                              amenity of the neighbourhood by reason of the creation of excessive noise, lighting,
                              air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
                              other emissions in accordance with the nuisance provisions of the Environmental
                              Protection Act 1994.
                              Waste Management
               39. (c)        Adequate area must be provided on-site for the collection and separate storage of
                              recyclable, non-recyclable, vegetative and hazardous materials in their specific waste
                              streams during removal or demolition works.
               39. (d)        All waste materials must be removed from the site to avoid causing unhealthy
                              conditions, with the site left clean, tidy and free from any debris.
               39. (e)        Where a development permit has not been issued for the future use of the site, hard
                              surfaced areas including concrete slabs must be removed and disturbed areas must
                              be revegetated in accordance with PSP2 Landscaping of the Noosa Plan 2020.
                              Alternatively, the site must be turfed within 20 business days of completing the removal
                              or demolition work.
                              Health and Safety
               39. (f)        All building materials containing asbestos, including asbestos cement sheeting or
                              roofing and lagging, are removed from the building prior to demolition or relocation.
               39. (g)        Removal of building materials containing asbestos must be undertaken by a licensed
                              asbestos removalist.
               39. (h)        Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                              requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                              Queensland (WHSQ) of licensed asbestos removal work at least five days before the
                              work commences. Notification must be made using Form 65: Notification of licensed
                              asbestos removal work, demolition work or emergency demolition.


               39. (i)        All building materials containing asbestos products are wrapped and disposed of in
                              accordance with the Public Health Regulation 2006 and the Environmental Protection
                              Regulation 2008 Note: Asbestos is a Regulated Waste. The Department of
                              Environment & Science licenses businesses that transport asbestos waste, and
                              landfills that accept this waste.
                              General
               39. (j)              Infrastructure including reticulated water, sewerage, stormwater, and electricity
                              must be protected from damage and made safe to the standard required by the
                              regulatory authority.
               39. (k)        Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                              bridges or roadways at the removal/demolition site must be repaired or reinstated to at
                              least pre-existing conditions.
                              Plumbing and Drainage
               39. (l)        It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                              demolition of a building, the existing sanitary drain upstream from the connection point
                              for a service provider’s sewerage system must be sealed water tight. This work is
                              deemed as notifiable Work and must be carried out by a suitably licenced plumber who
                              must submit an As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC
                              (Queensland Building Construction Commission) within 10 days of completing the
                              work.

                                                                                                         Page 6 of 7

Document Set ID: 24145124
Version: 4, Version Date: 29/10/2025

Used in these records

About this file

File size
1.2 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Report MCU23 0109 01, OPW23 0123.01 & RAL23 0017.01 (As Published).pdf · 1.2 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.