OPW15/0099 Decision Notice

of 1

Text shows just the words. Original shows the document exactly as it was published.

Officer:	Monkeith Kadhum
Direct Telephone:	07 53296293
Our Reference:	MKADHUM:OPW15/0099
Your Reference:	n/a

15 October 2015

Palm Lake Works
C/- Calibre Consulting
PO Box 997
BUDDINA  QLD  4575

[email protected]

Dear Sir/Madam

Decision Notice
Sustainable Planning Act 2009

I refer to your application and advise that on 13 October 2015, Council decided to approve the application in full subject to conditions.
Details of the decision are as follows:
1.	APPLICATION DETAILS

Application No:	OPW15/0099
Street Address:	19 Trading Post Rd & 4 Lamonts Rd, COOROY  QLD  4563
Real Property Description:	Lot 1 RP 215922 and Lot 2 RP 165418
Planning Scheme:	The Noosa Plan (16 September 2013)

2.	DECISION DETAILS

The following type of approval has been issued:
Development Permit for Operational Work - Bulk Earthworks

3.	RELEVANT PERIOD OF APPROVAL

The relevant period for this development approval is 2 years starting the day that this development approval takes effect.

4.	ASSESSMENT MANAGER CONDITIONS

APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.

Plan No.	Rev.	Plan/Document Name	Date
15-001261-102	-	Bulk Earthworks Layout Plan Sheet 1 of 3, prepared Calibre Consulting	12/06/2015
15-001261-103	A	Bulk Earthworks Layout Plan Sheet 2 of 3, prepared Calibre Consulting	27/08/2015
15-001261-104	-	Bulk Earthworks Layout Plan Sheet 3 of 3, prepared Calibre Consulting	12/06/2015
15-001261-105	A	Bulk Earthworks Interface Sections, prepared Calibre Consulting	27/08/2015

SITE SPECIFIC CONDITIONS
All Subsequent Operational Works Applications for internal stormwater, civil and landscaping must include design and other relevant documentation consistent with the Letter Report (Ref No B14158.W.7L) form Calibre Consulting dated 8 October 2015 and approved by Noosa Council on 13 October 2015 except as modified herein:
Cyanobacteria Blooms Operational Phase Monitoring for Macrophyte Coverage must be triggered where peer reviewed journals are published that specify a coverage or dieback rate for Macrophytes.
Performance indicators to trigger corrective actions for Microcystis aeruginosa must be updated as relevant to be consistent with health regulations.
References to declared weeds must also include for environmental weeds
The final form of earthworks shall provide for consistency with the Letter Report (Ref No B14158.W.7L) form Calibre Consulting dated 8 October 2015 and approved by Noosa Council on 13 October 2015, detailing the Stormwater Management and Construction and Maintenance Plan specifications, except as modified herein.

PRIOR TO COMMENCEMENT OF WORKS
Engineering
A condition report including photographs of the frontage of the site, leading roads and access points must be completed and submitted to Council at the prestart meeting.
The principal contractor must have all the appropriate insurance and public liability documentation to carry out the works. The principal contractor is also responsible to ensure that any subcontractors also have the appropriate insurance and public liability documentation. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart.  The contact number to arrange a pre-start meeting is 53296244.  The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works including the principal contractor.
Erosion and sediment control works.
Other interested parties.
A Construction Management Plan must be submitted to council prior to the prestart meeting and must specifically address the following:
Traffic management during all aspects of the construct phase including:
A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures to address any potential of adverse traffic impact on the main and local roads.
Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased.
Proposed fencing to the site during the construction phase of the development.
Adequate parking arrangements for construction workers.
No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off.
Works programme identifying key components of the works and their respective durations.
Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues.
Identification of complaint management procedures including:
Contact details for the onsite manager.
Dispute resolution procedures.
Where applicable, details on the location of external fill sites/sources, the haulage route, type of vehicle to be utilised during filling operations and frequency of usage.  NOTE: any damage to the existing road system as a result of the works and/or the haulage operations must be fully repaired at the applicant’s expense.
Where work access to the site is required via Elm Street, an approval of the Traffic Management Control Plan must be obtained from Department of Transport & Main Roads (DTMR) and submitted to Council prior to the prestart meeting.
Prior to the prestart meeting, a written advice must be provided to council detailing:
The name, contact details and ACN for the supervising Registered Professional Engineer of Queensland (RPEQ) and Principal Contractor.
Proposed dates for commencement and completion of construction.
Certificates demonstrating currency of public liability insurance and works insurance covering the works in line with the planning scheme.
Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.

DURING CONSTRUCTION
Engineering
The integrity and condition of any existing public or Council infrastructure and services (above ground and/or underground) must not be adversely affected by the proposed works.
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works approval.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans and conditions detailed in this Decision Notice.
The relevant conditions and associated approved reports of the higher order Material Change of Use approval File:132007.2398 to which this approval relates.
All relevant council Planning Scheme Policies, standard drawings, standard specifications and guidelines.
The latest version of Water Sensitive Urban Design Technical Design Guidelines for South East Queensland (Healthy Waterways) for all water quality devices to be constructed on site.
All retaining walls must be provided with appropriate fall hazard protection.
All retaining walls over one metre high must be supervised and certified by RPEQ
All earthworks shall be undertaken in accordance with the provisions of AS 3798, Guidelines on earthworks for commercial and residential development, with geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as defined in Appendix B.  Test results as required by AS 3798, and a certificate of quality and uniformity of fill, shall be provided by a RPEQ and submitted to council prior to final inspection.
Slope and batters are a maximum grade of:
1 in 6 where in proximity to waterbodies.
1 in 4 for grassed areas.
1 in 3 for planted areas.
1 in 2 for combined structural engineering and planting solutions.
Works Within Road Reserve
No removal of street trees is permitted without Council’s prior written approval.
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows).
Erosion and Sediment Control
A construction hold point with a council delegate and supervising RPEQ must be established prior to commencement of cut to fill earthworks for each stage of the development. The hold point must be held as soon as reasonably practical and prior to the first rain event forecast following initial tree clearing or removal of soil stabilising material for each stage. At the hold point inspection, all required sediment basins, drains and bunds to divert waters away from disturbed soil or soils about to become exposed through cut to fill activities must be installed. All areas that will not require earthworks in the imminent cut to fill operation must be stabilised to prevent entrainment of sediments into receiving waters.
Cut to fill earthworks must not commence until after the Supervising RPEQ has certified that all installed erosion and sediment controls required by this approval are sized in accordance with conditions of the approval and the written acceptance of the certification is provided to the supervising RPEQ by Council officers.
Offsite run-off must be diverted around exposed soils on the site without entraining additional sediments. Discharge from measures to divert the offsite water must not cause run-off impacts to other properties. Measures installed to divert the upstream water must be designed and certified by the supervising RPEQ and installed prior to commencement of bulk earthworks.
Any temporary drainage works to manage stormwater flows during the construction phase of development must be designed by the supervising RPEQ to provide a 150mm freeboard and convey the following flow capacities without resulting in visible scour within flow paths:
1 in 2 year event where disturbed area open for less than 12 months
1 in 5 year event where disturbed area open for 12-24 months
1 in 10-year ARI event where disturbed area open for 24 months
Minimum 1 in 1 year ARI Hydraulic capacity for temporary culvert crossings
E&SC measures must be  installed and maintained to ensure any waters discharged from the site up to and including a  85%ile 5 day rain event (or 46mm rainfall event)  contain less than 50mg Total Suspended Solids per litre. All relevant measures detailed in the International Erosion and Sediment Control Book 2008 or Sunshine Coast Manual for Erosion and Sediment Control must be installed to minimise the amount of sediment leaving the site in rainfall events that exceed 85%ile 5 day or 46mm.
Peak 1-year ARI event discharge from the construction phase of development must be equivalent to the pre-development peak 1-year ARI event discharge. Measures included in calculations to achieve management of peak flows must be incorporated into the development in a manner that is consistent with the Noosa Plan, all conditions of the approval and does not interfere with adjoining properties.
Unless otherwise agreed to in writing by Council Officers, all site surfaces must be effectively stabilised prior to the earthworks contractor vacating site. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Flora and Fauna Protection
A qualified person* must be engaged to manage fauna prior and during clearing to:
Ensure works are carried out in accordance with the Nature Conservation Act 1992.
Undertake pre-clearing inspections including fauna relocation and removal or blocking of all vacant hollows.
Ensure clearing works avoids nesting times of animals and birds.
Co-ordinate staging and sequence of clearing with fauna protection.
Protect and recover fauna during clearing operations (not previously removed).
Manage the translocation of animals and recovery procedures in accordance with relevant legislation.
(*refer advisory note)
Vegetation removal, felling and lopping must:
Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
Mulch all other wood and leaf material (without root balls, soil or debris and minimising weed seeds) for re-usable mulch.
Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum of three months.
Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation between piles.
Allow for existing endemic ground flora to be translocated to suitable landscaping and rehabilitation areas.
Vegetation removal or pruning must be undertaken in a manner that avoids damaging surrounding vegetation and habitat.
Conclude with the area being stabilised against erosion.

FOLLOWING CONSTRUCTION
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the requirements of this Operational Works permit.
A final inspection and approval of the completed works by Council’s Inspector is required.  Please contact Council on 5329 6244 to arrange for the inspection.

5.	REFERRAL AGENCIES

Not Applicable.

6.	REFERENCED DOCUMENTS

The following documents are referenced in the assessment manager conditions:
Referenced Documents
Document No.	Rev.	Document Name	Dated
B14158.W.7L		Update Letter Report for Concept Stormwater Quality Maintenance Plan, prepared by Calibre Consulting	8 Oct 2015 and approved by Council on 13 Oct 2015

7.	ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the accuracy of the drawings has not been undertaken, as they have been certified by a RPEQ.  The RPEQ bears full responsibility for all aspects of the engineering design.  Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent.
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Sustainable Planning Act 2009 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Prestart, Inspections Request
Contact Council on 5329 6244 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time.
It should be noted prior to arranging a pre-start meeting the Appeal Period of 20 business days must have passed or the applicant must have provided Council with written confirmation that the applicant has accepted the conditions of Decision Notice and waived their appeal rights
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
Environmental Advisory notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Qualified Person – Flora Fauna Protection
For the purpose of managing fauna, a qualified person is considered to be a spotter/catcher person with a minimum of 3 years current field experience and Undertaking Fauna site works is considered to be a Fauna Spotter Catcher with current certification under the Queensland Parks and Wildlife Service.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that:  “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage.”   It is an offence to fail to comply with the duty of care.  Substantial monetary penalties may apply to individuals or corporations breaching this duty of care.  Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3239 3647 to discuss any obligations under the ACH Act.

8.	PROPERTY NOTES

Not Applicable.

9.	PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME

Not Applicable.

10.	FURTHER DEVELOPMENT PERMITS REQUIRED

Not Applicable

11.	SELF ASSESSABLE CODES

Not Applicable.

12.	SUBMISSIONS

Not Applicable.

13.	REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not Applicable.

14.	RIGHTS OF APPEAL

You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.

15.	OTHER DETAILS

If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices.

Yours faithfully

Monkeith Kadhum
Development Engineer

cc	Unitywater

Enc:	Approved Plans/Documents
Appeal Rights

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009  (Chapter 7).
MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS

Division 8 	Appeals to court relating to development applications and approvals

461 	Appeals by applicants
(1) 	An applicant for a development application may appeal to the court against any of the following—
(a) 	the refusal, or the refusal in part, of the development application;
(b) 	any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242;
(c) 	the decision to give a preliminary approval when a development permit was applied for;
(d) 	the length of a period mentioned in section 341;
(e) 	a deemed refusal of the development application.
(2) 	An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after—
(a) 	if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or
(b) 	otherwise—the day a decision notice was required to be given to the applicant.
(3) 	An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made.

462 	Appeals by submitters—general
(1) 	A submitter for a development application may appeal to the court only against—
(a) 	the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	the part of the approval relating to the assessment manager’s decision under section 327.
(2) 	To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following—
(a) 	the giving of a development approval;
(b) 	any provision of the approval including—
(i) 	a condition of, or lack of condition for, the approval; or
(ii) 	the length of a period mentioned in section 341 for the approval.
(3) 	However, a submitter may not appeal if the submitter—
(a) 	withdraws the submission before the application is decided; or
(b) 	has given the assessment manager a notice under section 339(1)(b)(ii).
(4) 	The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter.

463 	Additional and extended appeal rights for submitters for particular development applications
(1) 	This section applies to a development application to which chapter 9, part 7 applies.
(2) 	A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application.
(3) 	However, the submitter may only appeal against a referral agency’s response to the extent it relates to—
(a) 	if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or
(b) 	if the prescribed concurrence agency is the chief executive (fisheries)—development that is—
(i) 	a material change of use of premises for aquaculture; or
(ii) 	operational work that is the removal, damage or destruction of a marine plant.
(4) 	Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment—
(a) 	a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries);
(b) 	a referral agency’s response mentioned in subsection (2).

464 	Appeals by advice agency submitters
(1) 	Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission.
(2) 	The advice agency may, within the limits of its jurisdiction, appeal to the court about—
(a) 	any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	any part of the approval relating to the assessment manager’s decision under section 327.
(3) 	The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter.
(4) 	However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision.

465 	Appeals about decisions relating to extensions for approvals
(1) 	For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.
(3) 	Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

467 	Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency
(1) 	A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.

[word/footer1.xml]
Page 11 of 11

[word/footer2.xml]
Page 1 of 11
	
		
						PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au

[word/header1.xml]
OPW15/0099

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
112 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

OPW15_0099 Decision Notice.docx · 112 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.