water quality code
Performance Outcomes Acceptable Outcomes
Stormwater drainage infrastructure is planned, designed and Stormwater drainage planning, design and construction is in
constructed to: accordance with PSP6 Engineering Design Standards Roads,
(a) incorporate allowance for increased flood risk and tidal drainage and earthworks and the latest version of the
inundation through pipework as a result of cilmate change Queensland Urban Drainage Design Manual.
and sea level rise; Able to Comply
(b) ensure the development is adequately drained; and AO2.2
The stormwater drainage system connects to a lawful point of
(c) ensure stormwater is managed and lawfully discharged discharge in accordance with PSP6 Engineering Design
without altering stormwater drainage characteristics
external to the site. Standards Roads, drainage and earthworks.
Able to Comply - water continues to
AO2.3 flow to creek (legal point of discharge)
Stormwater flows discharging from the development are
demonstrated to be consistent with predevelopment
characteristics.
Able to Comply - water continues to
flow to creek (legal point of discharge)
AO2.4
Development provides for the management of stormwater to
incorporate appropriate allowance for climate change impacts
(including rainfall intensity and sea level rise), in accordance with
PSP6 Engineering Design Standards – Roads, Drainage and
Earthworks. Able to Comply - water continues to
flow to creek (legal point of discharge)
PO3 AO3.1
Stormwater drainage infrastructure conveys runoff in a manner Stormwater drainage infrastructure meets the desired standards
that allows roads to deliver desired standards of service of service for roads functionality set out in PSP6 Engineering
appropriate to the local conditions and local stormwater drainage Design Standards Roads, Drainage and Earthworks.
characteristics. Able to Comply - no impacts to roads
PO4 AO4.1
Stormwater infrastructure is compatible with existing The location, design and construction of stormwater drainage
infrastructure, allows for easy access for the ongoing structures is in accordance with PSP6 Engineering Design
maintenance by Council, is cost effective across its design life. Standards Roads, drainage and earthworks.
Able to Comply
AO4.2
Where infrastructure is located on private land an easement is
dedicated over the infrastructure in accordance with PSP6
Engineering Design Standards Roads, drainage and
earthworks.
Not Applicable - related to new infrastructure
AO4.3
Any alterations or repairs to infrastructure as a result of the
development are made at no cost to Council.
Not Applicable - related to new infrastructure
AO4.4
Development avoids stormwater inflow and infiltration to the
sewer infrastructure network.
Not Applicable - Drains away from sewer
AO4.5
Stormwater infrastructure is designed to minimise maintenance
costs and the requirement for specialized equipment for
maintenance techniques.
Not Applicable - related to new infrastructure
PO5 AO5.1
Stormwater drainage infrastructure is aligned to avoid crossing Stormwater drainage infrastructure avoids crossing waterways,
waterways, wetlands, drainage lines and ecological important wetlands drainage lines and ecologically important areas or
areas, or where it is demonstrated this is unavoidable, disturbed follows the edge of existing disturbed areas.
areas are reinstated and revegetated upon completion of works.
Able to Comply
NOOSA PLAN 2020 AMENDED AT 25 SEPTEMBER 2020 Page 2 of 7