18. Preliminary written details of the anticipated construction period, anticipated traffic
impacts due to construction and measures to be undertaken to minimise interruption
to Hastings Street traffic flow, residents and businesses.
Land Development
Carparking
19. Demonstrate how vehicles can pass at the two internal 90 corners of the access
driveway. The vehicle paths and vehicles sizes shall be in accordance with AS/NZS
2890.1:2004.
20. Demonstrate how vehicles parked in proposed spaces 8 & 15 can reverse from the
space and exit the aisle in a forward gear in a total of 2 movements.
21. Demonstrate how vehicles can manoeuvre and exit the site in a forward gear if the
security gate is closed and all of spaces 1-2 and 9-15 are occupied. The manoeuvring
must be in a total of 3 movements (forward gear entry, reverse and forward gear exit).
22. Demonstrate how a motorbike parked in the rear isolated parking space of the four
can exit the space when all spaces are occupied.
Site/building stability
23. Please provide comment from a suitably qualified geotechnical/structural engineer
with regard to the site location and the possible affects of wave action and water
inundation in a major storm event.
Sewer
24. It is noted that a Council sewer main traverses the development site. The
development plans show buildings located over the sewer. Provide plans showing
buildings designed clear of the Council sewer within the development site, or a
diversion of the sewer. A sewer diversion will require plans and longitudinal sections
of the diverted sewer, the relationship to the proposed building and an easement over
the sewer in accordance with the Noosa Plan - Planning Scheme Policy No. 6.
Please note that No buildings or structures are permitted to be located within a sewer
easement.
Stormwater
25. There is a discrepancy between the architectural plans and the stormwater
management plans with regard to the location and extent of the retention and
detention tanks. Please provide consistent plans.
Works
26. Confirm that separate male & female shower / change facilities and lockers will be
provided for staff.
27. Demonstrate that the ramped public access path along the western boundary is
compliant with the Disability Discrimination Act.
28. Demonstrate that the Bicycle parking spaces comply with AUSTROADS Guide to
Traffic Engineering Practice, Part 14 – Bicycles, Section 10 and provide details of the
proposed security category level to be provided.
Building
29. A report addressing Probable Solutions S1.1 to S1.6 if the Building Removal,
Relocation & Demolition Code.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Request for Further Information - 010.2008.00001787.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 24 KB (small file)
- File type
No other editions are linked here.