sourced from Australian Government Elevation and Depth
            Foundation Spatial Data (ELVIS), Date Source: 2015, DEM Data;
        •   Rainfall and Meteorological 2019 IFD Data by the Australian Bureau of Meteorology;
        •   Information Extracted from Noosa Council Interactive Mapping;
        •   Aerial Imagery by Nearmap.




                                              Page 10 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092          [email protected]

Page 11

            HYDRAULIC MODELLING

Based on Council’s flood overlay mapping, the project site is affected by flood from the eastern Branch of Kin
Kin Creek which runs through the property. Overland flow modelling, has been undertaken for the site and
surrounding area under the existing conditions to establish the level of inundation immunity for the
development. Overland flow modelling was conducted for the 1%, 10% and the 63% AEP design flood events.


The modelling was completed using the TUFLOW software 2020-10-AD package and LiDAR data sourced from
the Department of Natural Resources and Mines. Details on the development of the model and discussion of
the results are provided herein.



                   BASE CASE MODEL SETUP

            Topography

A Digital Terrain Model (DTM) was created for the study area using 1m resolution LiDAR supplied by the
Department of Natural Resources and Mines in conjunction with detailed site survey.

            Hydraulic Roughness Coefficients

Different Manning’s coefficients (n) have been applied to reflect the various land uses within the catchment.
This was achieved by defining polygons for the various land uses and assigning the relevant “n” value. The
study area was delineated based on the following land uses:
        •   Urban Area (default)           n = 0.06;
        •   Road/Carpark           n = 0.02;
        •   Light Grass            n = 0.035;
        •   Dense Woodlands n = 0.1;
        •   Buildings and Shed n = 1;
        •   Creeks/Waterway n = 0.07;

            Boundary Conditions and 1d infrastructures

Inflows were undertaken and TUFLOW’s automatic HQ relation was adopted at Downstream boundary and
existing culverts’ details were indicated in the Tuflow model key




                                              Page 11 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092          [email protected]

Page 12

                    HYDRAULIC MODELLING RESULT

              Base case and Post Development hydraulic model results

2D Flood mapping has been conducted for peak flood levels, velocity, depth and flood level impact for the 1%,
10% and 63.2% AEP for the Base Case and Post development scenarios and are presented in the appendices
as follows:


        •     Appendix C Base Case Flood Maps; and
        •     Appendix D Post Development Flood Maps;



Inspection locations have been identified at the culvert crossing to assess the flooding characteristics of the
crossings. These inspection points are shown in Figure 5. The peak discharge levels for the simulated design
storm events in the pre-development scenario are presented in Table 4. These include the Q100, Q10 and the
Q2 events whereby vehicle access should be achievable.




                                     Figure 5 – Point inspection location



                                              Page 12 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092           [email protected]

Page 13

Table 1 – Peak Discharge at Culvert Crossing

         Location                1% AEP (m³/s)             10% AEP (m³/s)              50% AEP (m³/s)

 3 x 600 RCP
                                        60.0                    32.1                          16.3
 (Existing Driveway)
 3 x 900x600 RCBC                       51.9                    32.7                          17.3

 1500 x 900 RCBC                        8.2                      2.6                          0.2



Table 2 –Culvert Crossing Capacity

                        Pipe Capacity
     Location                                  1% AEP (m³/s)        10% AEP (m³/s)          50% AEP (m³/s)
                           (m³/s)
 3 x 600 RCP
 (Existing
                            4.119                  60.0                  32.1                    16.3
 Driveway)
 at 5% grade
 3 x 900x600 RCBC
                            6.882                  51.9                  32.7                    17.3
 at 3% grade
 1500 x 900 RCBC
                            9.967                   8.2                   2.6                       0.2
 at 5% grade


As demonstrated in Table 2, the existing driveway location to the dwelling (3 x 600 RCP) and the crossing to
the proposed units would be inaccessible during the design storm events. However, the existing culvert (1500
x 900 RCBC) linking the existing dwelling/managers residence to the cabin locations is immune to flooding for
each of the design events. Considering the flooding which would be occurring external to the site - along the
Eastern Branch Road - and would restrict access to the property during rain events, the only consideration
should be for clients who are already at the accommodation and are obliged to seek refuge.
It could therefore be considered the location of the existing dwelling/managers residence at a much higher
elevation would provide suitable protection during such times until water levels resided.

            Flood Extents

The flood extents for each storm event have been modelled and shown in Appendix D. The locations of each
of the proposed cabins are immune from flooding for all the design events. Though, it is noted that the most
eastern cabin would likely become isolated – albeit intermittently - during the designed storm events.




                                              Page 13 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092           [email protected]

Page 14

            STORMWATER QUALITY MANAGEMENT

In accordance with Council Planning Scheme Policy for Development Works, a development type MCU for
purposes other than industrial use and for lot sizes greater than 2500m2 and with a fraction impervious of less
than 25% will require vegetated buffers to waterways and drainage lines.


                      CONSTRUCTION PHASE

The design milestones for water quality during the construction phase of the development will be in
accordance with SPP Code: Water Quality. The design objectives will be achieved using approved Sediment
and Erosion Control measures.


General pollutants generated during construction are listed in Table 3 below.



Table 3 - General Construction Pollutants

            Pollutant                               Potential Source                          Priority
                            Paper, construction packaging, food packaging, cement bags,
        Litter                                                                                  High
                            off cuts
                            Unprotected exposed soils and stockpiles during earthworks
        Sediment                                                                                High
                            and building works
                            Fuel and oil spills, leaks from construction equipment and
        Hydrocarbons                                                                            High
                            temporary car park areas
                            Cement slurry, asphalt primer, solvents, cleaning agents,
        Toxic Materials                                                                       Medium
                            wash waters (e.g., From tile works)
        Alkaline
                            Cement slurry and wash waters                                       High
        Substances



Below are the characteristic treatment measures that will be implemented prior to any construction works.
Detailed Sediment and Erosion control measures and drawings are included as part of an operational works
application.

        •      Sensible site planning
        •      Stabilized site entry / exit point
        •      Minimization of site disturbance and duration of disturbance
        •      Implementation sediment control along the lower edge of the site
        •      Appropriate location and protection of stockpiles



                                              Page 14 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092                 [email protected]

Page 15

       •   Early connection of roof water downpipes
       •   Compaction of backfilled trenches
       •   Revegetation and stabilization of the site



                  OPERATIONAL PHASE

As demonstrated on the proposed layout, large open zones allow a natural buffer from each cabin to the creek
line. This buffer along with the proposed rainwater tanks would deem to comply with the stormwater quality
requirements of the Noosa Council.




                                              Page 15 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092        [email protected]

Page 16

              CONCLUSION

The pre and post development scenario for the subject and the external catchment hydrology has been
reviewed to ensure safe access can be achieved or refuge sought during flood events. Stormwater quantity
and quality from each of the proposed cabin locations has also been considered.


The following conclusions have been made:
     •    based on the proposed locations of the cabins, the areas proposed appear to be free of flood during
          the modelled storm events.
     •    Access to the cabins would be restricted during the design storm events modelled. Nonetheless so
          would access to the property based on the unpassable creek crossings on Eastern Branch Road.
          Therefore, access from the cabins to a point of refuge has been considered and can be achieved. This
          point of refuge would be the existing dwelling/managers residence at a higher elevation.
     •    Stormwater quality treatment can be achieved through rainwater harvesting tanks and buffer areas.
     •    The environmental footprint for the cabins would be minimal based on the areas already cleared and
          the tracks and culverts already in place.



In summary, the proposed cabin locations on the subject site will result in non-actionable nuisance of
stormwater runoff, be free of flooding and have safe refuge opportunities should it be faced with unpredicted
intermittent weather.


Yours Faithfully,




GLENN AINSWORTH
MIEAust CPEng NER RPEQ CPESC
BAX ENGINEERING PTY. LTD.
Ph: 0407 021 300




                                               Page 16 of 17
    2261 david low way, peregian beach, qld 4573      acn: 626 671 092          [email protected]

Page 17

 REFERENCES


Civil Design
Prepared by Bax Engineering (Document No: 304-001-001 to 800) dated 25.11.22

Noosa Council – Relevant Codes and Standards
Part 9 Development Code
9.4.8 Water Quality and Drainage Code

Noosa Council – Flood Hazard Mapping

Queensland Globe – Site Mapping
https://qldglobe.information.qld.gov.au/


The Queensland Urban Drainage Manual (QUDM),

Australian Rainfall and Runoff (2019)

MUSIC modelling guidelines (Water by Design, 2010).




                                              Page 17 of 17
   2261 david low way, peregian beach, qld 4573      acn: 626 671 092    [email protected]

Page 18

                                                    APPENDIX A
                                            Development Layout
https://www.dropbox.com/s/g7j0l9rofobnb32/Appendix%20A.pdf?dl=0

Page 19

APPENDIX B
WBNM Catchment Plan

Page 20

@
N

o ee

{3
a
Oo
Oo

So
N

ras
oO

QO
rar
are

=
pS s

19.9
6.1

BE
ee
w

oO
e
sb

25.0
13.2

O10
alu

Qa
e
N

ela|
Bile
w] oc

alalea
y
Es :

N

25

{a
N
NIL

Q
oO
b

>

B/S

§ g so
ac
oS

G

0

400 600

800

1,000 m

1:15,000 (A3)

Coordinate System: GDA 94/MGA Zone 56

Legend

(J catchment
|_| Project Site
{| veos
—— Contour
»——> Flowpath
Topography (mAHD)

238

 

Page 21

Legend
{| peps

[-} intemal catchment
—— Contour

100 150 200 250 300m Project: oe Development - 332 Eastern Branch Road,

Client: QRE Construction ror
1:4,000 (A3)
Coordinate System: GDA 94/MGA Zone 56 Figure: Internal Catchment Plan

 

Page 22

APPENDIX C

Tuflow Model Extent

Page 23

                         3x600x900 RCBC




       1500x900 RCBC


                       3x600 RCP




                                                                                                                         Legend
                                                                                                                         Existing Culvert

                                                                                                                         Existing Track

                                                                                                                         Project Site

                                                                                                                         Local inflow

                                                                                                                         Tuflow Model Extent




Rev.    Date                                               Project: Residential Development - 332 Eastern Branch Road,       Date
                                                                                                                             Feb 2023
                                                           Kin Kin
                                                                                                                             Project #
                                                           Client: QRE Construction                                          BAX22100
                                   1:7,000 (A3)
                                                                                                                             Drawing C02
                   Coordinate System: GDA 94/MGA Zone 56   Figure: Tuflow Model Configuration
 A     10.02.23

Page 24

                                                    APPENDIX D
                                     Pre Development Flood Maps
https://www.dropbox.com/s/g7j0l9rofobnb32/Appendix%20A.pdf?dl=0

Page 25

                                                    APPENDIX E
                                    Post Development Flood Maps
https://www.dropbox.com/s/g7j0l9rofobnb32/Appendix%20A.pdf?dl=0

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.