Skip to the record
Accept no substitutions.

Council archive · source document

Approved Decision Notice - DBW23/0128 [As Published]

of 7

Text shows just the words. Original shows the document exactly as it was published.

                      Site Access and Driveways
               11.    Driveway crossovers must be constructed in accordance with Council’s Standard Drawings
                      RS-049, RS-050 and any associated addendum.
               12.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
                      Stormwater Drainage
               13.    Stormwater runoff from the development must be discharged to a lawful point of discharge
                      and/or disposed of on-site without causing scour or damage to the subject site or any
                      adjoining property.
               14.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               15.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g., by blocking or interfering with natural overland flows).
               16.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Earthworks and Retaining Walls
               17.    All earthworks and associated retaining structures/batters, both above and below ground
                      level, both temporary and permanent, must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council. All
                      earthworks must be undertaken in accordance with the provisions of Australian Standard
                      AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
               18.    Contiguous piling forming a solid structure must not be constructed within the revised Erosion
                      Prone Area of 92 metres.
               19.    Detailed design of piling and foundations of the residence must consider the specific subsoil
                      conditions of the site and must consider failure mechanisms associated with the revised
                      Erosion Prone Area of 92 metres, excluding any contiguous piling.
                      Erosion and Sediment Control
               20.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               21.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      a.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      b.      Been revised to address predicted rainfall events, and
                      c.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.



                                                                                                        Page 3 of 7
Document Set ID: 23224152
Version: 4, Version Date: 05/09/2024
Log in to download the original file

Approved Decision Notice - DBW23_0128 [As Published].pdf · 157 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.