Council archive · source document
Negotiated Decision Notice - 010.2008.00000811.001 [As Published] · 132008.811
Officer: Glen Conforti
Direct Telephone: (07) 5449 5379
Response Address: PO Box 141, Tewantin QLD 4565
Email: [email protected]
Our Reference: 2008/811
Your Reference: 00977 LO1 NG
19 November 2008
Michael Ferris
CARE Martoo Consulting Pty Ltd
PO Box 1684
NOOSA HEADS QLD 4567
Dear Sir
Negotiated Decision Notice
Integrated Planning Act 1997
I refer to your application and the representations you made in respect to the Decision Notice. On 19
November 2008 Council decided your representations.
Details of the negotiated decision are as follows:
1 APPLICATION DETAILS
Application No: 2008/811
Street address: 8 Noosa Parade, Noosa Heads
Real property Lot 3 N 21841
description:
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
Council on 25 August 2008 decided to issue the following type of approval:-
Development Permit for Material Change of Use - Detached House
In relation to representations, Council on 19 November 2008 decided to:
A. Agree to change Condition 1
B. Agree to delete Condition 2
C. Issue a Negotiated Decision Notice
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are numbered, titled and dated:
1 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 6 pages
Page 2
2008/811
Plan / Rev. Plan / Document Name Date
Document No.
0719 1.2 TP07 Floor Plan - Ground Floor – SBT 3 September 2008
Designs
0719 1.3 TP06 Floor Plan - First Floor – SBT Designs 4 July 2008
0719 1.4 TP06 Site Cover Plan - GF & Site Cover Plan 4 July 2008
– FF – SBT Designs
0719 2.1 TP07 Eastern Elevation & Northern Elevation 3 September 2008
– SBT Designs
0719 2.2 TP07 Western Elevation & Southern 3 September 2008
Elevation – SBT Designs
6567-D-1 A Detail Survey – LAU Surveys 14 July 2008
and as may be amended by these conditions and annotations on the plans.
2. Deleted.
3. The existing Pandanus tectorius located at the southwest corner of the site shall be
maintained onsite, with protective measures installed to ensure protection during construction.
4. Security in the form of a cash bond or trading bank guarantee to the sum of $3000.00 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for building works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
5. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
6. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to
service the detached house. The tank is to be installed to ensure water from the tank can be
used both:
6.1 For external use such as watering gardens, irrigation, ornamental ponds or water
features, topping up swimming pools, outdoor cleaning; and
6.2 For use in flushing of toilets internal to the building.
7. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
8. The building height shall not exceed 8.0 metres above natural ground level.
9. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:-
9.1 Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
minimum of 10 metres between edges of heaps.
9.2 Disposal for firewood.
9.3 Disposal for landscaping purposes.
9.4 Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
9.5 The Applicant is advised that other methods may be considered provided full details of
the method are submitted.
2 of 7
Page 3
2008/811
9.6 The applicant is advised that burning off is an unacceptable method of disposal.
10. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
not constructed under overhead electricity transmission lines, or within any easements.
11. Sediment and erosion control measures must be in place prior to building works. If such
measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines
can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways.
Currency
12. The Development Permit for a material change of use lapses if the use has not happened by
25 August 2012, unless an application to extend the currency is approved by Council.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
0719 1.2 TP07 Floor Plan - Ground Floor – SBT 3 September 2008
Designs
0719 1.3 TP06 Floor Plan - First Floor – SBT Designs 4 July 2008
0719 1.4 TP06 Site Cover Plan - GF & Site Cover Plan 4 July 2008
– FF – SBT Designs
0719 2.1 TP07 Eastern Elevation & Northern Elevation 3 September 2008
– SBT Designs
0719 2.2 TP07 Western Elevation & Southern 3 September 2008
Elevation – SBT Designs
6567-D-1 A Detail Survey – LAU Surveys 14 July 2008
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
1.1. On a Sunday or public holiday, at any time; or
1.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
2. Prior to the commencement of the development, a plumbing assessment must be obtained
from Noosa Council’s Plumbing Services Section in accordance with the Plumbing & Drainage
Act 2002 (as applicable).
3 of 7
Page 4
2008/811
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Subject of the required Development Permit
required
Development Permit for Building All Building Works including Demolition and/or Removal of a
Works Building
11 SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Detached House Driveways Code
12 SUBMISSIONS
Not applicable
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable
14 RIGHTS OF APPEAL
You have continuing appeal rights in respect of Council’s decision on your application. Refer Section
4.1.27. of the Integrated Planning Act 1997.
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision, electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
4 of 7
Page 5
2008/811
DECISION NOTICE HISTORY
Original Decision Notice issued 25 August
2008.
Negotiated Decision Notice issued 19
November 2008 with amendment to Condition
1.
Yours faithfully,
Denis Wallace
PLANNING OFFICER
5 of 7
Page 6
2008/811
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated (6) If an application involves assessment against a
Planning Act (Chapter 4). concurrence agency code, appeal rights for submitters
for the application are not available against the part of
Division 8 - Appeals to court relating to the approval that represents the concurrence agency’s
development applications response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application may 4.1.29.(1) An advice agency may, within the limits of its
appeal to the court against any of the following- jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development development approval for a development application if-
application; (a) the development application involves impact
(b) a matter stated in a development approval, including any assessment; and
condition applying to the development, and the (b) the advice agency told the applicant and the
identification of a code under section 3.1.6;1 assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a currency period; days after the day the decision notice or negotiated
(e) a deemed refusal. decision notice is given to the advice agency as a
submitter.
(2) An appeal under subsection (1)(a) to (d) must be
started within 20 business days (the “applicant’s appeal Appeals for matters arising after approval given
period”) after the day the decision notice or negotiated (co-respondents)
decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
(3) An appeal under subsection (1)(e) may be started at development application, a person to whom any of the
any time after the last day a decision on the matter should following notices have been given may appeal to the
have been made. court against the decision in the notice-
Appeals by submitters (a) a notice giving a decision on a request for extension
4.1.28.(1) A submitter for a development application may of the currency period for an approval;
appeal to the court about- (b) a notice giving a decision on a request to make a
(a) the giving of a development approval, including any minor change to an approval.
conditions (or lack of conditions) or other provisions (2) The appeal must be started within 20 business
of the approval; or days after the day the notice of the decision is given to
(b) the length of a currency period for the approval. the person.
(2) The appeal must be started within 20 business (3) Subsection (1)(a) does not apply if the approval
days (the “submitters appeal period”) after the day the resulted from a development application (superseded
decision notice or negotiated decision notice is given to planning scheme) that was assessed as if it were an
the submitter. application under a superseded planning scheme.
(3) If a person withdraws a submission before the (4) Also, a person who has made a request
application is decided, the person may not appeal the mentioned in subsection (1) may appeal to the court
decision. against a deemed refusal of the request.
(4) If an application involves both impact assessment (5) An appeal under subsection (4) may be started at
and code assessment, appeal rights for submitters are any time after the last day the decision on the matter
available only for the part of the application involving should have been made.
impact assessment.
Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the application (no co-respondents)
are available only for the aspects of the development that
would have required public notification under the 4.1.31.(1) A person to whom any of the following notices
repealed Act. have been given may appeal to the court against the
decision in the notice-
(a) a notice giving a decision on a request to change or
cancel a condition of a development approval.
1
Section 3.1.6 (Preliminary approval may override local
planning instrument)
6 of 7
Page 7
2008/811
(b) a notice under section 6.1.442 giving a decision to (c) the decision to give a preliminary approval when a
change or cancel a condition of a development development permit was applied for;
approval. (d) the length of a period mentioned in section 3.5.21
(2) The appeal must be started within 20 business currency period;
days after the day the notice of the decision is (e) a deemed refusal.
given to the person.
(2) An appeal under subsection (1)(a) to (d) must be
(3) Also, a person who has made a request started within 20 business days (the “applicant’s appeal
mentioned in subsection (1)(a) may appeal to the period”) after the day the decision notice or negotiated
court against a deemed refusal of the request. decision notice is given to the applicant.
(4) An appeal under subsection (3) may be started at (3) An appeal under subsection (1)(e) may be started
any time after the last day the decision on the at any time after the last day a decision on the matter
matter should have been made. should have been made.
Appeals against decisions to change approval conditions The Registrar for the Building and Development
under the repealed Act Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court 4.1.36 Appeals about particular infrastructure
against- charges
(a) the decision; or (1) This section applies to a person who has been
(b) a deemed refusal of the application. given, and is dissatisfied with, an infrastructure charges
notice or a regulated State infrastructure charges notice.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of (2) The person may appeal to the court against the
the decision is to be given to the person. notice.
(3) An appeal under subsection (1)(b) may be started (3) The appeal must be started within 20 business days
at any time after the last day a decision on the matter after-
should have been made. (a) if the notice is given because of a development
Appeals against local laws approval or master plan approval-the day the
applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a approval; or
decision of a local government or the conditions applied
under a local law about the use of premises or the (b) otherwise-the day the notice is given to the person.
erection of a building or other structure permitted by the (4) An appeal under this section may only be about-
planning scheme may appeal to the court against the (a) whether a charge in the notice is so unreasonable
decision or the conditions applied. that no reasonable relevant local government, State
(2) The appeal must be started within 20 business infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the have imposed it; or
applicant. (b) an error in the calculation of the charge.
For Building Works Only (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the under this section can not be about the methodology
Integrated Planning Act 1997 as follows: used to establish the charge in the relevant infrastructure
charges schedule or regulated State infrastructure
Division 3 – Appeals to tribunals relating to
charges schedule.
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-
(a) the refusal, or the refusal in part, of a development
application;
(b) a matter stated in a development approval, including
any condition applying to the development, and the
identification of a code under section 3.1.6;3
2
Section 6.1.44 (Conditions may be changed or cancelled
by assessment manager or concurrence agency in certain
circumstances)
3
Section 3.1.6 (Preliminary approval may override local
planning instrument)
7 of 7
Used in these records
Negotiated Decision Notice - 010.2008.00000811.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 57 KB (small file)
- File type
No other editions are linked here.